7.3 Concrete Work: Pre-Pour Checks, Pumping and Placing, Cement Health Hazards and Striking
NIOSH Site Safety Supervisor SSS
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The SSS Role & Malaysian OSH Legislation
1.1 The Site Safety Supervisor: Legal Appointment, DOSH Registration & Core Duties 1.2 OSHA 1994 as Amended by Act A1648: Structure, Duties, Rights & Penalties 1.3 Regulations Under OSHA 1994 That a Site Safety Supervisor Applies 1.4 CDM Regulations 2024: Duty Holders, Notification, Plans and Site Requirements
2 Chapter 2: OSH Management Systems, Human Factors & Risk Management
2.1 OSH Management Systems: Planning, OSH Policy, Site Organisation & Safety Committees 2.2 Human and Behavioural Factors in Construction Safety 2.3 HIRARC and the General Principles of Prevention 2.4 Safe Work Procedures and Permit-to-Work Systems 2.5 Monitoring, Accident Investigation, NADOPOD Reporting, Record Keeping & Audit
3 Chapter 3: Site Planning, General Control, Welfare & Communication
3.1 Site Initial Planning, Hoarding, Access and Vehicle & Plant Movement 3.2 General Control and Welfare: Housekeeping, Storage, Site Security, Welfare Facilities and First Aid 3.3 Safety Communication: Site Induction, Toolbox Meetings, Signs and Safety Promotion
4 Chapter 4: Working at Height & Fall Protection
4.1 Working at Height: Legal Basis, Fall Physics and the Fall-Control Hierarchy 4.2 Collective Fall Protection: Guardrails, Floor Openings, Nets and Catch Platforms 4.3 Personal Fall Protection, Ladders, MEWPs and Rescue from Height
5 Chapter 5: Scaffolding: Components, Design, Erection & Inspection
5.1 Scaffolding Types, Components, Foundations, Bracing and Tower Scaffolds 5.2 Scaffold Design, Loading, Competent Scaffolders and Safe Erection & Dismantling 5.3 Scaffold Inspection, Tagging Systems and Records
6 Chapter 6: Excavation, Shoring & Underground Services
6.1 Excavation Hazards, Soil Behaviour and Pre-Excavation Investigation 6.2 Protecting Excavation Sides: Battering, Benching, Shoring and Trench Support Systems 6.3 Deep Excavations, Retaining Systems, Cofferdams & Caissons, Monitoring and Rescue 6.4 Excavation Access, Edge Protection, Inspection Reports, Underground Services, Water and Air
7 Chapter 7: Piling, Formwork & Falsework, Concrete Work & Demolition
7.1 Piling Operations: Rigs, Working Platforms, Driven and Bored Piles 7.2 Formwork and Falsework: Temporary Works Design, Erection, Inspection and Loading 7.3 Concrete Work: Pre-Pour Checks, Pumping and Placing, Cement Health Hazards and Striking 7.4 Demolition and Dismantling: Surveys, Written Arrangements, Methods, Debris and Asbestos
8 Chapter 8: Lifting Operations, Work Equipment & Mobile Plant
8.1 Cranes and Hoists: Certificates of Fitness, Competent Operators, Ground and Crane Safety 8.2 Lifting Tackle and Rigging: Slings, Shackles, Hooks, Inspection and Discard 8.3 Lift Planning, Load Charts, Sling Angles and Crane Signalling 8.4 Work Equipment and Mobile Plant: Earthmoving Machines, Hand and Power Tools, Compressors and Guarding
9 Chapter 9: Electrical Safety, Fire & Hot Work, and Confined Spaces
9.1 Electrical Safety on Construction Sites: Temporary Supply, RCDs, Competent Persons and Safe Isolation 9.2 Fire Safety, Emergency Arrangements, Hot Work and Welding 9.3 Confined Spaces: The 2010 ICOP, Hazardous Atmospheres, Roles, Permits and Rescue
10 Chapter 10: Occupational Health Hazards & Controls
10.1 Physical Hazards: Noise, Vibration, Heat Stress, Radiation and Lighting 10.2 Musculoskeletal Hazards: Manual Handling and Ergonomics on Construction Sites 10.3 Chemical and Biological Hazards: USECHH, CLASS, Silica, Asbestos, Lead and Site Infections 10.4 Psychological Health: Psychosocial Hazards, Stress, Fatigue, Violence and Substance Misuse 10.5 Personal Protective Equipment and Site Emergency Response
11 Chapter 11: The SSS Examination: Paper 1, Site Assessment & Presentation
11.1 The SSS Examination: Entry Rules, Format, Retakes and Paper 1 Technique 11.2 Paper 2: Site Visit Practice, the Site Assessment and the Online HIRARC Presentation
7.3 Concrete Work: Pre-Pour Checks, Pumping and Placing, Cement Health Hazards and Striking
Key Takeaways Explain This Topic AI
A permit to pour should be issued only after falsework, formwork, edge protection, access, pump set-up and the pour sequence have been checked against the temporary works design.
