10.3 Radon Control Measures (Chapter 1303) & Indoor Air Quality
Minnesota General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Minnesota Licensing Statutes & DLI Regulatory Framework
1.1 Scope of Practice, License Types & DLI Administration 1.2 Qualifying Person Requirements & Continuing Education 1.3 Exemptions, Prohibited Acts & DLI Enforcement
2 Chapter 2: Minnesota Contract Law & Statutory Home Warranties
2.1 Essential Terms of Construction Contracts & Change Orders 2.2 Statutory Warranties under Minn. Stat. Chapter 327A 2.3 Insurance Deductible Rebates & Contractor Recovery Fund
3 Chapter 3: Minnesota Mechanics Lien Law (Minn. Stat. Chapter 514)
Section 3.1: Pre-Lien Notice Requirements for Prime & Subcontractors Section 3.2: Recording Mechanics Liens & The 120-Day Filing Deadline Section 3.3: Foreclosure Actions, Priority & Lien Waivers
4 Chapter 4: Business Management, Accounting & Taxes
4.1 Financial Statements, Cash vs. Accrual Accounting & Cash Flow 4.2 Minnesota Business Structures, State Taxes & Capital Improvements 4.3 Payroll Management, Prevailing Wage & Employer Tax Obligations
5 Chapter 5: Risk Management, Insurance & Surety Bonds
Section 5.1: Commercial General Liability & Workers' Compensation Insurance Section 5.2: Surety Bonds vs. Insurance (Bid, Performance & Payment Bonds) Section 5.3: Risk Assessment, Subcontractor Certificates & Indemnification
6 Chapter 6: Jobsite Safety & Minnesota OSHA Compliance
6.1 MN OSHA Regulations, Inspections & Employer Rights 6.2 Fall Protection, Scaffolding & Personal Protective Equipment 6.3 Trenching, Excavation, Hazard Communication & Silica Standards
7 Chapter 7: Minnesota State Building Code Administration & Permits
7.1 MN Rules Chapter 1300 (Administration, Permits & Plan Review) 7.2 Building Inspections, Code Violations & Certificates of Occupancy 7.4 Building Planning: Means of Egress, Stairways, Exit Doors & Garage Separation 7.5 Life Safety: Smoke Alarms, Safety Glazing, Natural Light, Ceiling Heights & Replacement Windows 7.3 Site Preparation, Surveying & Soil Bearing Capacity
8 Chapter 8: Foundations, Footings, Concrete & Masonry
8.1 Frost Depth Requirements, Soils & Footing Design 8.2 Foundation Wall Systems, Waterproofing & Damp-Proofing 8.3 Concrete Specifications, Reinforcement & Cold-Weather Concreting
9 Chapter 9: Wood Framing, Structural Systems & Load Requirements
9.1 Floor Systems, Girders & Joist Spanning 9.2 Wall Framing, Shear Walls & Structural Headers 9.3 Roof Framing, Trusses, Snow Load & Wind Load Design 9.4 Decks, Balconies, Stairs, Decay Protection & Wood Foundations
10 Chapter 10: Building Enclosure, Energy Code & Environmental Systems
10.1 Roofing Underlayment, Ice Dam Protection & Flashing Details 10.2 Insulation (R-Values), Vapor Retarders & MN Energy Code (Chapter 1322) 10.3 Radon Control Measures (Chapter 1303) & Indoor Air Quality 10.4 Exterior Finishes: House Wrap, Flashing, Siding, Stucco & Brick Veneer 10.5 Foam Plastic Insulation & Interior Finishes (Drywall) 10.6 Roof Covering Materials: Asphalt, Rolled Roofing & Wood Shingles/Shakes 10.7 Associated Issues: Electrical & Plumbing Awareness for Builders
10.3 Radon Control Measures (Chapter 1303) & Indoor Air Quality
Key Takeaways Explain This Topic AI
Minnesota Rules Chapter 1303.2400 mandates passive radon control systems in all newly constructed residential dwellings across the state of Minnesota.
Essential passive radon mitigation components include a 4-inch gas-permeable aggregate layer, a continuous 6-mil soil-gas retarder membrane, a 3-inch or 4-inch vertical PVC vent stack, and an attic electrical junction box.
Vertical radon vent pipes must be continuously labeled "Radon Vent Pipe" at least once per floor level and in the attic space to prevent unauthorized plumbing modifications.
The Minnesota Energy Code mandates continuous mechanical ventilation (HRVs/ERVs) to maintain indoor air quality in tight building envelopes.
