8.3 Lift Planning, Load Charts, Sling Angles and Crane Signalling
NIOSH Site Safety Supervisor SSS
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The SSS Role & Malaysian OSH Legislation
1.1 The Site Safety Supervisor: Legal Appointment, DOSH Registration & Core Duties 1.2 OSHA 1994 as Amended by Act A1648: Structure, Duties, Rights & Penalties 1.3 Regulations Under OSHA 1994 That a Site Safety Supervisor Applies 1.4 CDM Regulations 2024: Duty Holders, Notification, Plans and Site Requirements
2 Chapter 2: OSH Management Systems, Human Factors & Risk Management
2.1 OSH Management Systems: Planning, OSH Policy, Site Organisation & Safety Committees 2.2 Human and Behavioural Factors in Construction Safety 2.3 HIRARC and the General Principles of Prevention 2.4 Safe Work Procedures and Permit-to-Work Systems 2.5 Monitoring, Accident Investigation, NADOPOD Reporting, Record Keeping & Audit
3 Chapter 3: Site Planning, General Control, Welfare & Communication
3.1 Site Initial Planning, Hoarding, Access and Vehicle & Plant Movement 3.2 General Control and Welfare: Housekeeping, Storage, Site Security, Welfare Facilities and First Aid 3.3 Safety Communication: Site Induction, Toolbox Meetings, Signs and Safety Promotion
4 Chapter 4: Working at Height & Fall Protection
4.1 Working at Height: Legal Basis, Fall Physics and the Fall-Control Hierarchy 4.2 Collective Fall Protection: Guardrails, Floor Openings, Nets and Catch Platforms 4.3 Personal Fall Protection, Ladders, MEWPs and Rescue from Height
5 Chapter 5: Scaffolding: Components, Design, Erection & Inspection
5.1 Scaffolding Types, Components, Foundations, Bracing and Tower Scaffolds 5.2 Scaffold Design, Loading, Competent Scaffolders and Safe Erection & Dismantling 5.3 Scaffold Inspection, Tagging Systems and Records
6 Chapter 6: Excavation, Shoring & Underground Services
6.1 Excavation Hazards, Soil Behaviour and Pre-Excavation Investigation 6.2 Protecting Excavation Sides: Battering, Benching, Shoring and Trench Support Systems 6.3 Deep Excavations, Retaining Systems, Cofferdams & Caissons, Monitoring and Rescue 6.4 Excavation Access, Edge Protection, Inspection Reports, Underground Services, Water and Air
7 Chapter 7: Piling, Formwork & Falsework, Concrete Work & Demolition
7.1 Piling Operations: Rigs, Working Platforms, Driven and Bored Piles 7.2 Formwork and Falsework: Temporary Works Design, Erection, Inspection and Loading 7.3 Concrete Work: Pre-Pour Checks, Pumping and Placing, Cement Health Hazards and Striking 7.4 Demolition and Dismantling: Surveys, Written Arrangements, Methods, Debris and Asbestos
8 Chapter 8: Lifting Operations, Work Equipment & Mobile Plant
8.1 Cranes and Hoists: Certificates of Fitness, Competent Operators, Ground and Crane Safety 8.2 Lifting Tackle and Rigging: Slings, Shackles, Hooks, Inspection and Discard 8.3 Lift Planning, Load Charts, Sling Angles and Crane Signalling 8.4 Work Equipment and Mobile Plant: Earthmoving Machines, Hand and Power Tools, Compressors and Guarding
9 Chapter 9: Electrical Safety, Fire & Hot Work, and Confined Spaces
9.1 Electrical Safety on Construction Sites: Temporary Supply, RCDs, Competent Persons and Safe Isolation 9.2 Fire Safety, Emergency Arrangements, Hot Work and Welding 9.3 Confined Spaces: The 2010 ICOP, Hazardous Atmospheres, Roles, Permits and Rescue
10 Chapter 10: Occupational Health Hazards & Controls
10.1 Physical Hazards: Noise, Vibration, Heat Stress, Radiation and Lighting 10.2 Musculoskeletal Hazards: Manual Handling and Ergonomics on Construction Sites 10.3 Chemical and Biological Hazards: USECHH, CLASS, Silica, Asbestos, Lead and Site Infections 10.4 Psychological Health: Psychosocial Hazards, Stress, Fatigue, Violence and Substance Misuse 10.5 Personal Protective Equipment and Site Emergency Response
11 Chapter 11: The SSS Examination: Paper 1, Site Assessment & Presentation
11.1 The SSS Examination: Entry Rules, Format, Retakes and Paper 1 Technique 11.2 Paper 2: Site Visit Practice, the Site Assessment and the Online HIRARC Presentation
8.3 Lift Planning, Load Charts, Sling Angles and Crane Signalling
Key Takeaways Explain This Topic AI
Regulation 15(2) of the Plant Requiring Certificate of Fitness Regulations 2024 requires the owner or occupier to establish a lifting plan for tower and mobile crane operations, taking the risk assessment report into account.
