Study guide

10.3 Chemical and Biological Hazards: USECHH, CLASS, Silica, Asbestos, Lead and Site Infections

NIOSH Site Safety Supervisor SSS

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: The SSS Role & Malaysian OSH Legislation

1.1 The Site Safety Supervisor: Legal Appointment, DOSH Registration & Core Duties 1.2 OSHA 1994 as Amended by Act A1648: Structure, Duties, Rights & Penalties 1.3 Regulations Under OSHA 1994 That a Site Safety Supervisor Applies 1.4 CDM Regulations 2024: Duty Holders, Notification, Plans and Site Requirements

2 Chapter 2: OSH Management Systems, Human Factors & Risk Management

2.1 OSH Management Systems: Planning, OSH Policy, Site Organisation & Safety Committees 2.2 Human and Behavioural Factors in Construction Safety 2.3 HIRARC and the General Principles of Prevention 2.4 Safe Work Procedures and Permit-to-Work Systems 2.5 Monitoring, Accident Investigation, NADOPOD Reporting, Record Keeping & Audit

3 Chapter 3: Site Planning, General Control, Welfare & Communication

3.1 Site Initial Planning, Hoarding, Access and Vehicle & Plant Movement 3.2 General Control and Welfare: Housekeeping, Storage, Site Security, Welfare Facilities and First Aid 3.3 Safety Communication: Site Induction, Toolbox Meetings, Signs and Safety Promotion

4 Chapter 4: Working at Height & Fall Protection

4.1 Working at Height: Legal Basis, Fall Physics and the Fall-Control Hierarchy 4.2 Collective Fall Protection: Guardrails, Floor Openings, Nets and Catch Platforms 4.3 Personal Fall Protection, Ladders, MEWPs and Rescue from Height

5 Chapter 5: Scaffolding: Components, Design, Erection & Inspection

5.1 Scaffolding Types, Components, Foundations, Bracing and Tower Scaffolds 5.2 Scaffold Design, Loading, Competent Scaffolders and Safe Erection & Dismantling 5.3 Scaffold Inspection, Tagging Systems and Records

6 Chapter 6: Excavation, Shoring & Underground Services

6.1 Excavation Hazards, Soil Behaviour and Pre-Excavation Investigation 6.2 Protecting Excavation Sides: Battering, Benching, Shoring and Trench Support Systems 6.3 Deep Excavations, Retaining Systems, Cofferdams & Caissons, Monitoring and Rescue 6.4 Excavation Access, Edge Protection, Inspection Reports, Underground Services, Water and Air

7 Chapter 7: Piling, Formwork & Falsework, Concrete Work & Demolition

7.1 Piling Operations: Rigs, Working Platforms, Driven and Bored Piles 7.2 Formwork and Falsework: Temporary Works Design, Erection, Inspection and Loading 7.3 Concrete Work: Pre-Pour Checks, Pumping and Placing, Cement Health Hazards and Striking 7.4 Demolition and Dismantling: Surveys, Written Arrangements, Methods, Debris and Asbestos

8 Chapter 8: Lifting Operations, Work Equipment & Mobile Plant

8.1 Cranes and Hoists: Certificates of Fitness, Competent Operators, Ground and Crane Safety 8.2 Lifting Tackle and Rigging: Slings, Shackles, Hooks, Inspection and Discard 8.3 Lift Planning, Load Charts, Sling Angles and Crane Signalling 8.4 Work Equipment and Mobile Plant: Earthmoving Machines, Hand and Power Tools, Compressors and Guarding

9 Chapter 9: Electrical Safety, Fire & Hot Work, and Confined Spaces

9.1 Electrical Safety on Construction Sites: Temporary Supply, RCDs, Competent Persons and Safe Isolation 9.2 Fire Safety, Emergency Arrangements, Hot Work and Welding 9.3 Confined Spaces: The 2010 ICOP, Hazardous Atmospheres, Roles, Permits and Rescue

10 Chapter 10: Occupational Health Hazards & Controls

10.1 Physical Hazards: Noise, Vibration, Heat Stress, Radiation and Lighting 10.2 Musculoskeletal Hazards: Manual Handling and Ergonomics on Construction Sites 10.3 Chemical and Biological Hazards: USECHH, CLASS, Silica, Asbestos, Lead and Site Infections 10.4 Psychological Health: Psychosocial Hazards, Stress, Fatigue, Violence and Substance Misuse 10.5 Personal Protective Equipment and Site Emergency Response

11 Chapter 11: The SSS Examination: Paper 1, Site Assessment & Presentation

11.1 The SSS Examination: Entry Rules, Format, Retakes and Paper 1 Technique 11.2 Paper 2: Site Visit Practice, the Site Assessment and the Online HIRARC Presentation

10.3 Chemical and Biological Hazards: USECHH, CLASS, Silica, Asbestos, Lead and Site Infections

Key Takeaways Explain This Topic AI

USECHH 2000 requires employers to keep a register of chemicals hazardous to health, have a chemical health risk assessment carried out by a registered assessor, and act on its recommendations within one month.

