1.5 Missouri Design Standards, Construction Permits & the Design Guides
Missouri Water and Wastewater Operator Certification Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Missouri State Laws, Regulations & Operator Certification
1.1 MoDNR Regulatory Framework & Operator Classification 1.2 Operator Certification, Experience Requirements & Reciprocity 1.3 Certification Renewal, Continuing Education & Compliance 1.4 Federal & State Drinking Water & Clean Water Acts 1.5 Missouri Design Standards, Construction Permits & the Design Guides 1.6 Utility Management, Administration & Recordkeeping
2 Chapter 2: Water Sources, Hydrology & Raw Water Quality
2.1 Hydrologic Cycle, Groundwater & Surface Water Sources 2.2 Well Construction, Sanitary Protection & Groundwater Hydraulics 2.3 Physical, Chemical & Biological Characteristics of Raw Water 2.4 Water Chemistry Fundamentals for Operators
3 Chapter 3: Coagulation, Flocculation & Sedimentation Processes
3.1 Coagulation Principles & Chemical Additives 3.2 Flocculation Hydraulics & Floc Formation 3.3 Sedimentation Basin Design, Clarifiers & Solids Separation 3.4 Aeration, Taste & Odor Control 3.5 Jar Testing Procedure & Chemical Feed Equipment
4 Chapter 4: Granular Media Filtration & Membrane Technologies
4.1 Conventional Rapid Sand & Dual/Multi-Media Filtration 4.2 Filter Operations, Backwashing & Turbidity Optimization 4.3 Membrane Filtration: Microfiltration, Ultrafiltration, Nanofiltration & Reverse Osmosis
5 Chapter 5: Water Disinfection & Chemical Handling Safety
5.1 Chlorination Chemistry, Breakpoint & Residual Monitoring 5.2 Alternative Disinfectants: Chloramines, Chlorine Dioxide, Ozone & UV 5.3 Disinfection Byproducts & Regulatory Compliance 5.4 Chlorine Gas Safety, Storage & Emergency Containment 5.5 CT Values, Contact Time & Log Inactivation Compliance 5.6 Wastewater Effluent Disinfection & Dechlorination
6 Chapter 6: Softening, Stabilization, Iron/Manganese Removal & Fluoridation
6.1 Lime-Soda Ash Softening & Ion Exchange Demineralization 6.2 Iron and Manganese Removal Technologies 6.3 Corrosion Control, Lead & Copper Rule & Stabilization 6.4 Fluoridation Chemistry, Feed Equipment & Safety
7 Chapter 7: Water Distribution Systems & Infrastructure Operations
7.1 Distribution Piping, Main Installation & Appurtenances 7.2 Distribution Storage Facilities & Pressure Management 7.3 Valves, Fire Hydrants & Metering Systems 7.4 Cross-Connection Control & Backflow Prevention
8 Chapter 8: Wastewater Characteristics, Preliminary & Primary Treatment
8.1 Wastewater Characteristics, Flow Variations & Sampling 8.2 Preliminary Treatment: Screening, Grinding & Grit Removal 8.3 Primary Clarification & Sedimentation Operations
9 Chapter 9: Biological Wastewater Treatment & Secondary Processes
9.1 Activated Sludge Fundamentals & Microbiology 9.2 Activated Sludge Process Control & Operational Parameters 9.3 Activated Sludge Variations: Extended Aeration, Oxidation Ditches & SBRs 9.4 Fixed-Film Processes & Waste Stabilization Ponds
10 Chapter 10: Advanced Wastewater Treatment, Nutrient Removal & Sludge Management
10.1 Biological & Chemical Phosphorus Removal 10.2 Biological Nitrogen Removal: Nitrification & Denitrification 10.3 Sludge Thickening, Stabilization & Digestion 10.4 Biosolids Dewatering, Land Application & 40 CFR Part 503 10.5 Thermal Solids Reduction & Sewage Sludge Incineration
11 Chapter 11: Wastewater Collection Systems & Lift Station Maintenance
11.1 Gravity Sewer Design, Hydraulics & Inflow/Infiltration 11.2 Lift Stations, Pumps & Level Control Systems 11.3 Collection System Operation, Cleaning & Inspection
12 Chapter 12: Water & Wastewater Laboratory Methods, Process Math & Safety
12.1 Water & Wastewater Laboratory Procedures & QA/QC 12.2 Applied Math: Pounds Formula, Chemical Feed & Flow Conversions 12.3 Applied Math: Process Loading, Weir Rates, SVI & Sludge Age 12.4 Plant Safety, Confined Space Entry, Chemical Hazards & Emergency Protocols 12.5 Pumps, Motors, Electrical Controls & Flow Measurement
1.5 Missouri Design Standards, Construction Permits & the Design Guides
Key Takeaways Explain This Topic AI
Missouri drinking water construction standards live in 10 CSR 60 Chapter 3 and the department's design guides; wastewater design standards live in 10 CSR 20-8.
