Study guide

2.4 Voltage Drop Calculations & Chapter 9 Conductor Properties

Minnesota Journeyman Electrician Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Minnesota Exam, Licensing & Electrical Law

1.1 Exam Format, Provided References, Scoring & Scheduling 1.2 The Minnesota Electrical Act, Board of Electricity & Code Adoption 1.3 Personal Licenses, Scope of Work & Electrical Contractors 1.4 Experience Credit, Registration, Reciprocity, Renewal & Continuing Education 1.5 Direct Supervision, Ratios & Licensing Exemptions 1.6 Electrical Permits, Inspections, Condemnation & Enforcement

2 Electrical Theory, Math & Power Calculations

2.1 Exam Math, Ohm's Law, Watt's Law & Series/Parallel Circuits 2.2 AC Fundamentals: Reactance, Impedance & Power Factor 2.3 Three-Phase Systems: Wye vs. Delta Calculations 2.4 Voltage Drop Calculations & Chapter 9 Conductor Properties 2.5 Transformer Ratios, Connections, Taps & Available Fault Current 2.6 Motor Connections, Control Circuits & Troubleshooting

3 NEC Structure & General Requirements

3.1 Navigating the 2026 NEC: Article 90, Code Structure & Article 100 Definitions 3.2 NEC Article 110: Working Clearances, Dedicated Space & Termination Ratings 3.3 Over-1000-Volt Installations, Guarding & Manholes (Article 110, Parts III–V)

4 Conductors, Identification & Ampacity

4.1 Conductor Insulation Types, Copper vs. Aluminum & Table 310.16 Allowable Ampacities 4.2 Ampacity Derating: Ambient Temperature Correction & Raceway Bundling Adjustments 4.3 Conductor Identification, Splices & Parallel Conductors

5 Branch Circuits, GFCI/AFCI & Required Outlets

5.1 Branch Circuit Sizing, Overcurrent Ratings & Multiwire Branch Circuits 5.2 GFCI & AFCI Protection Requirements (NEC 210.8 & 210.12) 5.3 Dwelling Receptacle Outlets, Required Circuits & Lighting Outlets (NEC 210.11, 210.52, 210.63 & 210.70)

6 Load Calculations (2026 NEC Article 120)

6.1 Article 120 Basics: Dwelling Lighting, Small-Appliance & Laundry Loads 6.2 Dwelling Standard Method: Appliances, Dryers, Ranges, Heating, EVSE & Neutral 6.3 Optional Methods: Single Dwelling, Existing Dwelling & Multifamily (2026 NEC 120.82–120.85) 6.4 Commercial Lighting, Receptacle, Sign & Show-Window Loads (Table 120.42(A) & 120.44) 6.5 Commercial Kitchens, Schools & Restaurants (2026 NEC 120.56, 120.86 & 120.88) 6.6 Farm Load Calculations (2026 NEC 120.102 & 120.103) 6.7 Feeder & Service Neutral Sizing (2026 NEC 120.61)

7 Feeders, Outside Wiring & Services

7.1 Feeder Design & Sizing Requirements (NEC Article 215) 7.2 Outside Feeders & Separate Buildings (Article 225 & 250.32) 7.3 Service Clearances, Overhead Drops & Underground Service Laterals 7.4 Service Equipment, Disconnecting Means, Surge Protection & GFPE (2026 NEC Article 230)

8 Overcurrent Protection

8.1 Overcurrent Protective Devices: Fuses, Breakers & Standard Ampere Ratings 8.2 Conductor Overcurrent Protection & Feeder Tap Rules (NEC 240.4 & 240.21) 8.3 OCPD Location, Breaker Voltage Ratings, Handle Ties & Arc Energy Reduction

9 System Grounding & Grounding Electrodes

9.1 Grounding vs. Bonding Principles & System Grounding (NEC Article 250 Parts I-II) 9.2 Grounding Electrode System: Permitted Electrodes & Installation (NEC 250.50 & 250.52) 9.3 Grounding Electrode Conductor (GEC) Sizing & Protection (NEC Table 250.66) 9.4 Main Bonding Jumper, System Bonding Jumper & Separately Derived Systems