USECHH regulation 15 sets the control order: elimination, substitution, total enclosure, isolation, process modification, engineering control equipment, safe work systems and, last, approved personal protective equipment.

Asbestos, benzene, free crystalline silica, isocyanates and lead are listed in Schedule II of USECHH 2000 as chemicals for which medical surveillance is appropriate, at intervals of no more than 12 months.

The OSH (Prohibition of Use of Substance) Order 1999 prohibits the use of crocidolite (blue asbestos) for all purposes except research or analysis.

Leptospirosis, viral hepatitis and pneumoconioses such as silicosis and asbestosis are listed occupational diseases in the Third Schedule of NADOPOD 2004, reportable within 7 days.

Last updated: October 2026

How chemicals harm

Chemicals enter the body by:

inhalation: dusts, fumes, vapours and gases. This is the main route on construction sites.

  • skin contact: cement, solvents and epoxy resins
  • ingestion: eating or smoking with contaminated hands
  • injection: high-pressure fluid or cuts

Effects may be:

acute: burns, poisoning, asphyxiation, dizziness

chronic: silicosis, asbestosis and mesothelioma, cancer, nerve damage, sensitisation (dermatitis, occupational asthma)

USECHH 2000: the employer's duties

The OSH (Use and Standards of Exposure of Chemicals Hazardous to Health) Regulations 2000 apply wherever chemicals hazardous to health are used.

Duty Regulation Requirement

Register 5 Identify and record all chemicals hazardous to health used at the workplace; keep the register updated and accessible to exposed employees

Exposure limits 6–8 Exposure must not exceed the permissible exposure limits (ceiling limits and 8-hour time-weighted averages)

Assessment of risk to health (CHRA) 9–12 Carried out by a registered assessor ; reviewed after a significant change, after five years , or when DOSH directs

Action 14 Carry out the recommended actions within one month of receiving the report; reduce exposure below the PELs, or to the lowest practicable level

Controls 15 In order: elimination; substitution; total enclosure; isolation; process modification; engineering control equipment; safe work systems; approved PPE . Safe work systems are documented and reviewed

PPE 16 Approved PPE only where other controls are impracticable, as an interim measure, or as a top-up; suitable, fitted, issued, maintained, with training

Engineering control equipment 17–19 Inspected at least monthly ; examined and tested by a hygiene technician at least every 12 months ; local exhaust ventilation designed and tested by a registered Professional Engineer; records kept

  • Labelling 20–21 Containers labelled; relabelled if labels are lost or contents are decanted
  • Information and training 22–24 Workers told the risks, precautions, and monitoring and surveillance results
  • Safety data sheets 25 Available at the workplace

Exposure monitoring 26 By a hygiene technician where the assessment requires it (gas and oxygen checks before confined space entry excepted); Schedule II chemicals at least every six months ; personal records kept 30 years

Health surveillance 27 By an occupational health doctor ; Schedule II chemicals at least every 12 months ; records kept 30 years

Medical removal 28 Remove workers at increased risk, including pregnant or breastfeeding employees on medical advice

Warning signs 29 At entrances to hazardous areas, in Bahasa Malaysia and English, dark red on white

Schedule II, chemicals for which medical surveillance is appropriate, includes asbestos, benzene, free crystalline silica, isocyanates, lead and its compounds , cadmium and arsenic, among others.

CLASS 2013: labels and safety data sheets

The OSH (Classification, Labelling and Safety Data Sheet of Hazardous Chemicals) Regulations 2013 put the UN Globally Harmonized System (GHS) into Malaysian law, with the detail in DOSH's ICOP on chemical classification and hazard communication.

Classification: the principal supplier classifies each chemical.

Label: the label shows the product identifier, supplier identification, signal word ("Danger" or "Warning", never both), hazard statements , pictograms (a black symbol on a white background in a red-bordered diamond) and precautionary statements , in Bahasa Malaysia and English (regulations 8 and 9).

Safety data sheet: the supplier provides an SDS with 16 headings in a fixed order, in both languages, and revises it when new information appears or every five years (regulation 13).

