9.2 Fire Safety, Emergency Arrangements, Hot Work and Welding

NIOSH Site Safety Supervisor SSS

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: The SSS Role & Malaysian OSH Legislation

1.1 The Site Safety Supervisor: Legal Appointment, DOSH Registration & Core Duties 1.2 OSHA 1994 as Amended by Act A1648: Structure, Duties, Rights & Penalties 1.3 Regulations Under OSHA 1994 That a Site Safety Supervisor Applies 1.4 CDM Regulations 2024: Duty Holders, Notification, Plans and Site Requirements

2 Chapter 2: OSH Management Systems, Human Factors & Risk Management

2.1 OSH Management Systems: Planning, OSH Policy, Site Organisation & Safety Committees 2.2 Human and Behavioural Factors in Construction Safety 2.3 HIRARC and the General Principles of Prevention 2.4 Safe Work Procedures and Permit-to-Work Systems 2.5 Monitoring, Accident Investigation, NADOPOD Reporting, Record Keeping & Audit

3 Chapter 3: Site Planning, General Control, Welfare & Communication

3.1 Site Initial Planning, Hoarding, Access and Vehicle & Plant Movement 3.2 General Control and Welfare: Housekeeping, Storage, Site Security, Welfare Facilities and First Aid 3.3 Safety Communication: Site Induction, Toolbox Meetings, Signs and Safety Promotion

4 Chapter 4: Working at Height & Fall Protection

4.1 Working at Height: Legal Basis, Fall Physics and the Fall-Control Hierarchy 4.2 Collective Fall Protection: Guardrails, Floor Openings, Nets and Catch Platforms 4.3 Personal Fall Protection, Ladders, MEWPs and Rescue from Height

5 Chapter 5: Scaffolding: Components, Design, Erection & Inspection

5.1 Scaffolding Types, Components, Foundations, Bracing and Tower Scaffolds 5.2 Scaffold Design, Loading, Competent Scaffolders and Safe Erection & Dismantling 5.3 Scaffold Inspection, Tagging Systems and Records

6 Chapter 6: Excavation, Shoring & Underground Services

6.1 Excavation Hazards, Soil Behaviour and Pre-Excavation Investigation 6.2 Protecting Excavation Sides: Battering, Benching, Shoring and Trench Support Systems 6.3 Deep Excavations, Retaining Systems, Cofferdams & Caissons, Monitoring and Rescue 6.4 Excavation Access, Edge Protection, Inspection Reports, Underground Services, Water and Air

7 Chapter 7: Piling, Formwork & Falsework, Concrete Work & Demolition

7.1 Piling Operations: Rigs, Working Platforms, Driven and Bored Piles 7.2 Formwork and Falsework: Temporary Works Design, Erection, Inspection and Loading 7.3 Concrete Work: Pre-Pour Checks, Pumping and Placing, Cement Health Hazards and Striking 7.4 Demolition and Dismantling: Surveys, Written Arrangements, Methods, Debris and Asbestos

8 Chapter 8: Lifting Operations, Work Equipment & Mobile Plant

8.1 Cranes and Hoists: Certificates of Fitness, Competent Operators, Ground and Crane Safety 8.2 Lifting Tackle and Rigging: Slings, Shackles, Hooks, Inspection and Discard 8.3 Lift Planning, Load Charts, Sling Angles and Crane Signalling 8.4 Work Equipment and Mobile Plant: Earthmoving Machines, Hand and Power Tools, Compressors and Guarding

9 Chapter 9: Electrical Safety, Fire & Hot Work, and Confined Spaces

9.1 Electrical Safety on Construction Sites: Temporary Supply, RCDs, Competent Persons and Safe Isolation 9.2 Fire Safety, Emergency Arrangements, Hot Work and Welding 9.3 Confined Spaces: The 2010 ICOP, Hazardous Atmospheres, Roles, Permits and Rescue

10 Chapter 10: Occupational Health Hazards & Controls

10.1 Physical Hazards: Noise, Vibration, Heat Stress, Radiation and Lighting 10.2 Musculoskeletal Hazards: Manual Handling and Ergonomics on Construction Sites 10.3 Chemical and Biological Hazards: USECHH, CLASS, Silica, Asbestos, Lead and Site Infections 10.4 Psychological Health: Psychosocial Hazards, Stress, Fatigue, Violence and Substance Misuse 10.5 Personal Protective Equipment and Site Emergency Response

11 Chapter 11: The SSS Examination: Paper 1, Site Assessment & Presentation

11.1 The SSS Examination: Entry Rules, Format, Retakes and Paper 1 Technique 11.2 Paper 2: Site Visit Practice, the Site Assessment and the Online HIRARC Presentation

9.2 Fire Safety, Emergency Arrangements, Hot Work and Welding

Key Takeaways Explain This Topic AI

CDM 2024 regulation 31 requires suitable and sufficient steps to prevent risk of injury from fire or explosion, flooding, or any substance liable to cause asphyxiation.