10 Bonding & Equipment Grounding

10.1 Equipment Grounding Conductor (EGC) Types, Identification & Sizing (NEC Table 250.122) 10.2 Proportional Upsizing of EGC for Voltage Drop (NEC 250.122(B)) 10.3 Bonding of Interior Metal Piping, Structural Steel & Other Systems (NEC 250.104) 10.4 Bonding Methods, Equipment Requiring Grounding & Receptacle Grounding

11 General Wiring Methods & Underground Installations

11.1 General Wiring Methods & Mechanical Protection (NEC Article 300) 11.2 Underground Wiring Cover Requirements (NEC Table 300.7) 11.3 Securing & Supporting, Plenums, Firestopping & Raceway Installation (Article 300)

12 Raceways, Cables & Conduit Fill

12.1 Metal (RMC, IMC, EMT) & Nonmetallic (PVC, RTRC, LFNC) Raceways 12.2 Flexible Conduits, ENT, Wireways, Auxiliary Gutters & Surface Raceways 12.3 Busways & Cable Tray Systems (Articles 368 & 392) 12.4 Cable Assemblies (NM, UF, MC) & Minnesota Cold-Weather Installation Rules 12.5 Conduit & Tubing Fill Calculations (Chapter 9 & Annex C)

13 Boxes, Conduit Bodies & Cabinets

13.1 Box Installation, Support, Accessibility & Luminaire and Fan Boxes (Article 314) 13.2 Outlet, Switch & Junction Box Fill Calculations (NEC 314.16) 13.3 Pull and Junction Box Sizing for Conductors 4 AWG & Larger (NEC 314.28) 13.4 Cabinets, Cutout Boxes & Wire Bending Space (NEC Article 312)

14 Cords, Wiring Devices, Panelboards, Luminaires & Appliances

14.1 Flexible Cords, Flexible Cables & Fixture Wires (Articles 400 & 402) 14.2 Switches, Receptacles & Wiring Devices (Articles 404 & 406) 14.3 Panelboards, Switchboards & Switchgear (NEC Article 408) 14.4 Luminaires, Lampholders, Lighting Track & Low-Voltage Lighting (Articles 410 & 411) 14.5 Appliances, Fixed Electric Space Heating & Deicing Equipment (Articles 422, 424 & 426)

15 Motors, Controllers & Air Conditioning

15.1 Motor Full-Load Current Determination & Conductor Sizing (NEC 430.6 & 430.22) 15.2 Motor Branch-Circuit Short-Circuit & Ground-Fault Protection (NEC Table 430.52) 15.3 Motor Overload Protection & Feeder Calculations for Multiple Motors (NEC 430.32 & 430.24) 15.4 Motor Controllers, Disconnecting Means, Drives & Motor Control Centers (Article 430 Parts VII–XI) 15.5 Air Conditioning & Refrigeration Equipment (NEC Article 440)

16 Transformers, Generators & Equipment Over 1000 Volts

16.1 Transformer Overcurrent Protection & Sizing (NEC Article 450) 16.2 Generators & Transfer Switches (NEC Article 445) 16.3 Capacitors, Transformers Over 1000 V & Medium-Voltage Equipment (Articles 460, 450 & 495)

17 Hazardous (Classified) Locations

17.1 Hazardous (Classified) Locations: Classes, Divisions & Zones (NEC Articles 500-506) 17.2 Class I Locations: Wiring Methods & Conduit Seal-Offs (NEC Article 501) 17.3 Class II & Class III Locations and the Zone System (Articles 502, 503, 505 & 506) 17.4 Commercial Garages & Motor Fuel Dispensing Facilities (NEC Articles 511 & 514) 17.5 Spray Areas, Aircraft Hangars, Hazardous-Location Bonding & Intrinsic Safety (Articles 500, 504, 513 & 516)

18 Health Care, Assembly, Agricultural & Mobile Occupancies

18.1 Health Care Facilities: Patient Care Spaces & Redundant Grounding (NEC Article 517) 18.2 Places of Assembly, Carnivals & Fairs, and Temporary Installations (Articles 518, 525 & 590) 18.3 Agricultural Buildings, Equipotential Planes & Farm Distribution Points (Article 547) 18.4 Mobile & Manufactured Homes, RV Parks, and Marinas & Docks (Articles 550, 551 & 555)