On site the SSS checks that every chemical has a label and an SDS before use, that decanted containers are labelled, and that the SDS information on PPE, storage, spills and first aid is followed.

Construction chemical hazards

Hazard Where it arises Health effect Key controls

Wet cement and concrete Concreting, plastering, mortar Alkaline burns; irritant and allergic dermatitis Gloves, boots, long sleeves; washing facilities; skin care; report dermatitis (NADOPOD)

Respirable crystalline silica Cutting, drilling, chasing, grinding, breaking concrete, block, brick or stone; dry sweeping Silicosis , lung cancer, COPD Water suppression or on-tool extraction; vacuum cleaning instead of dry sweeping; respirators to the CHRA; health surveillance (Schedule II)

Asbestos Old roof sheets, ceiling boards, pipe lagging, floor tiles in refurbishment or demolition Asbestosis, lung cancer, mesothelioma, often decades later Survey before work; do not disturb; specialist removal under DOSH's 2017 guidelines; crocidolite prohibited (1999 Order); scheduled waste disposal

Lead Removing old lead paint by burning or blasting; cutting coated steel Lead poisoning, affecting nerves, kidneys, blood and reproduction Avoid hot work on lead paint; wet methods; extraction; hygiene; health surveillance

Solvents Paints, thinners, adhesives, cleaning, especially in confined areas Dizziness, narcosis, liver and nerve damage; fire Water-based substitutes; ventilation; confined space controls; no ignition sources

Isocyanates and epoxies Polyurethane coatings, sealants, foams, epoxy resins Occupational asthma, skin sensitisation Substitution; supplied-air or suitable respirators when spraying; gloves; health surveillance

Welding and cutting fumes Steelwork, rebar welding, galvanised steel Metal fume fever, lung irritation, long-term effects Fume extraction; ventilation; respiratory protection (Section 9.2)

Diesel exhaust Plant and generators in basements and tunnels Irritation, lung disease; carbon monoxide poisoning Keep engines outside; ventilation; maintenance

Wood dust Formwork cutting, carpentry Irritation, asthma; some hardwood dusts cause cancer Extraction on saws; respiratory protection

Bitumen and torch-on membranes Roofing, waterproofing Burns, fumes, fire Hot work permit; ventilation; PPE

Pneumoconioses ( silicosis, asbestosis ) and occupational dermatitis appear in the NADOPOD Third Schedule . A diagnosed case must be reported within 7 days on form JKKP 7 .

Biological hazards on construction sites

Hazard Source Controls

Leptospirosis Bacteria in rat urine , contaminating water, mud and soil in excavations, drains and flooded areas Rodent control; good waste management; cover cuts; gloves and boots; washing facilities; early treatment if flu-like illness follows exposure

Dengue Aedes mosquitoes breeding in stagnant water in containers, tyres, roof slabs and lift pits Remove standing water daily; inspect for breeding; cooperate with health authority inspections (Destruction of Disease-Bearing Insects Act 1975); repellents

Tetanus Puncture wounds from nails and rusty metal Remove projecting nails (CDM regulation 20); first aid; tetanus vaccination

Hepatitis A and gastro-enteritis Sewage, contaminated water and food Clean drinking water; toilets and handwashing (CDM Second Schedule); hygiene

Legionella Stagnant water in tanks, cooling systems and hoses Flush and disinfect water systems; avoid spraying stagnant water

Tuberculosis and other respiratory infections Crowded worker accommodation Housing standards (Act 446); ventilation; health screening

Bird and bat droppings Old roofs and plant rooms during refurbishment Damp down before removal; respiratory protection

DOSH's 2015 excavation bulletin lists leptospirosis, gastro-enteritis, hepatitis A and tetanus as health hazards for groundworkers. Leptospirosis and viral hepatitis are listed in the NADOPOD Third Schedule for relevant work.

Scenario: chasing walls in a refurbishment

Electricians are cutting chases in brick walls with dry angle grinders in an enclosed corridor of a 1980s building. The dust is visible, and the ceiling boards above are a grey fibrous material. The SSS:

Stops the cutting, and keeps everyone out until the dust settles and is cleaned up with an H-class vacuum, not by sweeping.

Suspends work near the ceiling boards and arranges an asbestos survey . If asbestos is present, removal follows DOSH's 2017 guidelines, including DOSH acknowledgement, before the boards are disturbed.

Requires silica controls for the chasing: wall chasers with on-tool extraction , or wet cutting where electrics allow, plus respiratory protection specified by the CHRA. Ensures the chemicals register and CHRA cover silica, and that health surveillance follows Schedule II.

Briefs the electricians on why "just a bit of dust" can cause silicosis years later.