CDM 2024 regulation 32 requires emergency arrangements, including evacuation procedures, that everyone on site is familiar with and that are tested by being put into effect at suitable intervals.

Under CDM 2024 regulation 34, fire-fighting equipment and fire detection and alarm systems must be suitable, sited, signed, examined, tested and maintained, every worker must be instructed in their correct use, and work with a particular fire risk may be done only after suitable instruction.

A widely used hot work standard, NFPA 51B, requires combustibles within 11 metres (35 feet) of hot work to be removed or protected, and a fire watch for at least 30 minutes after the work ends.

USECHH 2000 requires a chemical health risk assessment where welding fumes or other hazardous chemicals are present, and approved respiratory protection only where other controls are impracticable or inadequate.

Last updated: October 2026

Fire risks on construction sites

A fire needs fuel, heat and oxygen , which is the fire triangle. Remove any one and the fire goes out. Construction sites have plenty of all three:

Fuels: timber formwork, packaging, plastic sheeting, insulation, paints and solvents, diesel, LPG and acetylene, waste skips

Ignition sources: welding, cutting and grinding sparks, torch-on roofing, faulty electrics, overloaded cables, smoking, generators and hot engines, arson

Oxygen: air, plus oxygen cylinders, which make materials burn fiercely, and leaking oxygen hoses that enrich clothing

High-rise buildings under construction are especially vulnerable: fire protection systems are incomplete, escape routes change week by week, and fire services may struggle to reach upper floors.

The law: CDM 2024 regulations 31 to 34

Reg. Requirement (summary)

31 Suitable and sufficient steps to prevent, so far as practicable, risk of injury from fire or explosion , flooding , or any substance liable to cause asphyxiation

32 Where necessary, emergency arrangements , including evacuation of the site or any part of it, taking account of: the type of work; the site's size and characteristics and the number and location of workplaces; the plant used; the number of people likely to be present; and the physical and chemical properties of substances present. Everyone must be familiar with the arrangements, and they must be tested by being put into effect at suitable intervals , which means drills

33 Sufficient emergency routes and exits , leading as directly as possible to an identified safe area; signed ; kept clear ; emergency lighting where needed

34 Fire-fighting equipment and fire detection and alarm systems where needed: suitably sited and signed; examined, tested and maintained at suitable intervals; non-automatic equipment easily accessible ; every worker instructed in the correct use of fire-fighting equipment; work with a particular fire risk may be done only after suitable instruction

These are construction-site duties of the contractor. Most breaches carry up to RM500,000 or one year or both. The Fire and Rescue Department of Malaysia (JBPM, BOMBA) is the fire authority under the Fire Services Act 1988 (Act 341) , and building fire safety for completed buildings falls under the Uniform Building By-Laws 1984 . Coordinate with the local fire station on access for fire engines, hydrants and high-rise firefighting.

The site fire plan

A fire and emergency section of the construction phase plan should cover:

Fire risk assessment by area and phase: stores, waste areas, hot work locations, basements, upper floors.

Prevention:

  • housekeeping and frequent waste removal
  • storage of flammables and gas cylinders (Section 3.2)
  • smoking only in designated areas
  • electrical safety (Section 9.1)
  • hot work control
  • security against arson

Detection and alarm: a site alarm that can be heard everywhere, for example sirens or air horns on each floor, with fire detection in cabins, stores and finished areas.

Fire-fighting equipment: extinguishers at stores, hot work points, plant, each floor and stair; temporary dry risers or hose reels on high-rise sites as the design progresses.

Escape: at least two escape routes where practicable, protected stairs, signed routes, emergency lighting, assembly points, and a roll-call system.

People: fire wardens on each floor or zone, trained in extinguisher use and evacuation, and first-aiders.

