6.2 Protecting Excavation Sides: Battering, Benching, Shoring and Trench Support Systems
NIOSH Site Safety Supervisor SSS
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The SSS Role & Malaysian OSH Legislation
1.1 The Site Safety Supervisor: Legal Appointment, DOSH Registration & Core Duties 1.2 OSHA 1994 as Amended by Act A1648: Structure, Duties, Rights & Penalties 1.3 Regulations Under OSHA 1994 That a Site Safety Supervisor Applies 1.4 CDM Regulations 2024: Duty Holders, Notification, Plans and Site Requirements
2 Chapter 2: OSH Management Systems, Human Factors & Risk Management
2.1 OSH Management Systems: Planning, OSH Policy, Site Organisation & Safety Committees 2.2 Human and Behavioural Factors in Construction Safety 2.3 HIRARC and the General Principles of Prevention 2.4 Safe Work Procedures and Permit-to-Work Systems 2.5 Monitoring, Accident Investigation, NADOPOD Reporting, Record Keeping & Audit
3 Chapter 3: Site Planning, General Control, Welfare & Communication
3.1 Site Initial Planning, Hoarding, Access and Vehicle & Plant Movement 3.2 General Control and Welfare: Housekeeping, Storage, Site Security, Welfare Facilities and First Aid 3.3 Safety Communication: Site Induction, Toolbox Meetings, Signs and Safety Promotion
4 Chapter 4: Working at Height & Fall Protection
4.1 Working at Height: Legal Basis, Fall Physics and the Fall-Control Hierarchy 4.2 Collective Fall Protection: Guardrails, Floor Openings, Nets and Catch Platforms 4.3 Personal Fall Protection, Ladders, MEWPs and Rescue from Height
5 Chapter 5: Scaffolding: Components, Design, Erection & Inspection
5.1 Scaffolding Types, Components, Foundations, Bracing and Tower Scaffolds 5.2 Scaffold Design, Loading, Competent Scaffolders and Safe Erection & Dismantling 5.3 Scaffold Inspection, Tagging Systems and Records
6 Chapter 6: Excavation, Shoring & Underground Services
6.1 Excavation Hazards, Soil Behaviour and Pre-Excavation Investigation 6.2 Protecting Excavation Sides: Battering, Benching, Shoring and Trench Support Systems 6.3 Deep Excavations, Retaining Systems, Cofferdams & Caissons, Monitoring and Rescue 6.4 Excavation Access, Edge Protection, Inspection Reports, Underground Services, Water and Air
7 Chapter 7: Piling, Formwork & Falsework, Concrete Work & Demolition
7.1 Piling Operations: Rigs, Working Platforms, Driven and Bored Piles 7.2 Formwork and Falsework: Temporary Works Design, Erection, Inspection and Loading 7.3 Concrete Work: Pre-Pour Checks, Pumping and Placing, Cement Health Hazards and Striking 7.4 Demolition and Dismantling: Surveys, Written Arrangements, Methods, Debris and Asbestos
8 Chapter 8: Lifting Operations, Work Equipment & Mobile Plant
8.1 Cranes and Hoists: Certificates of Fitness, Competent Operators, Ground and Crane Safety 8.2 Lifting Tackle and Rigging: Slings, Shackles, Hooks, Inspection and Discard 8.3 Lift Planning, Load Charts, Sling Angles and Crane Signalling 8.4 Work Equipment and Mobile Plant: Earthmoving Machines, Hand and Power Tools, Compressors and Guarding
9 Chapter 9: Electrical Safety, Fire & Hot Work, and Confined Spaces
9.1 Electrical Safety on Construction Sites: Temporary Supply, RCDs, Competent Persons and Safe Isolation 9.2 Fire Safety, Emergency Arrangements, Hot Work and Welding 9.3 Confined Spaces: The 2010 ICOP, Hazardous Atmospheres, Roles, Permits and Rescue
10 Chapter 10: Occupational Health Hazards & Controls
10.1 Physical Hazards: Noise, Vibration, Heat Stress, Radiation and Lighting 10.2 Musculoskeletal Hazards: Manual Handling and Ergonomics on Construction Sites 10.3 Chemical and Biological Hazards: USECHH, CLASS, Silica, Asbestos, Lead and Site Infections 10.4 Psychological Health: Psychosocial Hazards, Stress, Fatigue, Violence and Substance Misuse 10.5 Personal Protective Equipment and Site Emergency Response
11 Chapter 11: The SSS Examination: Paper 1, Site Assessment & Presentation
11.1 The SSS Examination: Entry Rules, Format, Retakes and Paper 1 Technique 11.2 Paper 2: Site Visit Practice, the Site Assessment and the Online HIRARC Presentation
6.2 Protecting Excavation Sides: Battering, Benching, Shoring and Trench Support Systems
Key Takeaways Explain This Topic AI
DOSH's excavation bulletin says no employee should enter an excavated area unless supports such as sheet piling or shoring, or other necessary safeguards, are provided.
