Study guide
6.1 Article 120 Basics: Dwelling Lighting, Small-Appliance & Laundry Loads
Minnesota Journeyman Electrician Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Minnesota Exam, Licensing & Electrical Law
1.1 Exam Format, Provided References, Scoring & Scheduling 1.2 The Minnesota Electrical Act, Board of Electricity & Code Adoption 1.3 Personal Licenses, Scope of Work & Electrical Contractors 1.4 Experience Credit, Registration, Reciprocity, Renewal & Continuing Education 1.5 Direct Supervision, Ratios & Licensing Exemptions 1.6 Electrical Permits, Inspections, Condemnation & Enforcement
2 Electrical Theory, Math & Power Calculations
2.1 Exam Math, Ohm's Law, Watt's Law & Series/Parallel Circuits 2.2 AC Fundamentals: Reactance, Impedance & Power Factor 2.3 Three-Phase Systems: Wye vs. Delta Calculations 2.4 Voltage Drop Calculations & Chapter 9 Conductor Properties 2.5 Transformer Ratios, Connections, Taps & Available Fault Current 2.6 Motor Connections, Control Circuits & Troubleshooting
3 NEC Structure & General Requirements
3.1 Navigating the 2026 NEC: Article 90, Code Structure & Article 100 Definitions 3.2 NEC Article 110: Working Clearances, Dedicated Space & Termination Ratings 3.3 Over-1000-Volt Installations, Guarding & Manholes (Article 110, Parts III–V)
4 Conductors, Identification & Ampacity
4.1 Conductor Insulation Types, Copper vs. Aluminum & Table 310.16 Allowable Ampacities 4.2 Ampacity Derating: Ambient Temperature Correction & Raceway Bundling Adjustments 4.3 Conductor Identification, Splices & Parallel Conductors
5 Branch Circuits, GFCI/AFCI & Required Outlets
5.1 Branch Circuit Sizing, Overcurrent Ratings & Multiwire Branch Circuits 5.2 GFCI & AFCI Protection Requirements (NEC 210.8 & 210.12) 5.3 Dwelling Receptacle Outlets, Required Circuits & Lighting Outlets (NEC 210.11, 210.52, 210.63 & 210.70)
6 Load Calculations (2026 NEC Article 120)
6.1 Article 120 Basics: Dwelling Lighting, Small-Appliance & Laundry Loads 6.2 Dwelling Standard Method: Appliances, Dryers, Ranges, Heating, EVSE & Neutral 6.3 Optional Methods: Single Dwelling, Existing Dwelling & Multifamily (2026 NEC 120.82–120.85) 6.4 Commercial Lighting, Receptacle, Sign & Show-Window Loads (Table 120.42(A) & 120.44) 6.5 Commercial Kitchens, Schools & Restaurants (2026 NEC 120.56, 120.86 & 120.88) 6.6 Farm Load Calculations (2026 NEC 120.102 & 120.103) 6.7 Feeder & Service Neutral Sizing (2026 NEC 120.61)
7 Feeders, Outside Wiring & Services
7.1 Feeder Design & Sizing Requirements (NEC Article 215) 7.2 Outside Feeders & Separate Buildings (Article 225 & 250.32) 7.3 Service Clearances, Overhead Drops & Underground Service Laterals 7.4 Service Equipment, Disconnecting Means, Surge Protection & GFPE (2026 NEC Article 230)
8 Overcurrent Protection
8.1 Overcurrent Protective Devices: Fuses, Breakers & Standard Ampere Ratings 8.2 Conductor Overcurrent Protection & Feeder Tap Rules (NEC 240.4 & 240.21) 8.3 OCPD Location, Breaker Voltage Ratings, Handle Ties & Arc Energy Reduction
9 System Grounding & Grounding Electrodes
9.1 Grounding vs. Bonding Principles & System Grounding (NEC Article 250 Parts I-II) 9.2 Grounding Electrode System: Permitted Electrodes & Installation (NEC 250.50 & 250.52) 9.3 Grounding Electrode Conductor (GEC) Sizing & Protection (NEC Table 250.66) 9.4 Main Bonding Jumper, System Bonding Jumper & Separately Derived Systems
10 Bonding & Equipment Grounding