A crane's rated capacity falls as radius increases, so the duty chart must be read for the actual radius, boom length and configuration, and the load must include the hook block and lifting tackle.
Each leg of a two-leg sling carries the load divided by 2 times the cosine of the leg's angle from vertical, so at a 60-degree included angle each leg carries about 58% of the load.
At a 120-degree included sling angle, each leg of a two-leg sling carries a tension equal to the whole load, double what it carries in a straight vertical lift.
Only one signaller should direct the crane at a time, but any person may give the emergency stop signal, and the operator must stop if signals are unclear.
Last updated: October 2026
The lifting plan
Regulation 15(2) of the Plant Requiring Certificate of Fitness Regulations 2024 requires the owner or occupier to establish a lifting plan, taking into account the risk assessment report , so the tower or mobile crane can be operated safely. The CDM 2024 construction phase plan should say how lifting is planned and controlled. Lifts involving heavy prefabricated components are Fourth Schedule particular-risk work.
Who is involved
Roles in the widely used British code BS 7121 (safe use of cranes):
Role Responsibility
Lift planner (appointed person) Plans the lift, selects the crane and tackle, writes the method, and briefs the team
Lift supervisor Supervises the lift on site in line with the plan
Crane operator Operates the crane; competent person under regulation 15(1); does pre-shift limit switch tests (15(3)(b)) and checks the ground (15(3)(c))
- Rigger or slinger Selects and attaches tackle as planned; checks it before use
- Signaller (banksman) Directs the operator; one person at a time
The SSS audits the plan and checks on site that the lift matches it.
Contents of a lift plan
The load: weight from documents or calculation, centre of gravity, lifting points, dimensions, fragility.
The crane: type and configuration (boom length, counterweight, outrigger extension), certificate of fitness, operator.
Radius and capacity: maximum radius during the lift, including slewing and placing; capacity from the duty chart; percentage utilisation.
Ground and set-up: ground bearing pressure under the tracks or outriggers; mats; distance from excavations and slopes.
Tackle: slings, shackles, spreader beams and their ratings; sling angle; weight of tackle.
Environment: overhead lines (CDM regulation 27), structures, other cranes, public areas; wind speed limits; lighting.
Exclusion zones: barricades below the load path and around the counterweight's slew.
Communication: signaller, radio channel, hand signals; blind lifts.
Sequence and contingencies: step-by-step method; what happens if the load sticks, the wind rises or a fault occurs.
Emergency arrangements: rescue and first aid, including a crane cab emergency.
Many sites use categories :
- basic: a routine lift in good conditions, using a generic plan
- standard: a specific plan
complex: tandem lifts, lifts near power lines, heavy precast, or lifts above about 75–80% of capacity, needing an engineered plan and senior sign-off
Define the categories in the site lifting procedure.
Reading a duty (load) chart
A crane's rated capacity depends on its configuration and on the radius , the horizontal distance from the centre of rotation to the hook. Capacity falls quickly as radius increases.
Rules for using the chart:
Use the chart for the exact configuration : boom length, counterweight, outriggers fully extended or not, and the slewing area (over the rear, side or front).
Use the maximum radius reached during the lift, including where the load is placed. Slewing and the booms bending under load increase the radius.
Deduct from the chart capacity the weight of the hook block, slings, shackles and spreader beams , and any stowed jib if the manufacturer requires.