19 Signs, Elevators, Pools, Solar & Other Specific Equipment

19.1 Signs & Outline Lighting, Office Partitions, IT Rooms & Irrigation Machines (Articles 600, 605, 645 & 675) 19.2 Elevators, Escalators & Platform Lifts (Article 620) 19.3 Swimming Pools, Spas & Water Features: Equipotential Bonding & GFCI (NEC Article 680) 19.4 Spas, Hot Tubs, Hydromassage Bathtubs, Fountains & Natural Bodies of Water (Article 680 Parts IV–VII & Article 682) 19.5 Solar Photovoltaic Systems (Article 690) 19.6 Small Wind Systems, Fire Pumps & Electric Vehicle Charging (Articles 694, 695 & 625)

20 Emergency, Standby & Interconnected Power Sources

20.1 Emergency Systems vs. Legally Required vs. Optional Standby (NEC Articles 700, 701, 702) 20.2 Interconnected Power Sources, Energy Storage & Power Control Systems (Articles 705, 706, 480 & 130)

21 Limited-Energy, Fire Alarm & Communications Systems

21.1 Remote-Control, Signaling & Power-Limited Circuits: Class 1, 2 & 3 (2026 Articles 206, 720–725) 21.2 Class 4 Fault-Managed Power, Tray Cables, Fire-Resistive Cable Systems & Limited-Energy Grounding (Articles 726, 727, 742, 750 & 772) 21.3 Fire Alarm Systems: NPLFA vs. PLFA Wiring & Overcurrent Protection (NEC Article 760) 21.4 Optical Fiber Cables & Communications Systems Entering Buildings (2026 Articles 720–723, 800, 810, 820)

2.4 Voltage Drop Calculations & Chapter 9 Conductor Properties

Key Takeaways Explain This Topic AI

Informational Notes in NEC 210.19 and 215.2 recommend no more than 3% voltage drop on a branch circuit or feeder and no more than 5% total; DLI's exam guide states the same recommendation.

Single-phase voltage drop is V D = 2 × K × I × L CM V_D = \frac{2 \times K \times I \times L}{\text{CM}} V D ​ = CM 2 × K × I × L ​ ; DLI's worked examples use K = 12.8 K = 12.8 K = 12.8 for copper and K = 21.1 K = 21.1 K = 21.1 for aluminum, while many references use 12.9 and 21.2.

Three-phase balanced voltage drop replaces the multiplier of 2 with 3 \sqrt{3} 3 ​ : V drop ( 3 ϕ ) = 3 × K × I × L CM ≈ 1.732 × K × I × L CM V_{\text{drop}(3\phi)} = \frac{\sqrt{3} \times K \times I \times L}{\text{CM}} \approx \frac{1.732 \times K \times I \times L}{\text{CM}} V drop ( 3 ϕ ) ​ = CM 3 ​ × K × I × L ​ ≈ CM 1.732 × K × I × L ​ .

Rearranging formulas solves for required conductor cross-sectional area: CM = 2 × K × I × L V drop \text{CM} = \frac{2 \times K \times I \times L}{V_{\text{drop}}} CM = V drop ​ 2 × K × I × L ​ for single-phase and CM = 3 × K × I × L V drop \text{CM} = \frac{\sqrt{3} \times K \times I \times L}{V_{\text{drop}}} CM = V drop ​ 3 ​ × K × I × L ​ for three-phase, with wire gauge cross-referenced in NEC Chapter 9 Table 8.

Under NEC 250.122(B), whenever ungrounded conductors are increased in size for voltage drop, equipment grounding conductors must be increased proportionately in circular mil area.

Last updated: October 2026

2.4 Voltage Drop Calculations & Chapter 9 Conductor Properties

Electrical conductors are manufactured from materials with low, but finite, electrical resistance. As load current flows through feeder and branch conductors, energy is converted into heat, creating a potential loss along the length of the run known as voltage drop . If unmitigated over long distances, voltage drop deprives utilization equipment of rated operating potential, resulting in motor overheating, nuisance tripping of electronic drives, diminished lighting lumen output, and excessive energy consumption.