Drills: evacuation drills at suitable intervals, with lessons recorded (regulation 32(3)(b)).

Extinguishers and fire classes

Fire classes under the common international system (EN 2 and ISO 3941):

  • Class Fuel Suitable extinguishers
  • A Ordinary solids: timber, paper, textiles, plastics Water, foam, multipurpose (ABC) dry powder
  • B Flammable liquids: diesel, petrol, solvents, paint Foam, dry powder, carbon dioxide

C Flammable gases: LPG, acetylene Isolate the gas supply first; dry powder to knock down a fire if it is safe to do so

  • D Combustible metals Special metal-fire powder only
  • F Cooking oils and fats Wet chemical; never water

Electrical (energised equipment) Fires involving live equipment (not a separate EN 2 class) Carbon dioxide or dry powder after isolating the supply where possible; never water or foam on live equipment

Use extinguishers with the PASS method:

P ull the pin.

A im at the base of the fire.

S queeze the handle.

S weep across the fire.

Always keep an escape route behind you. Tackle a fire only if it is small, you are trained, and the alarm has been raised.

Hot work control

Hot work is any work producing flames, sparks or heat that could ignite materials: welding, gas cutting, grinding, brazing, soldering and torch-on waterproofing. Regulation 34(6) of CDM 2024 means hot work may be done only by people who have been suitably instructed . Most sites use a hot work permit (Section 2.4).

Typical hot work permit conditions, based on the widely used NFPA 51B standard:

Look for alternatives first, such as bolting instead of welding, or cold cutting.

Remove or protect combustibles within 11 m (35 ft) . Cover openings, gaps and drains so sparks cannot fall to lower floors.

Check walls, ceilings and floors for combustibles on the other side.

A fire extinguisher at the work, and a trained fire watch throughout and for at least 30 minutes after the work stops.

Gas testing where flammable vapours may be present, such as tanks, drains and basements.

Fit gas cutting sets with flashback arrestors and hose check valves. Check hoses for damage, close cylinders after use, and keep cylinders upright and secured.

Return the permit and inspect the area before close-out.

Hot work inside a confined space needs both permits. The confined space permit is the overriding permit (ICOP 2010), and the ICOP's Appendix C gives extra recommendations for hot work in confined spaces.

Welding and cutting: health and safety hazards

Hazard Effect Controls

Arc radiation (UV and IR) "Arc eye" (photokeratitis), skin burns, eye damage Welding helmet with the correct filter shade; welding screens or curtains to protect others; covered skin

Fumes and gases Metal fume fever; lung irritation; long-term effects from manganese, chromium and nickel in stainless steel; ozone and nitrogen oxides Chemical health risk assessment under USECHH; local exhaust ventilation or fume extraction; good general ventilation; approved respirators where needed; extra care in confined spaces

Electric shock Shock from the welding circuit, especially in wet or confined conductive areas Dry gloves and clothing; insulated electrode holders; correct earthing and return leads; voltage-reducing devices where available

Burns and fire Spatter, hot metal, sparks Flame-retardant clothing, gauntlets, safety boots; hot work permit controls

Gas cylinder hazards Leaks, fire, explosion; oxygen enrichment Secured upright cylinders; flashback arrestors; leak checks; never use oxygen to "sweeten" air

Noise Hearing loss from air-arc gouging, grinding Noise assessment; hearing protection zones (Noise Exposure Regulations 2019)

Working position Awkward postures, working at height Ergonomic set-up; platforms with guardrails

USECHH regulation 15 applies the hierarchy to welding fume: for example, a process change, local exhaust ventilation and safe work practices, with approved PPE only where other controls are impracticable, as an interim measure, or as a top-up (regulation 16).

Scenario: sparks through the slab

A welder fixes steel brackets on Level 6 next to an unprotected service opening. Directly below, on Level 5, plastic-wrapped insulation is stacked against a hoarding. There is no fire watch, and the hot work permit is signed but the conditions are not met. The SSS stops the work and:

Gets the opening covered and the insulation moved outside the 11 m zone on both levels.

Sets up a welding screen, an extinguisher at hand and a fire watch posted on Level 5. The fire watch stays at least 30 minutes after work ends.

Has the permit reissued after the issuer's physical check. The fire watch signs off the close-out inspection.

Adds "openings below hot work" to the permit checklist, and briefs all welders at the next toolbox meeting.