10.1 Equipment Grounding Conductor (EGC) Types, Identification & Sizing (NEC Table 250.122) 10.2 Proportional Upsizing of EGC for Voltage Drop (NEC 250.122(B)) 10.3 Bonding of Interior Metal Piping, Structural Steel & Other Systems (NEC 250.104) 10.4 Bonding Methods, Equipment Requiring Grounding & Receptacle Grounding
11 General Wiring Methods & Underground Installations
11.1 General Wiring Methods & Mechanical Protection (NEC Article 300) 11.2 Underground Wiring Cover Requirements (NEC Table 300.7) 11.3 Securing & Supporting, Plenums, Firestopping & Raceway Installation (Article 300)
12 Raceways, Cables & Conduit Fill
12.1 Metal (RMC, IMC, EMT) & Nonmetallic (PVC, RTRC, LFNC) Raceways 12.2 Flexible Conduits, ENT, Wireways, Auxiliary Gutters & Surface Raceways 12.3 Busways & Cable Tray Systems (Articles 368 & 392) 12.4 Cable Assemblies (NM, UF, MC) & Minnesota Cold-Weather Installation Rules 12.5 Conduit & Tubing Fill Calculations (Chapter 9 & Annex C)
13 Boxes, Conduit Bodies & Cabinets
13.1 Box Installation, Support, Accessibility & Luminaire and Fan Boxes (Article 314) 13.2 Outlet, Switch & Junction Box Fill Calculations (NEC 314.16) 13.3 Pull and Junction Box Sizing for Conductors 4 AWG & Larger (NEC 314.28) 13.4 Cabinets, Cutout Boxes & Wire Bending Space (NEC Article 312)
14 Cords, Wiring Devices, Panelboards, Luminaires & Appliances
14.1 Flexible Cords, Flexible Cables & Fixture Wires (Articles 400 & 402) 14.2 Switches, Receptacles & Wiring Devices (Articles 404 & 406) 14.3 Panelboards, Switchboards & Switchgear (NEC Article 408) 14.4 Luminaires, Lampholders, Lighting Track & Low-Voltage Lighting (Articles 410 & 411) 14.5 Appliances, Fixed Electric Space Heating & Deicing Equipment (Articles 422, 424 & 426)
15 Motors, Controllers & Air Conditioning
15.1 Motor Full-Load Current Determination & Conductor Sizing (NEC 430.6 & 430.22) 15.2 Motor Branch-Circuit Short-Circuit & Ground-Fault Protection (NEC Table 430.52) 15.3 Motor Overload Protection & Feeder Calculations for Multiple Motors (NEC 430.32 & 430.24) 15.4 Motor Controllers, Disconnecting Means, Drives & Motor Control Centers (Article 430 Parts VII–XI) 15.5 Air Conditioning & Refrigeration Equipment (NEC Article 440)
16 Transformers, Generators & Equipment Over 1000 Volts
16.1 Transformer Overcurrent Protection & Sizing (NEC Article 450) 16.2 Generators & Transfer Switches (NEC Article 445) 16.3 Capacitors, Transformers Over 1000 V & Medium-Voltage Equipment (Articles 460, 450 & 495)
17 Hazardous (Classified) Locations
17.1 Hazardous (Classified) Locations: Classes, Divisions & Zones (NEC Articles 500-506) 17.2 Class I Locations: Wiring Methods & Conduit Seal-Offs (NEC Article 501) 17.3 Class II & Class III Locations and the Zone System (Articles 502, 503, 505 & 506) 17.4 Commercial Garages & Motor Fuel Dispensing Facilities (NEC Articles 511 & 514) 17.5 Spray Areas, Aircraft Hangars, Hazardous-Location Bonding & Intrinsic Safety (Articles 500, 504, 513 & 516)
18 Health Care, Assembly, Agricultural & Mobile Occupancies
18.1 Health Care Facilities: Patient Care Spaces & Redundant Grounding (NEC Article 517) 18.2 Places of Assembly, Carnivals & Fairs, and Temporary Installations (Articles 518, 525 & 590) 18.3 Agricultural Buildings, Equipotential Planes & Farm Distribution Points (Article 547) 18.4 Mobile & Manufactured Homes, RV Parks, and Marinas & Docks (Articles 550, 551 & 555)
19 Signs, Elevators, Pools, Solar & Other Specific Equipment