NEC Voltage Drop Recommendations vs. Mandatory Code

Understanding the legal status of voltage drop in the National Electrical Code is critical for the licensing examination:

Informational Note Status: The primary NEC guidelines on voltage drop appear in Informational Notes :

Informational Note to NEC 210.19: Recommends branch-circuit conductors sized to limit voltage drop to 3% at the farthest outlet of power, heating, and lighting loads.

Informational Note to NEC 215.2: Recommends feeder conductors sized to limit voltage drop to 3% .

Total Overall System Limit: Combined feeder and branch circuit voltage drop should not exceed 5% from the service equipment to the final utilization point.

Code Rule: Under NEC 90.5(C), Informational Notes are non-mandatory and unenforceable unless specifically adopted into state/local municipal amendments or specified in project engineering criteria.

Mandatory NEC Voltage Drop Requirements: In select critical applications, the NEC makes voltage drop compliance mandatory:

Fire Pumps (NEC 695.7): Voltage drop must not exceed 15% under motor starting conditions, and must not exceed 5% under normal full-load operating conditions.

Sensitive Electronic Equipment (NEC 647.4(D)): Limits total voltage drop to 1.5% for branch circuits and 2.5% total.

Voltage Drop Limits for Standard Nominal Voltages

Nominal System Voltage Maximum 3% Drop (Branch / Feeder) Minimum Operating Potential at 3% Maximum 5% Drop (Total System) Minimum Operating Potential at 5%

120 V 120\text{ V} 120 V ( 1 ϕ 1\phi 1 ϕ ) 3.60 V 3.60\text{ V} 3.60 V 116.40 V 116.40\text{ V} 116.40 V 6.00 V 6.00\text{ V} 6.00 V 114.00 V 114.00\text{ V} 114.00 V

208 V 208\text{ V} 208 V ( 3 ϕ 3\phi 3 ϕ ) 6.24 V 6.24\text{ V} 6.24 V 201.76 V 201.76\text{ V} 201.76 V 10.40 V 10.40\text{ V} 10.40 V 197.60 V 197.60\text{ V} 197.60 V

240 V 240\text{ V} 240 V ( 1 ϕ 1\phi 1 ϕ ) 7.20 V 7.20\text{ V} 7.20 V 232.80 V 232.80\text{ V} 232.80 V 12.00 V 12.00\text{ V} 12.00 V 228.00 V 228.00\text{ V} 228.00 V

277 V 277\text{ V} 277 V ( 1 ϕ 1\phi 1 ϕ ) 8.31 V 8.31\text{ V} 8.31 V 268.69 V 268.69\text{ V} 268.69 V 13.85 V 13.85\text{ V} 13.85 V 263.15 V 263.15\text{ V} 263.15 V

480 V 480\text{ V} 480 V ( 3 ϕ 3\phi 3 ϕ ) 14.40 V 14.40\text{ V} 14.40 V 465.60 V 465.60\text{ V} 465.60 V 24.00 V 24.00\text{ V} 24.00 V 456.00 V 456.00\text{ V} 456.00 V

The Circular Mil Method and Formulas

The standard method for calculating voltage drop on the Minnesota Journeyman examination utilizes the circular mil formula .

Definitions of Variables

V drop V_{\text{drop}} V drop ​ : Total circuit voltage drop in volts ( V \text{V} V ).

K K K (Specific Conductor Resistivity): The resistance of a conductor 1 circular mil 1\text{ circular mil} 1 circular mil in cross-sectional area and 1 foot 1\text{ foot} 1 foot long, often called ohms per mil-foot:

  • Copper: K ≈ 12.9 K \approx 12.9 K ≈ 12.9 (DLI's examples use 12.8 )
  • Aluminum: K ≈ 21.2 K \approx 21.2 K ≈ 21.2 (DLI's examples use 21.1 )

On the exam, use the K value the question gives. If none is given, results with 12.8 or 12.9 differ by less than 1%, so the answer choice is rarely affected.