A MoDNR construction permit or authorization is required before covered construction or substantial modification; completed drinking-water facilities require final construction approval and a permit to dispense, while wastewater discharges operate under an MSOP.
The Missouri Wastewater Design Guidelines and Standards (PUB2754) is a named study reference on the official MoDNR wastewater exam descriptions.
Design criteria the exam expects operators to know include the 20 psi minimum during normal distribution operations, 10-foot horizontal water/sewer separation, and 18-inch vertical clearance at crossings unless the department approves protective alternatives.
Operators should maintain approved and as-built plans and verify that repairs and replacements preserve applicable sanitary and design requirements.
Last updated: September 2026
Exam candidates often treat design standards as an engineer's problem. Missouri does not. DESIGN GUIDE is a named objective on the official MoDNR test descriptions for Drinking Water A, B and C and Distribution System 3, and the wastewater test descriptions list the Missouri Wastewater Design Guidelines and Standards as a study reference alongside the Sacramento State manuals. Operators are expected to know the criteria their facilities were approved under, because those criteria become operating limits.
Construction Approval and Permission to Operate
Missouri separates permission to build from permission to dispense water or discharge wastewater . The names are track-specific:
Approval When it is required What it controls
Construction permit / authorization Before covered construction, extension or substantial alteration of a public water system or wastewater works Department review of engineering reports, plans and specifications against the applicable design rules
Final construction approval and permit to dispense Before a completed public drinking-water facility dispenses water to the public Conformance with the approved project and the system's continuing operating authority
Missouri State Operating Permit (MSOP) Before a regulated wastewater discharge occurs Effluent limits, monitoring, reporting and other NPDES conditions
The wastewater MSOP is Missouri's implementation of the federal NPDES permit under RSMo Chapter 644. The MSOP is also where the wastewater facility classification is confirmed when the permit is renewed. A drinking-water permit to dispense is not an NPDES/MSOP and should not be described as though both tracks use one generic operating permit.
Substantial modification is the phrase that catches operators out. Replacing a failed pump with an identical unit is maintenance. Changing the type of disinfection, adding a treatment process, increasing hydraulic capacity, or extending a main into a new service area is a modification that needs a construction permit first — and, in the drinking water case, may change the plant's Table 1 classification and therefore the certificate level the chief operator must hold.
Drinking Water Design Criteria Operators Should Know
- Criterion Standard
- Minimum residual pressure, normal demand 20 psi throughout the distribution system at all points
- Working pressure, typical design range 35 to 80 psi
- Minimum water main size for fire protection 6 inches (8 inches common on new grids)
- Water main / sanitary sewer horizontal separation 10 feet edge to edge
Water main / non-potable pipeline crossing At least 18 inches of vertical clear distance , whether the water main is above or below; locate water-pipe joints as far from the crossing as possible and use approved protective construction where separation cannot be achieved
Finished water storage Sized for equalisation plus fire flow plus emergency reserve; turnover sufficient to prevent excessive water age
Well construction Casing extended above the highest known flood elevation, grouted annular space, sanitary seal, and a screened, downward-facing vent
The separation rules protect a depressurized water main from nearby contamination and protect both pipes from structural failure. PUB2489 generally requires 10 feet horizontally for parallel lines and 18 inches vertically at crossings. At a crossing, the water main may be above or below the non-potable line; if the prescribed separation cannot be achieved, the department must approve restrained, fusion-welded or continuously cased construction and any needed structural support.
Wastewater Design Criteria Operators Should Know
The Missouri Wastewater Design Guidelines and Standards and 10 CSR 20-8 fix the numbers that operators later have to live inside.
- Criterion Typical standard
- Minimum gravity sewer velocity 2.0 ft/s flowing full or half full, to keep solids in suspension
- Minimum sewer size, public gravity main 8 inches
Manhole spacing Generally 400 feet maximum on small-diameter sewers, and at every change of grade, size or alignment
Lift station capacity Firm capacity with the largest pump out of service must still pass peak flow
Lagoon design Multiple cells in series, controlled discharge, minimum operating depth typically 2 to 5 feet with freeboard
Design flow basis Average day design flow, or peak month average day flow, whichever is larger — the same basis the 10 CSR 20-9 point table uses
That last row links design directly to certification: the point table awards 1 point per MGD based on design flow or peak month flow, whichever is larger, so an operator reading the design report can reproduce part of the plant's own classification score.
Why This Matters Day to Day
Repairs must restore the approved standard. A repair must preserve approved bedding, restraint, sanitary separation, disinfection and pressure-testing requirements. If site conditions prevent the specified water/sewer separation, obtain the required engineering and department approval for the protective alternative.
As-built records are an operator responsibility. The renewal training rules explicitly credit training on construction, record keeping and repair of system components — the department expects operators to maintain accurate plans and valve records.
Design capacity is a compliance limit. A lagoon designed for 0.25 MGD that routinely receives 0.40 MGD needs more than an improvised process adjustment: document the loading, protect current compliance, notify the responsible authority as required, and obtain engineering and permitting review for capacity correction.