Concrete pumps and truck mixers working near overhead lines must follow CDM 2024 regulation 27: divert, isolate and earth, or protect the line with barriers, warning notices and suspended protection, and observe the line owner's safe distance.
Wet cement is strongly alkaline and can cause chemical burns and dermatitis; occupational dermatitis appears in the Third Schedule of NADOPOD 2004 as a reportable occupational disease.
CDM 2024 regulation 37 requires suitable and sufficient lighting, including secondary lighting where failure of the main artificial lighting would create risk, which applies to night pours.
Formwork may be struck only when the engineer's criteria, such as concrete cube strength or age, are met; early stripping has caused slab and beam failures.
Last updated: October 2026
Why concrete work deserves its own plan
Concreting brings several high-risk activities together at one place and time:
- heavy trucks reversing and queuing
- a boom pump with outriggers on uncertain ground
- pipelines under pressure
- workers on newly loaded falsework at an open slab edge
- vibrators and power tools
- cement contact
- often night work or long hours in heat
Each element is covered elsewhere in this guide. A pour succeeds when they are coordinated through one plan and one permit.
Before the pour: inspection and permit to pour
The permit to pour, or permit to load, links the temporary works process (Section 7.2) to the day's operation. Do not issue it until:
Check What is confirmed
Falsework and formwork Built to the drawings; inspected by the designated person or temporary works coordinator; defects closed
Edge protection and access Guardrails at slab edges and openings; safe ladder or stair access; walk boards over reinforcement
Pump set-up Firm, level location; outriggers fully extended on pads sized for the ground; outside the excavation's zone of influence; clear of overhead lines
Traffic plan Truck route, waiting area inside the hoarding, washout point, banksman, pedestrian separation (CDM regulations 29 and 30)
Pour sequence Order and rate of placing as the design requires; watcher appointed with authority to stop the pour
People and equipment Crew briefed in a toolbox meeting; vibrators and electrical supply checked (RCD-protected); lighting for night work; first aid and emergency arrangements; drinking water
Weather Rain or lightning forecast and the stop rules
Signatories normally include the principal contractor's engineer, the temporary works coordinator and the SSS, with the consultant where the contract requires.
- Delivery and pumping
- Truck mixers
Follow the traffic routes and avoid reversing. Where reversing is unavoidable, use a trained banksman (CDM regulation 30(2)).
Keep trucks back from excavation edges and use stop blocks where they discharge near trenches (regulation 30(5)).
Provide a washout area that contains the alkaline washwater and stops it entering drains.
Boom pumps
Operate to the manufacturer's instructions by a trained operator. Use the outrigger pads and set-up the manufacturer specifies.
The boom must never be used as a crane.
Overhead lines: this is the main electrocution risk in concreting. Under CDM regulation 27(2) and (3), the line must be diverted or isolated and earthed. If neither is practicable, provide warning notices, barriers and suspended protection or equivalent measures, and keep to the safe distance set by the line owner , usually TNB. Plan the pump position so the boom cannot reach the line in any slew position. A spotter is not a substitute for planning.
Delivery hose: keep people away from the end hose during priming and blockage clearing. Do not kink or stand on lines.
Line pumps and pipelines
Secure pipelines independently of falsework unless the falsework design allows for them. Pumping surges can shake light props.