19.1 Signs & Outline Lighting, Office Partitions, IT Rooms & Irrigation Machines (Articles 600, 605, 645 & 675) 19.2 Elevators, Escalators & Platform Lifts (Article 620) 19.3 Swimming Pools, Spas & Water Features: Equipotential Bonding & GFCI (NEC Article 680) 19.4 Spas, Hot Tubs, Hydromassage Bathtubs, Fountains & Natural Bodies of Water (Article 680 Parts IV–VII & Article 682) 19.5 Solar Photovoltaic Systems (Article 690) 19.6 Small Wind Systems, Fire Pumps & Electric Vehicle Charging (Articles 694, 695 & 625)
20 Emergency, Standby & Interconnected Power Sources
20.1 Emergency Systems vs. Legally Required vs. Optional Standby (NEC Articles 700, 701, 702) 20.2 Interconnected Power Sources, Energy Storage & Power Control Systems (Articles 705, 706, 480 & 130)
21 Limited-Energy, Fire Alarm & Communications Systems
21.1 Remote-Control, Signaling & Power-Limited Circuits: Class 1, 2 & 3 (2026 Articles 206, 720–725) 21.2 Class 4 Fault-Managed Power, Tray Cables, Fire-Resistive Cable Systems & Limited-Energy Grounding (Articles 726, 727, 742, 750 & 772) 21.3 Fire Alarm Systems: NPLFA vs. PLFA Wiring & Overcurrent Protection (NEC Article 760) 21.4 Optical Fiber Cables & Communications Systems Entering Buildings (2026 Articles 720–723, 800, 810, 820)
6.1 Article 120 Basics: Dwelling Lighting, Small-Appliance & Laundry Loads
Key Takeaways Explain This Topic AI
The 2026 NEC 120.41 sets the dwelling general lighting load at 2 VA per square foot for feeder and service calculations, down from 3 VA per square foot in the 2023 edition.
Section 120.13 still uses 3 VA per square foot to determine how many general-purpose branch circuits a dwelling needs.
Each 2-wire small-appliance branch circuit and each laundry branch circuit adds 1,500 VA under 120.52.
Table 120.45 takes the first 3,000 VA of the combined dwelling lighting, small-appliance, and laundry load at 100%, the next 117,000 VA at 35%, and the remainder at 25%.
Section 120.5(E) states that load calculations do not apply the 125% continuous-load multiplier; that factor is applied when sizing conductors and overcurrent devices.
Last updated: October 2026
Where load calculations live now
The 2026 NEC relocated branch-circuit, feeder, and service load calculations from Article 220 to Article 120 in Chapter 1, because they apply to every installation. Section numbers mostly kept their old endings: 220.55 became 120.55 , 220.82 became 120.82 , and so on. DLI's exam guide refers candidates to Annex D of the NEC for worked examples of more complex calculations, so practice with the 2026 Annex D examples.
General rules (120.5)
Rule Requirement
Voltages (120.5(A)) Unless other voltages are specified, use nominal system voltages such as 120, 120/240, 208Y/120, 240, 480Y/277, and 480 V
Fractions of an ampere (120.5(B)) Round to the nearest whole ampere; fractions smaller than 0.5 may be dropped
Floor area (120.5(C)) Use the outside dimensions; for dwellings, exclude open porches, garages, and unused or unfinished spaces not adaptable for future use; the 2026 NEC also confirms that nonhabitable detached spaces such as detached garages are excluded
DC loads (120.5(D), new) For dc equipment, volt-amperes equal watts
Continuous loads (120.5(E), new) Load calculations do not apply the 125% continuous-load factor; that multiplier belongs to conductor and OCPD sizing rules such as 210.19, 215.2, and 230.42
Branch-circuit loads and circuit count
Section 120.13 , new in 2026, keeps the older 3 VA/ft² value for one purpose: determining the number of general-purpose branch circuits in a dwelling. Section 210.11(A) and (B) then require enough circuits to carry that load, evenly proportioned among multioutlet circuits.