I I I : Circuit design load current in amperes ( A \text{A} A ).

L L L : One-way length of the circuit run in feet ( ft \text{ft} ft ).

CM \text{CM} CM : Cross-sectional conductor area in circular mils (from NEC Chapter 9, Table 8).

Single-Phase Circuits

In a single-phase circuit, current flows out along the ungrounded conductor and returns along the neutral (or second ungrounded conductor), traversing twice the one-way circuit length. The factor of 2 2 2 accounts for both conductors:

V drop ( 1 ϕ ) = 2 × K × I × L CM V_{\text{drop}(1\phi)} = \frac{2 \times K \times I \times L}{\text{CM}} V drop ( 1 ϕ ) ​ = CM 2 × K × I × L ​

Three-Phase Balanced Circuits

In a balanced three-phase system, current returns through the remaining two phase conductors with a 120 ∘ 120^\circ 12 0 ∘ vector displacement. The single-phase factor of 2 2 2 is replaced by 3 ≈ 1.732 \sqrt{3} \approx 1.732 3 ​ ≈ 1.732 :

V drop ( 3 ϕ ) = 3 × K × I × L CM ≈ 1.732 × K × I × L CM V_{\text{drop}(3\phi)} = \frac{\sqrt{3} \times K \times I \times L}{\text{CM}} \approx \frac{1.732 \times K \times I \times L}{\text{CM}} V drop ( 3 ϕ ) ​ = CM 3 ​ × K × I × L ​ ≈ CM 1.732 × K × I × L ​

Sizing Conductors to Comply with Voltage Drop

To find the minimum conductor size required to stay within an allowable voltage drop limit ( V drop V_{\text{drop}} V drop ​ ), rearrange the formulas to solve for circular mils ( CM \text{CM} CM ):

CM ( 1 ϕ ) = 2 × K × I × L V drop \text{CM}_{(1\phi)} = \frac{2 \times K \times I \times L}{V_{\text{drop}}} CM ( 1 ϕ ) ​ = V drop ​ 2 × K × I × L ​ CM ( 3 ϕ ) = 3 × K × I × L V drop \text{CM}_{(3\phi)} = \frac{\sqrt{3} \times K \times I \times L}{V_{\text{drop}}} CM ( 3 ϕ ) ​ = V drop ​ 3 ​ × K × I × L ​

NEC Chapter 9 Table 8 Conductor Properties

Once the minimum required circular mil area is calculated, electricians refer to NEC Chapter 9 Table 8 (Conductor Properties) to select the next standard American Wire Gauge (AWG) or kcmil size with an area equal to or greater than the calculated value.

  • Conductor Size Area (cmil) Uncoated Copper, Stranded (Ω/1000 ft at 75°C) Aluminum (Ω/1000 ft at 75°C)
  • 14 AWG 4,110 3.14 (solid 3.07) 5.17
  • 12 AWG 6,530 1.98 (solid 1.93) 3.25
  • 10 AWG 10,380 1.24 (solid 1.21) 2.04
  • 8 AWG 16,510 0.778 (solid 0.764) 1.28
  • 6 AWG 26,240 0.491 0.808
  • 4 AWG 41,740 0.308 0.508
  • 3 AWG 52,620 0.245 0.403
  • 2 AWG 66,360 0.194 0.319
  • 1 AWG 83,690 0.154 0.253
  • 1/0 AWG 105,600 0.122 0.201
  • 2/0 AWG 133,100 0.0967 0.159
  • 3/0 AWG 167,800 0.0766 0.126
  • 4/0 AWG 211,600 0.0608 0.100
  • 250 kcmil 250,000 0.0515 0.0847

Table 8 gives direct-current resistance. For long feeders or inductive loads, NEC Chapter 9 Table 9 gives alternating-current resistance and reactance, but DLI's guide notes that its simplified formulas ignore skin effect, power factor, and harmonics. Each set of parallel conductors is treated as one conductor when calculating voltage drop.