Couplings need correct clamps and pins. Damaged pipes are replaced, because worn pipes can burst.
Clearing blockages and cleaning with compressed air can fire debris and "sponge balls" out of the pipe at high speed. Release pressure first, follow the manufacturer's procedure, use catch cages and exclusion zones , and never uncouple a pressurised line.
Skips and crane pours
Skips and crane pours are lifting operations under Chapter 8:
- a lifting plan and a competent signaller
- a rated skip in good condition
- nobody under the load
operators of tower and mobile cranes who are competent persons under the Plant Requiring Certificate of Fitness Regulations 2024
Placing and compacting
Place evenly in layers as the pour sequence requires. Avoid heaping concrete in one place, which overloads part of the falsework (Section 7.2).
Watch for distress signs: bulging forms, moving props, cracking noises, unexpected sag. Stop the pour if any appear.
Edges: keep guardrails in place. Workers pulling hoses near edges are at risk of being pulled over.
Poker vibrators:
Electrical: use residual current device protection and reduced-voltage or battery tools where possible, with cables kept out of water and concrete (Chapter 9).
Hand-arm vibration: rotate operators and maintain equipment (Section 10.1).
Slips and trips: walk boards over reinforcement mesh; manage hoses and cables.
Manual handling: concrete, hoses and skips are heavy. Use mechanical handling and team lifts (Section 10.2).
Cement and concrete health hazards
Skin: wet cement is strongly alkaline . Prolonged contact, such as kneeling in wet concrete or concrete inside boots or gloves, can cause serious chemical burns . Repeated contact causes irritant and allergic dermatitis . Occupational dermatitis is listed in the NADOPOD Third Schedule , so diagnosed cases must be reported within 7 days on JKKP 7.
Eyes: splashes can cause serious injury. Wear eye protection and keep an eyewash nearby.
Dust: dry cement and cutting or grinding hardened concrete release dust, including respirable crystalline silica , which causes silicosis (Section 10.3).
Chemicals: admixtures, release agents and curing compounds. Check the safety data sheets and labels (CLASS 2013) and include them in the USECHH chemical register and assessment.
Controls:
- waterproof gloves and boots with trousers worn outside the boots
- long sleeves
- washing facilities with clean water on site (CDM Second Schedule)
- prompt washing of skin contamination
- health surveillance where the chemical health risk assessment calls for it
- Night pours, long pours and heat
Lighting (CDM regulation 37): suitable and sufficient lighting on the deck, access routes and truck routes, with secondary (emergency) lighting where failure of the main lights would create danger. Coloured lighting must not change how safety signs look.
Fatigue: long pours and back-to-back shifts lead to fatigue errors. Plan crew changes (Section 10.4).
Heat: daytime pours on exposed decks drive heat stress. Provide water, shade and rest breaks as DOSH's heat stress guideline sets out (Section 10.1).
Weather: rain changes slip risk and concrete quality, and lightning stops all deck and boom work.
Striking and back-propping
Permit to strike: strike only when the designer's or engineer's criteria are met, such as minimum cube strength, age or curing conditions. The repealed BOWEC regulation 31 required the Professional Engineer's specification and approval before stripping.
Order: follow the specified sequence. Vertical forms are usually struck earlier than slab and beam soffits, which carry load.
Back-props and reshores: install and keep them as designed to carry loads from the floors above. Remove only on authority.
During and after stripping: control the drop zone, lower formwork, clear stripped material promptly, and remove projecting nails and ties (CDM regulation 20).
Scenario: a night pour on Level 9
At 21:00 the boom pump is set up at the site entrance under an 11 kV line, with outriggers on unpadded fill. Floodlights cover the deck but not the stair access, and the falsework permit has not been signed. The SSS stops the start and:
Relocates the pump to the pre-planned pad position away from the line. The line owner's safe distance and the barrier arrangement are confirmed in the lift and pour plan (CDM regulation 27).
Has the outriggers set on the manufacturer's pads on firm ground, checked by the pump operator.
Arranges extra lighting for the stairs and the truck route, with secondary lighting (regulation 37).
Has the temporary works coordinator inspect and sign the permit to load before the first truck discharges.
Briefs the crew on the stop signals and the watcher's role.