Study guide
2.3 HIRARC and the General Principles of Prevention
NIOSH Site Safety Supervisor SSS
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The SSS Role & Malaysian OSH Legislation
1.1 The Site Safety Supervisor: Legal Appointment, DOSH Registration & Core Duties 1.2 OSHA 1994 as Amended by Act A1648: Structure, Duties, Rights & Penalties 1.3 Regulations Under OSHA 1994 That a Site Safety Supervisor Applies 1.4 CDM Regulations 2024: Duty Holders, Notification, Plans and Site Requirements
2 Chapter 2: OSH Management Systems, Human Factors & Risk Management
2.1 OSH Management Systems: Planning, OSH Policy, Site Organisation & Safety Committees 2.2 Human and Behavioural Factors in Construction Safety 2.3 HIRARC and the General Principles of Prevention 2.4 Safe Work Procedures and Permit-to-Work Systems 2.5 Monitoring, Accident Investigation, NADOPOD Reporting, Record Keeping & Audit
3 Chapter 3: Site Planning, General Control, Welfare & Communication
3.1 Site Initial Planning, Hoarding, Access and Vehicle & Plant Movement 3.2 General Control and Welfare: Housekeeping, Storage, Site Security, Welfare Facilities and First Aid 3.3 Safety Communication: Site Induction, Toolbox Meetings, Signs and Safety Promotion
4 Chapter 4: Working at Height & Fall Protection
4.1 Working at Height: Legal Basis, Fall Physics and the Fall-Control Hierarchy 4.2 Collective Fall Protection: Guardrails, Floor Openings, Nets and Catch Platforms 4.3 Personal Fall Protection, Ladders, MEWPs and Rescue from Height
5 Chapter 5: Scaffolding: Components, Design, Erection & Inspection
5.1 Scaffolding Types, Components, Foundations, Bracing and Tower Scaffolds 5.2 Scaffold Design, Loading, Competent Scaffolders and Safe Erection & Dismantling 5.3 Scaffold Inspection, Tagging Systems and Records
6 Chapter 6: Excavation, Shoring & Underground Services
6.1 Excavation Hazards, Soil Behaviour and Pre-Excavation Investigation 6.2 Protecting Excavation Sides: Battering, Benching, Shoring and Trench Support Systems 6.3 Deep Excavations, Retaining Systems, Cofferdams & Caissons, Monitoring and Rescue 6.4 Excavation Access, Edge Protection, Inspection Reports, Underground Services, Water and Air
7 Chapter 7: Piling, Formwork & Falsework, Concrete Work & Demolition
7.1 Piling Operations: Rigs, Working Platforms, Driven and Bored Piles 7.2 Formwork and Falsework: Temporary Works Design, Erection, Inspection and Loading 7.3 Concrete Work: Pre-Pour Checks, Pumping and Placing, Cement Health Hazards and Striking 7.4 Demolition and Dismantling: Surveys, Written Arrangements, Methods, Debris and Asbestos
8 Chapter 8: Lifting Operations, Work Equipment & Mobile Plant
8.1 Cranes and Hoists: Certificates of Fitness, Competent Operators, Ground and Crane Safety 8.2 Lifting Tackle and Rigging: Slings, Shackles, Hooks, Inspection and Discard 8.3 Lift Planning, Load Charts, Sling Angles and Crane Signalling 8.4 Work Equipment and Mobile Plant: Earthmoving Machines, Hand and Power Tools, Compressors and Guarding
9 Chapter 9: Electrical Safety, Fire & Hot Work, and Confined Spaces
9.1 Electrical Safety on Construction Sites: Temporary Supply, RCDs, Competent Persons and Safe Isolation 9.2 Fire Safety, Emergency Arrangements, Hot Work and Welding 9.3 Confined Spaces: The 2010 ICOP, Hazardous Atmospheres, Roles, Permits and Rescue
10 Chapter 10: Occupational Health Hazards & Controls
10.1 Physical Hazards: Noise, Vibration, Heat Stress, Radiation and Lighting 10.2 Musculoskeletal Hazards: Manual Handling and Ergonomics on Construction Sites 10.3 Chemical and Biological Hazards: USECHH, CLASS, Silica, Asbestos, Lead and Site Infections 10.4 Psychological Health: Psychosocial Hazards, Stress, Fatigue, Violence and Substance Misuse 10.5 Personal Protective Equipment and Site Emergency Response
11 Chapter 11: The SSS Examination: Paper 1, Site Assessment & Presentation
11.1 The SSS Examination: Entry Rules, Format, Retakes and Paper 1 Technique 11.2 Paper 2: Site Visit Practice, the Site Assessment and the Online HIRARC Presentation
2.3 HIRARC and the General Principles of Prevention
Key Takeaways Explain This Topic AI
The DOSH HIRARC Guidelines 2008 define hazard as a source or situation with a potential for harm in terms of human injury or ill health, damage to property, damage to the environment or a combination of these.