For dry ground, DOSH's excavation bulletin (quoting HSE guidance) gives typical safe slope angles of 30–40° for gravel, 30–35° for sand, 20–40° for silt and 20–45° for clay, with much flatter slopes in wet ground.
DOSH's excavation bulletin says benching steps should be no more than 1.2 metres high and at least 1.2 metres wide, and that trenches over 3 metres deep should be benched or stepped if not supported.
DOSH's excavation bulletin recommends placing spoil and other loads at least 610 mm from the edge, or a distance equal to the trench depth, depending on depth, slope, soil and load.
Proprietary trench boxes, hydraulic frames and slide-rail systems must be used strictly to the manufacturer's instructions, according to DOSH's excavation bulletin.
Last updated: October 2026
Two ways to keep the sides up
Cut the sides back (batter or bench) to a slope at which the ground will stand under all foreseeable conditions of work and weather.
Support the sides with timbering, sheeting, sheet piles, trench boxes or hydraulic frames designed for the ground, water and surcharge.
CDM 2024 regulation 24(1) requires whichever measures are practicable to prevent collapse, burial and falling material, "including providing supports or reinforcement" . DOSH's 2015 Tapak Selamat excavation bulletin (paragraph 11) is blunt: no employee shall be permitted to enter any excavated area unless supports such as sheet piling, shoring or other necessary safeguards are provided . Designing supports or slopes needs reliable soil and rock parameters from site investigation.
Battering (sloping)
An unsupported trench must be cut back to a safe slope , so that the material in the sides can stand under all expected work and weather conditions. DOSH's bulletin gives typical safe angles from the HSE (UK) guidance it cites:
- Material Dry ground (degrees to horizontal) Wet ground (degrees to horizontal)
- Gravel 30–40 10–30
- Sand 30–35 10–30
- Silt 20–40 5–20
- Clay 20–45 10–35
- Peat 10–45 5–35
Use the table with care:
Natural soils are usually mixtures.
A small rise in water content can greatly reduce strength.
Battered excavations need regular monitoring .
Rock faces may need regular scaling to remove loose material.
The bulletin also notes that in a shallow trench in uniform material known to be stable, which will be backfilled soon, vertical faces may be safe up to 1.5 m . This is a judgement for a competent person, not a free pass: water, vibration, fill or surcharge cancel it.
Worked example: a 3 m deep trench in dry sand battered at 30° needs each side to extend horizontally about 3 / tan 30° = 3 / 0.577 = 5.2 m from the toe. In a narrow lane that space rarely exists, which is why support systems are used.
Benching (stepping)
Benching cuts the sides into a series of steps. DOSH's bulletin says:
- step dimensions follow the safe slope angles above
- the vertical rise of each step should not exceed 1.2 m (HSE)
- each step should be at least 1.2 m wide (DOSH 2000)
where a trench exceeds 3 m in depth and is not otherwise supported, it should be benched or stepped (DOSH 2000)
Benching is unsuitable for granular soils that run, and for wet ground where the steps themselves slump.