Passive radon systems can be upgraded to active sub-slab depressurization systems by installing an inline fan in the attic junction box location if testing exceeds 4.0 pCi/L.
Last updated: July 2026
Radon Control Measures (Chapter 1303) & Indoor Air Quality
Radon is a colorless, odorless, naturally occurring radioactive gas produced by the radioactive decay of uranium in soil and rock. Because of Minnesota's unique glacial geology, the EPA classifies the majority of Minnesota counties as Zone 1 (High Radon Potential) , where average indoor radon levels exceed 4.0 picocuries per liter (pCi/L) . Radon inhalation is the leading cause of lung cancer among non-smokers in the United States. To mitigate this health risk, Minnesota Rules Chapter 1303.2400 mandates the installation of Passive Radon Control Systems in all new residential buildings constructed in Minnesota.
1. Passive Radon Control System Requirements (MN Rules Chapter 1303.2400)
A passive radon system relies on natural stack effect (buoyancy of warm air rising through the building envelope) to draw soil gas from beneath the concrete slab and exhaust it safely above the roofline without mechanical fans. PASSIVE RADON CONTROL SYSTEM SCHEMATIC
- Attic Vent Pipe Terminal (≥ 12" above roof, ≥ 10' from windows)
- ▲
- │
- ┌────────────────┴────────────────┐
- │ ATTIC SPACE │
- │ Unswitched 120V Junction Box │ ◄── For Future Active Fan
- │ Labeled "Radon Vent Pipe" │
- └────────────────┬────────────────┘
- │
- ┌────────────────┴────────────────┐
- │ LIVING SPACE / FIRST FLOOR │
- │ Vertical 3" or 4" PVC Pipe │ ◄── Routed through conditioned
- │ Labeled "Radon Vent Pipe" │ space to prevent freezing
- └────────────────┬────────────────┘
- │
- ┌────────────────┴────────────────┐
- │ BASEMENT / SLAB FLOOR │
- │ Concrete Slab Floor │
- ├─────────────────────────────────┤
- │ 6-mil Soil-Gas Retarder Poly │ ◄── Sealed at seams & sumps
- ├─────────────────────────────────┤
- │ 4" Clean Aggregate Layer │ ◄── PVC T-Fitting in stone
- └─────────────────────────────────┘
- Essential System Components & Specifications
The Minnesota Passive Radon Code mandates five interconnected structural components during initial framing and slab construction:
1. Gas-Permeable Layer (Sub-Slab Aggregate)
Before pouring the basement or slab-on-grade concrete floor, a continuous gas-permeable layer must be placed over the subgrade soil:
Clean Aggregate Option: A minimum 4-inch layer of clean aggregate consisting of crushed stone or gravel with 100% passing a 1.5-inch sieve and no more than 5% passing a 1/2-inch sieve.
Soil-Gas Collection Matting: Alternatively, an approved soil-gas collection matting or perforated drainage pipe loop laid in a sand bed may be substituted.
2. Soil-Gas Retarder Membrane
A continuous soil-gas retarder membrane must be laid directly over the gas-permeable aggregate layer before placing concrete:
Material Specification: Minimum 6-mil (0.006 inch) thick polyethylene sheeting (or approved 3-ply polyolefin).
Seams & Penetrations: Sheeting joints must overlap by at least 12 inches . All seams, perimeter edges against foundation walls, and pipe penetrations must be sealed with radon-resistant caulking or tape. Sump pit basins must be equipped with airtight sealed lids.
3. T-Fitting & Vertical Vent Stack
Extraction Point: A 3-inch or 4-inch PVC T-fitting must be embedded into the sub-slab aggregate layer and connected to a vertical riser.
Vent Pipe Sizing: The vertical vent pipe must be a minimum 3-inch diameter (or 4-inch diameter for large footprints) Schedule 40 PVC pipe.
Routing: The pipe must run vertically upward from the sub-slab through conditioned building spaces (walls, chases) into the attic and out through the roof. Routing through conditioned space keeps the pipe warm, strengthening the passive chimney draft effect and preventing interior condensation freezing inside the pipe during winter.
Roof Termination: The pipe must terminate vertically at least 12 inches above the roof surface , at least 10 feet away from any operable window or building air intake , and at least 2 feet above any window within a 10-foot radius.
4. Mandatory Pipe Identification & Labeling
To prevent plumbing contractors or homeowners from inadvertently cutting into the radon pipe or tying sewage drain vents into it:
High-Contrast Labels: The vent pipe must be clearly labeled reading "Radon Vent Pipe" in high-contrast lettering at least once on every floor level and within the attic space.