DLI's worked voltage-drop examples

Single-phase, K method: 240 V, 150 ft, 28 A, No. 8 copper: V D = ( 2 × 12.8 × 28 × 150 ) ÷ 16,510 = 6.5 VD = (2 \times 12.8 \times 28 \times 150) \div 16{,}510 = 6.5 V D = ( 2 × 12.8 × 28 × 150 ) ÷ 16 , 510 = 6.5 V.

Three-phase, R method: 208 V, 205 ft, 33 A, conductors of 0.510 Ω per 1000 ft: V D = ( 1.732 × 0.510 × 33 × 205 ) ÷ 1000 = 5.98 VD = (1.732 \times 0.510 \times 33 \times 205) \div 1000 = 5.98 V D = ( 1.732 × 0.510 × 33 × 205 ) ÷ 1000 = 5.98 V.

Percent drop: 480 V three-phase feeder, 280 ft, 135 A, 250 kcmil aluminum: V D = ( 1.732 × 21.1 × 135 × 280 ) ÷ 250,000 = 5.53 VD = (1.732 \times 21.1 \times 135 \times 280) \div 250{,}000 = 5.53 V D = ( 1.732 × 21.1 × 135 × 280 ) ÷ 250 , 000 = 5.53 V, which is 5.53 ÷ 480 = 1.15 % 5.53 \div 480 = 1.15\% 5.53 ÷ 480 = 1.15% .

The Ohm's Law Table 8 Alternative Method

Instead of the circular mil formula, voltage drop can be verified directly using conductor resistance from Table 8:

R conductor = R table × ( L 1000 ft ) R_{\text{conductor}} = R_{\text{table}} \times \left(\frac{L}{1000\text{ ft}}\right) R conductor ​ = R table ​ × ( 1000 ft L ​ ) V drop ( 1 ϕ ) = 2 × I × R conductor V_{\text{drop}(1\phi)} = 2 \times I \times R_{\text{conductor}} V drop ( 1 ϕ ) ​ = 2 × I × R conductor ​ V drop ( 3 ϕ ) = 3 × I × R conductor V_{\text{drop}(3\phi)} = \sqrt{3} \times I \times R_{\text{conductor}} V drop ( 3 ϕ ) ​ = 3 ​ × I × R conductor ​

Mandatory Proportional Upsizing of EGC (NEC 250.122(B))

One of the most frequently tested provisions on the Minnesota Journeyman examination is NEC 250.122(B) :

"Where ungrounded conductors are increased in size from the minimum size that has sufficient ampacity for the intended installation, wire-type equipment grounding conductors, where installed, shall be increased in size proportionately according to the circular mil area of the ungrounded conductors."

Rationale for the Rule

When phase conductors are upsized to counteract voltage drop over long runs, conductor impedance decreases. If a phase-to-ground fault occurs at the end of that run, the circuit must maintain an equivalently low-impedance ground path to ensure sufficient fault current flows to rapidly trip the upstream overcurrent protective device. If the equipment grounding conductor (EGC) remained at its standard minimum size from Table 250.122, its relatively high resistance could limit ground-fault current or cause dangerous touch potential along metallic conduit enclosures.

Proportional Upsizing Formula

CM new EGC = CM orig EGC × ( CM upsized phase CM orig phase ) \text{CM}_{\text{new EGC}} = \text{CM}_{\text{orig EGC}} \times \left(\frac{\text{CM}_{\text{upsized phase}}}{\text{CM}_{\text{orig phase}}}\right) CM new EGC ​ = CM orig EGC ​ × ( CM orig phase ​ CM upsized phase ​ ​ )

Step-by-Step EGC Sizing Walkthrough

A 100 A 100\text{ A} 100 A single-phase feeder protected by a 100 A 100\text{ A} 100 A circuit breaker runs 350 ft 350\text{ ft} 350 ft from a main service to a subpanel. The calculated load current is 80 A 80\text{ A} 80 A at 240 V 240\text{ V} 240 V . Copper conductors with 75 ∘ C 75^\circ\text{C} 7 5 ∘ C THHN insulation are specified.

Determine Original Minimum Sizes:

Per NEC Table 310.16 ( 75 ∘ C 75^\circ\text{C} 7 5 ∘ C ), a 100 A 100\text{ A} 100 A breaker requires a minimum 3 AWG copper ungrounded conductor ( 52 , 620 cmil 52,620\text{ cmil} 52 , 620 cmil , rated at 100 A 100\text{ A} 100 A ).