In the HIRARC 2008 risk matrix, risk equals likelihood multiplied by severity, each rated 1 to 5: scores of 15 to 25 are High, 5 to 12 are Medium and 1 to 4 are Low.
A High risk under HIRARC 2008 requires immediate action to control the hazard as detailed in the hierarchy of control, documented on the assessment form with a completion date.
HIRARC 2008 says the assessment should be reviewed every three years or whenever there are changes in the process or activities.
The First Schedule of CDM 2024 lists nine general principles of prevention, beginning with avoiding risks and including giving collective protective measures priority over individual measures.
Last updated: October 2026
The legal hook
Before Act A1648, risk assessment was implied by the general duties in section 15. Since 1 June 2024, section 18B of OSHA 1994 requires every employer, self-employed person and principal to:
conduct a risk assessment of the risks to anyone who may be affected by its undertaking, and
implement whatever control the assessment shows is needed.
CDM 2024 adds that designers, the principal designer, the principal contractor and contractors must apply the general principles of prevention (First Schedule). Contractors must give workers the risk information identified by the section 18B assessment (regulation 17(2)(c)).
The DOSH Guidelines for HIRARC 2008 are the method NIOSH teaches. They also matter for Paper 2B: the presentation guideline tells candidates to present HIRARC "with reference to the HIRARC Guidelines 2008", and it is the largest single item in the marking scheme (20 of 100 marks).
Definitions in HIRARC 2008
Term Definition (HIRARC 2008, section 2.0)
Hazard A source or a situation with a potential for harm in terms of human injury or ill health, damage to property, damage to the environment or a combination of these
Hazard identification Identification of the undesired events that lead to the hazard materialising, and the mechanism by which they could occur
Risk A combination of the likelihood of a hazardous event occurring within a specified period or circumstances and the severity of injury or damage it causes
- Risk assessment The process of evaluating the risks to safety and health arising from hazards at work
- Hazard control The process of implementing measures to reduce the risk associated with a hazard
- Hierarchy of control The established priority order for the types of measures used to control risks
Risk management The total procedure of identifying a hazard, assessing the risk, putting control measures in place and reviewing the outcomes
Many trainers also use the word danger to describe a person's exposure to a hazard: an open floor edge is a hazard, and a worker standing next to it unprotected is in danger. Note that HIRARC 2008 itself does not define "danger". Quote the guideline's own definitions when a question asks for them.
The HIRARC process
HIRARC 2008 (section 4.3) describes four simple steps, supported by consultation between employer and worker representatives and by review :
Classify work activities. Group them by area, stage or defined task, not too big ("build the tower") and not too small ("tighten one bolt"). Example: "erect independent scaffold, Block B east façade".
Identify hazards. HIRARC groups them as health hazards (for example silica dust, noise, heat), safety hazards (falls, collapse, struck-by, electrocution) and environmental hazards (spills, silt runoff).
Assess the risk. Estimate likelihood and severity, taking existing controls into account, and read off the risk level.
Control the risk. Prepare and implement a risk control action plan using the hierarchy of control. Assign a responsible person and a target date, then reassess the residual risk.
Useful identification techniques on a construction site include:
- walk-through inspections
- task or job hazard analysis
- method statements
- checklists
- worker and toolbox feedback
- near-miss and accident records
- safety data sheets and manufacturers' manuals
design information from the principal designer, such as the pre-construction information and health and safety file
- Rating likelihood and severity
- Table A: likelihood (HIRARC 2008)
- Rating Likelihood Description
- 5 Most likely The most likely result of the hazard or event being realised
- 4 Possible Has a good chance of occurring and is not unusual
- 3 Conceivable Might occur at some time in future
- 2 Remote Has not been known to occur after many years
- 1 Inconceivable Is practically impossible and has never occurred
- Table B: severity (HIRARC 2008)
- Rating Severity Description
- 5 Catastrophic Numerous fatalities, irrecoverable property damage and productivity
- 4 Fatal Approximately one single fatality; major property damage if the hazard is realised
- 3 Serious Non-fatal injury, permanent disability
- 2 Minor Disabling but not permanent injury
- 1 Negligible Minor abrasions, bruises, cuts, first-aid type injury
- The risk matrix and required action
Risk = Likelihood (L) x Severity (S).