Do not interpolate unsafely between values. Use the next greater radius or the next shorter boom.
The rated capacity limiter (safe load indicator) supports the operator but does not replace planning. Never override it.
Worked example. A precast panel weighs 6.8 t . The hook block and tackle weigh 0.4 t , so the total load is 7.2 t . At the planned 18 m radius, with the boom length chosen, the duty chart shows 8.0 t for this configuration over the side.
Utilisation is 7.2 / 8.0 = 90% . That is too close for a wind-sensitive panel lift. The planner moves the crane to reduce the radius to 15 m, where the chart shows 10.5 t. Utilisation becomes 7.2 / 10.5 = 69% .
Sling angles and leg tension
When slings are not vertical, each leg carries more than its share of the load. For a sling with n equally loaded legs, each at angle θ from the vertical , the tension in each leg is: T = W n cos θ T = \frac{W}{n \cos\theta} T = n cos θ W
- Included angle between legs Angle of each leg from vertical (θ) Tension per leg in a two-leg sling (W = load)
- 0° (vertical legs) 0° 0.50 W
- 60° 30° 0.58 W
- 90° 45° 0.71 W
- 120° 60° 1.00 W
At a 120° included angle, each leg carries a tension equal to the whole load , twice the vertical case. Many lifting codes and manufacturers limit multi-leg slings to an included angle of 90° for normal rated use, and treat 120° as an absolute maximum. Keep sling angles narrow by using longer slings or a spreader beam.
Worked example. A 4.0 t load is lifted with a two-leg chain sling at a 60° included angle (θ = 30°): T = 4.0 2 × cos 30 ∘ = 4.0 2 × 0.866 = 2.31 t per leg T = \frac{4.0}{2 \times \cos 30^\circ} = \frac{4.0}{2 \times 0.866} = 2.31\ \text{t per leg} T = 2 × cos 3 0 ∘ 4.0 = 2 × 0.866 4.0 = 2.31 t per leg
Check the chain sling's tag. Multi-leg slings are rated at stated angle ranges, typically 0–45° and 45–60° from vertical, and the rated capacity at the actual angle must exceed the load.
Remember also:
Choke hitches reduce a sling's capacity, typically to about 80% for many slings. Use the manufacturer's mode factors.
Basket hitches can increase capacity only if both legs are vertical and the load is balanced.
Uneven legs or an offset centre of gravity put more load on one leg than the formula assumes.
Signalling and communication
One signaller directs the crane at a time, and is identified clearly, for example by a coloured vest. Anyone may give the emergency stop.
Use standard hand signals , such as those in ISO 16715 or BS 7121, agreed and briefed before the lift. Common signals:
Hoist: arm raised with forearm vertical, index finger pointing up, making small horizontal circles.
Lower: arm extended down, index finger pointing down, making small horizontal circles.
Stop: arm extended horizontally, palm down, held still.
Emergency stop: both arms extended, palms down, moved quickly back and forth.
Slew: arm extended pointing in the direction of slew.
Move slowly: one hand placed motionless over the hand giving the signal.
Radio: dedicated channel, identification at the start of each message, continuous communication during blind lifts, and an agreed signal for loss of contact, which means stop .
The operator must stop if signals are unclear, if communication is lost, or if anyone enters the danger zone.
Blind lifts , where the operator cannot see the load, need a signaller with a clear view of both the load and the operator, or a relay of signallers using radio, set out in the plan.
Scenario: the tandem lift that wasn't planned
Two mobile cranes are about to tandem-lift a 22 m steel girder. The "plan" is a sketch with no individual crane loads, the girder's centre of gravity is unknown, and one crane's operator is using a different radio channel. The SSS halts the lift because:
- a tandem lift is a complex lift
- each crane's share of the load changes as the girder tilts or the cranes move
- the regulation 15(2) lifting plan must be based on a proper risk assessment
The lift resumes only after an engineered plan:
- the girder's weight and centre of gravity are calculated
- each crane is limited to a reduced percentage of its capacity
- spreader beams keep slings vertical
- the radio channel is shared and the lift supervisor is named
- wind limits and an exclusion zone are set
- both operators record their limit switch tests before starting