- Supporting the sides
- Timbering and sheeting
Sheeting means steel sheets or timber boards against the trench walls. Close sheeting (boards or sheets touching) is used in loose or wet ground. Open sheeting (spaced boards) is suitable only in firm clay.
Walings (wales) are horizontal members holding the sheeting. Struts span between walings across the trench.
DOSH's bulletin, quoting the former FMA rules, says planks used as sheet piling should be at least 50 mm thick , wale spacing must keep the planks within their safe bending stress, and each end of each waling must be separately braced .
Earth-supported shores or braces must bear against footings large and stable enough, or be toed in deeply enough, not to shift.
Use timber packing so steel struts do not bear directly on steel.
Where banks are undercut , provide shoring to support the overhang. Do not remove temporary sheet piling for a retaining wall until the wall has developed its full strength.
Proprietary systems
System How it works Points to watch
Hydraulic waling frames and struts Frames lowered from the surface and pressurised against sheets or the soil Install and remove from the surface; check pressure and pins; manufacturer's depth and width limits
Trench boxes (drag boxes) Steel shield placed in the trench; workers stay inside it The box protects only inside its walls; keep it within its rated depth; never leave a gap below the box
Slide-rail systems Panels slide in vertical rails driven as excavation proceeds For deeper trenches and poor ground; specialist installation
Manhole shores Circular or rectangular frames for pits Rated depth and ground conditions
DOSH's bulletin (paragraph 25) says proprietary ground support systems must always be used in accordance with the manufacturer's instructions .
Where a trench needs two lengths of sheet piling, one above the other , the lower piling is set inside the bottom walings of the upper piling and is driven and braced as the excavation proceeds (bulletin paragraph 69).
Installing and removing support safely
Never enter an unsupported trench to install supports. Install from the surface, or progressively: dig, then immediately support, before anyone goes below.
Install struts from the top down . Remove them from the bottom up , as backfilling proceeds, so the trench is never left without support. DOSH's bulletin says temporary supports should not be withdrawn until enough backfill is in place to prevent collapse, and backfill must be placed and compacted in layers.
Re-inspect after any change to the support, after rain and at every shift start (Section 6.4).
Spoil and surcharge
CDM regulation 24(1)(e) requires steps so that no part of an excavation, or the ground next to it, is overloaded by plant or material. DOSH's bulletin (paragraph 55) recommends:
placing excavated material and other loads at least 610 mm from the edge , or a distance of the trench depth . Choose the distance by considering the excavation's depth and slope, the soil and the weight of the load.
piling or retaining spoil so it cannot fall back in , make the banks slip, or heave the excavation bed
placing spoil on the lower side of sloping ground where possible, without holding back runoff water, and shaping it to channel rainwater away from the excavation
For plant:
Keep heavy plant, cranes, concrete trucks and stockpiles out of the zone of influence unless the support design allows for their loads (bulletin paragraphs 53 and 54).
Use stop blocks or bunds where vehicles tip near edges (CDM regulation 30(5)).
Never let workers stay in a trench while plant is depositing material into it (bulletin paragraph 37).
Scenario: a 2.5 m sewer trench in silty sand
The method statement shows a vertical-sided trench with no support, the excavator dumping spoil on both edges, and pipe-layers working in the trench. The SSS stops the work because:
Silty sand with groundwater cannot stand vertically at 2.5 m, and the 1.5 m "shallow trench" allowance does not apply.
Spoil on the edge overloads the sides (regulation 24(1)(e)).
Nobody may enter without supports (bulletin paragraph 11).
The revised method:
- a trench box or hydraulic frame system within its rated depth, installed from the surface
- spoil loaded straight into trucks, or placed beyond the zone of influence on one side
- dewatering through a silt trap
- ladder access inside the protected zone
- shift-start inspections by a designated person, recorded under regulation 26