5. Electrical Junction Box Provision (Attic)
Power Provision: An unswitched 120V electrical junction box must be installed in the attic within 6 feet of the radon vent pipe.
Purpose: If post-construction radon testing shows levels exceeding the EPA action threshold ( 4.0 pCi/L ), an inline centrifugal radon fan can be installed directly into the pipe at the attic junction box location without tearing into finished walls to pull electrical wiring.
2. Converting Passive to Active Radon Depressurization
If testing reveals indoor radon levels ≥ 4.0 pCi/L:
An inline weatherproof radon suction fan is mounted to the vertical vent pipe in the attic space or outside the building envelope (never inside living spaces or basements).
The fan is wired into the pre-installed 120V attic junction box.
A U-tube oil manometer (pressure gauge) is installed on the basement vent pipe to visually verify active vacuum suction under the slab.
3. Indoor Air Quality & Mandatory Mechanical Ventilation
Because modern Minnesota homes achieve high air tightness (≤ 3.0 ACH50), natural building envelope air infiltration cannot replace indoor air or remove pollutants (VOCs, moisture, CO2).
Minnesota Mechanical Ventilation Code (MN Rules Chapter 1322 / 1303)
Minnesota mandates a continuous mechanical ventilation system in all new dwellings:
Balanced Ventilation & Heat Recovery (HRV / ERV)
Heat Recovery Ventilators (HRV): The standard choice for Minnesota (Climate Zones 6 & 7). An HRV continuously exhausts stale indoor air while drawing in fresh outdoor air. A heat-exchange core transfers up to 70–80% of the heat energy from the warm exhaust air to the cold incoming fresh air without mixing the air streams.
Energy Recovery Ventilators (ERV): Transfers sensible heat and latent moisture. ERVs are used in milder climates; in extreme Northern Minnesota winters, ERVs can suffer from core frost buildup if indoor humidity is high. HEAT RECOVERY VENTILATOR (HRV) OPERATION
- Stale Warm Indoor Air (70°F) ───► [ HRV Core ] ───► Exhaust to Outside (30°F)
- ▲
- │ Heat Exchange (No Air Mixing)
- │
- Fresh Cold Outdoor Air (0°F) ───► [ HRV Core ] ───► Pre-Warmed Fresh Air (55°F)
- Ventilation Calculation Standards
Continuous Ventilation Rate (CFM): Calculated based on house square footage and bedroom count:
CFM = (0.01 * Floor Area sq ft) + [7.5 * (Number of Bedrooms + 1)]
Example: A 2,400 sq ft, 4-bedroom home requires:
CFM = (0.01 * 2400) + [7.5 * (4 + 1)] = 24 + 37.5 = 61.5 CFM continuous fresh air flow.
4. Passive Radon Mitigation System Specification Table
System Component MN Code Reference Statutory Installation Requirement
Gas-Permeable Layer MN Rules 1303.2402 Min 4" clean aggregate (1/2" to 1-1/2" stone) or approved soil-gas matting.
Soil-Gas Retarder MN Rules 1303.2403 Min 6-mil polyethylene sheeting over aggregate; 12" lap joints; sealed at edges.
Vent Stack Riser MN Rules 1303.2404 Min 3" or 4" Schedule 40 PVC connected to sub-slab T-fitting; runs vertically.
Stack Termination MN Rules 1303.2404 Min 12" above roof surface; ≥ 10 ft away from operable windows/air intakes.
Pipe Identification MN Rules 1303.2406 Marked "Radon Vent Pipe" on every floor level and in attic space.
Attic Junction Box MN Rules 1303.2407 Unswitched 120V electrical box installed within 6 ft of vent pipe in attic.
Action Threshold EPA / MN Dept of Health 4.0 pCi/L indoor air concentration triggers active fan conversion.
Mechanical Ventilation MN Rules 1322 / 1303 Continuous balanced HRV/ERV system mandatory for tight envelopes (≤ 3.0 ACH50).
Exam Tips & Common Pitfalls (MN General Contractor Exam)
Important
Key Exam Distinctions to Memorize:
Radon System Status: Minnesota requires a PASSIVE system installed during initial construction in all new homes. An active fan is NOT required upfront—only the attic electrical junction box for future active conversion!
Radon Action Level: Memorize 4.0 pCi/L as the EPA / Minnesota Department of Health action level that requires active fan conversion.
Sub-Slab Aggregate Thickness: Remember the aggregate thickness: 4 inches of clean washed stone (1/2" to 1-1/2" size).
Roof Termination Clearances: The radon vent stack must extend at least 12 inches above the roof and at least 10 feet away from operable windows or mechanical intakes.