Circuits = Area × 3 VA/ft 2 120 V × circuit rating \text{Circuits} = \frac{\text{Area} \times 3\ \text{VA/ft}^2}{120\ \text{V} \times \text{circuit rating}} Circuits = 120 V × circuit rating Area × 3 VA/ft 2
For a 2,400 ft² house: 2400 × 3 = 7200 2400 \times 3 = 7200 2400 × 3 = 7200 VA, and 7200 ÷ 120 = 60 7200 \div 120 = 60 7200 ÷ 120 = 60 A. That is four 15 A circuits ( 60 ÷ 15 60 \div 15 60 ÷ 15 ) or three 20 A circuits ( 60 ÷ 20 60 \div 20 60 ÷ 20 ), in addition to the required small-appliance, laundry, bathroom, and garage circuits.
Other branch-circuit loads under 120.14 include 180 VA per single or multiple receptacle on one yoke (in other than dwelling units), the nameplate rating of specific appliances, and 5,000 VA or the nameplate rating, whichever is larger, for each household electric clothes dryer.
Feeder and service general lighting load (120.41)
For one-family, two-family, and multifamily dwellings, the minimum unit load is 2 VA/ft² of floor area in the 2026 NEC, down from 3 VA/ft². DOE studies of modern LED lighting and receptacle use supported the change. The general-use receptacles and lighting outlets are included in this unit load, so you do not add 180 VA per receptacle in a dwelling.
Small-appliance and laundry loads (120.52)
Load Value Note
Small-appliance circuits (120.52(A)) 1,500 VA for each 2-wire small-appliance branch circuit required by 210.11(C)(1), at least two An individual 15 A or larger refrigerator circuit permitted by 210.52(B)(1) may be left out
Laundry circuit (120.52(B)) 1,500 VA for each 2-wire laundry branch circuit required by 210.11(C)(2), at least one —
Both loads may be added to the general lighting load and reduced together using Table 120.45 .
Lighting load demand factors (Table 120.45)
- Occupancy Portion of load Demand factor
- Dwelling units First 3,000 VA 100%
- 3,001 to 120,000 VA 35%
- Over 120,000 VA 25%
- Hotels and motels, including apartment houses without cooking provisions for tenants First 20,000 VA 50%
- 20,001 to 100,000 VA 40%
- Over 100,000 VA 30%
- Warehouses (storage) First 12,500 VA 100%
- Over 12,500 VA 50%
- All others Total VA 100%
- Worked example: 2,400 ft² dwelling
General lighting: 2400 × 2 = 4800 2400 \times 2 = 4800 2400 × 2 = 4800 VA.
Small-appliance circuits: 2 × 1500 = 3000 2 \times 1500 = 3000 2 × 1500 = 3000 VA.
Laundry circuit: 1500 1500 1500 VA.
Total before demand: 4800 + 3000 + 1500 = 9300 4800 + 3000 + 1500 = 9300 4800 + 3000 + 1500 = 9300 VA.
Table 120.45: first 3,000 VA at 100% = 3,000 VA ; remaining 9300 − 3000 = 6300 9300 - 3000 = 6300 9300 − 3000 = 6300 VA at 35% = 2,205 VA .
Net lighting, small-appliance, and laundry demand: 3000 + 2205 = 5205 3000 + 2205 = 5205 3000 + 2205 = 5205 VA.
Under the 2023 NEC the general lighting line would have been 2400 × 3 = 7200 2400 \times 3 = 7200 2400 × 3 = 7200 VA, giving a net demand of 6,045 VA. Be sure to use the 2026 value on the exam.
Common mistakes
Adding 180 VA per receptacle in a dwelling; dwelling general-use receptacles are included in the 2 VA/ft² unit load.
Counting the garage or an open porch in the floor area.
Forgetting the second small-appliance circuit: at least two are required, even in a small kitchen.
Applying Table 120.45 to fixed appliances , ranges, or dryers; those loads have their own rules in 120.53 to 120.55.
Warning