- L \ S 1 Negligible 2 Minor 3 Serious 4 Fatal 5 Catastrophic
- 5 Most likely 5 M 10 M 15 H 20 H 25 H
- 4 Possible 4 L 8 M 12 M 16 H 20 H
- 3 Conceivable 3 L 6 M 9 M 12 M 15 H
- 2 Remote 2 L 4 L 6 M 8 M 10 M
- 1 Inconceivable 1 L 2 L 3 L 4 L 5 M
Risk Score Action required by HIRARC 2008 (Table D)
High 15–25 Immediate action to control the hazard as detailed in the hierarchy of control, documented on the risk assessment form with a completion date. The person responsible for action and follow-up must be identified
Medium 5–12 A planned approach to controlling the hazard, with temporary measures if required, documented with a completion date
Low 1–4 May be considered acceptable and further reduction may not be necessary. If it can be resolved quickly and efficiently, control it and record it
On site, "immediate action" for a High risk usually means the activity does not start, or is stopped, until controls have brought the risk down. That is the practical way to meet the duty, and it is what the SSS's stop-work authority is for.
The hierarchy of control
HIRARC 2008 (section 5) prefers controls at the source , then along the path to the worker, and only then at the worker .
Level HIRARC 2008 examples Construction examples
Elimination Get rid of the hazardous job, tool, process, machine or substance Assemble roof trusses at ground level and lift them as one unit
Substitution Do the same work in a less hazardous way Water-based instead of solvent-based coatings; a mechanical breaker on a long-reach arm instead of hand-held jackhammers
Engineering control Redesign, isolation, automation, barriers, absorption, dilution Guardrails and floor-opening covers; local exhaust or water suppression on cutting saws; acoustic enclosures on generators
Administrative control Safe work procedures, supervision and training, job rotation, housekeeping and maintenance, hygiene Permit-to-work; exclusion zones; rotating breaker operators; daily housekeeping
Personal protective equipment Last resort, used with the other levels Harness and lanyard where edge protection is impracticable; respirators; hearing protection
USECHH regulation 15 and the Noise Exposure Regulations 2019 apply the same order to chemicals and noise.
The general principles of prevention (CDM 2024, First Schedule)
Avoid risks.
Evaluate the risks that cannot be avoided.
Combat risks at source.
Adapt the work to the individual, especially in the design of workplaces, the choice of plant and the choice of working and production methods, to reduce monotonous work and work at a predetermined rate and their effect on health.
Adapt to technical progress.
Replace the dangerous by the non-dangerous or the less dangerous.
Develop a coherent overall prevention policy covering technology, organisation of work, working conditions, social relationships and the influence of factors related to the working environment.
Give collective protective measures priority over individual protective measures.
Give appropriate instructions to workers.
Principle 8 is the legal basis for preferring guardrails and nets (collective) over harnesses (individual). Principle 4 links HIRARC to ergonomics and human factors.
Writing a HIRARC entry that scores
- Field Weak entry Strong entry
- Activity "Formwork" "Erect beam formwork at Level 8 perimeter, grid A–F"
- Hazard "Fall" "Fall of person from unprotected slab edge (about 28 m)"
- Existing control "PPE" "Harness issued; no anchorage; no edge protection"
- L x S "High" "L4 Possible x S4 Fatal = 16, High"
Additional control "Be careful" "Install proprietary edge protection before work starts (engineering); permit for edge work; SSS check before start (administrative); harness only while fitting edge protection"
- Responsible person and date blank "Site engineer; before 07:30, 24 Oct 2026"
- Residual risk blank "L1 x S4 = 4, Low"
- When to review
HIRARC 2008 (section 6.2) says to "review HIRARC every three years or whenever there are changes in process or activities". On a construction project, changes happen constantly: new trades, new plant, weather, design changes and incidents. In practice the activity HIRARC is reviewed far more often than every three years, and every review must be recorded.