Per NEC Table 250.122, a 100 A 100\text{ A} 100 A overcurrent device requires a minimum 8 AWG copper equipment grounding conductor ( 16 , 510 cmil 16,510\text{ cmil} 16 , 510 cmil ).

Calculate Maximum Allowable Voltage Drop (3% Feeder Limit): V drop(max) = 240 V × 0.03 = 7.20 V V_{\text{drop(max)}} = 240\text{ V} \times 0.03 = 7.20\text{ V} V drop(max) ​ = 240 V × 0.03 = 7.20 V

Calculate Required Ungrounded Conductor Area: CM = 2 × K × I × L V drop = 2 × 12.9 × 80 A × 350 ft 7.20 V = 722 , 400 7.20 = 100 , 333 cmil \text{CM} = \frac{2 \times K \times I \times L}{V_{\text{drop}}} = \frac{2 \times 12.9 \times 80\text{ A} \times 350\text{ ft}}{7.20\text{ V}} = \frac{722,400}{7.20} = 100,333\text{ cmil} CM = V drop ​ 2 × K × I × L ​ = 7.20 V 2 × 12.9 × 80 A × 350 ft ​ = 7.20 722 , 400 ​ = 100 , 333 cmil

Select Upsized Ungrounded Conductor:

Consulting NEC Table 8: 1 AWG is 83 , 690 cmil 83,690\text{ cmil} 83 , 690 cmil (insufficient).

Select 1/0 AWG copper ( 105 , 600 cmil 105,600\text{ cmil} 105 , 600 cmil ).

Apply NEC 250.122(B) Proportional EGC Upsizing: Ratio = CM upsized CM original = 105 , 600 cmil 52 , 620 cmil ≈ 2.00684 \text{Ratio} = \frac{\text{CM}_{\text{upsized}}}{\text{CM}_{\text{original}}} = \frac{105,600\text{ cmil}}{52,620\text{ cmil}} \approx 2.00684 Ratio = CM original ​ CM upsized ​ ​ = 52 , 620 cmil 105 , 600 cmil ​ ≈ 2.00684 CM new EGC = 16 , 510 cmil × 2.00684 ≈ 33 , 133 cmil \text{CM}_{\text{new EGC}} = 16,510\text{ cmil} \times 2.00684 \approx 33,133\text{ cmil} CM new EGC ​ = 16 , 510 cmil × 2.00684 ≈ 33 , 133 cmil

Select Upsized EGC from Table 8:

6 AWG is 26 , 240 cmil 26,240\text{ cmil} 26 , 240 cmil (insufficient, less than 33 , 133 cmil 33,133\text{ cmil} 33 , 133 cmil ).

4 AWG copper ( 41 , 740 cmil 41,740\text{ cmil} 41 , 740 cmil ) is the next standard size.

Result: The ungrounded conductors must be upsized to 1/0 AWG , and the equipment grounding conductor must be upsized from 8 AWG to 4 AWG .

Conductor Sizing Summary Workflow

Step Action Code Reference

1. Continuous Load Sizing Calculate minimum ampacity at 125 % 125\% 125% continuous + 100 % + 100\% + 100% non-continuous NEC 210.19, 215.2

2. Table Selection Select base ungrounded conductor from allowable ampacity table NEC Table 310.16

3. Ambient & Bundling Apply temperature correction and raceway fill adjustment factors NEC 310.15(B), 310.15(C)

4. Voltage Drop Verification Calculate required circular mil area using 2 K I L / V drop 2 K I L / V_{\text{drop}} 2 K I L / V drop ​ or 3 K I L / V drop \sqrt{3} K I L / V_{\text{drop}} 3 ​ K I L / V drop ​ Informational Notes in NEC 210.19 and 215.2

5. EGC Adjustment If ungrounded conductors upsize, calculate new EGC area proportionally NEC 250.122(B)

6. Conduit Fill Check Size raceway based on upsized phase, neutral, and ground dimensions NEC Chapter 9 Tables 4 & 5