Study guide
3.3 Bidding, Markup, Overhead, and Profit
NASCLA Contractor Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Coverage Map & Exam Overview
Coverage Map & Exam Overview
2 Business Organization, Licensing & Law
1.1 Business Entity Types and Formation 1.2 NASCLA Trade-Exam Waiver and Agency Licensing Boundaries 1.3 Construction Contract Law and Types of Contracts 1.4 Lien Law, Bond Claims, and Dispute Resolution
3 Financial Management, Tax & Labor Law
2.1 Financial Statements, Job Costing, and Cash Flow 2.2 Payroll, Federal/State Tax, and Recordkeeping 2.3 Labor & Employment Law (FLSA, immigration/I-9, EEO) 2.4 Insurance, Surety Bonds, and Risk Management
4 Estimating, Bidding & Plan Reading
3.1 Reading Construction Drawings and Specifications (CSI MasterFormat) 3.2 Quantity Takeoff and Material Estimating 3.3 Bidding, Markup, Overhead, and Profit 3.4 Change Orders, Allowances, and Unit Pricing
5 Project Management & Scheduling
4.1 Project Delivery Methods and the Submittal/RFI Process 4.2 Scheduling (CPM, Bar Charts, Critical Path) 4.3 Quality Control, Inspections, and Closeout 4.4 Permits, Codes, and the Inspection Process
6 Construction Safety & OSHA (29 CFR 1926)
5.1 OSHA Administration, Recordkeeping, and the General Duty Clause 5.2 Fall Protection, Scaffolds, and Ladders 5.3 Excavation/Trenching, Electrical, and Hazard Communication 5.4 PPE, Fire Protection, Cranes, and Confined Spaces
7 General Requirements & Sitework
6.1 Division 01 General Requirements and Temporary Facilities 6.2 Surveying, Site Layout, and Excavation 6.3 Soils, Compaction, and Erosion/Sediment Control 6.4 Foundations, Footings, and Site Drainage
8 Concrete (CSI Division 03)
7.1 Concrete Materials, Mix Design, and Water-Cement Ratio 7.2 Formwork and Reinforcement Placement 7.3 Placing, Finishing, Curing, and Testing (slump, cylinders) 7.4 Concrete Defects, Joints, and Cold-Weather Practices
9 Masonry (CSI Division 04)
8.1 Masonry Units, Mortar Types (M/S/N/O), and Grout 8.2 Brick and CMU Bonds, Reinforcement, and Coursing 8.3 Lintels, Control/Expansion Joints, and Flashing 8.4 Masonry Estimating and Cold/Hot Weather Construction
10 Metals & Wood (CSI Divisions 05 & 06)
9.1 Structural Steel, Connections, and Welding/Bolting 9.2 Light-Gauge Metal Framing 9.3 Wood Framing, Species/Grades, and Fasteners 9.4 Engineered Wood, Trusses, and Load Paths
11 Thermal & Moisture Protection (CSI Division 07)
10.1 Waterproofing, Dampproofing, and Below-Grade Protection 10.2 Insulation, R-Values, and Vapor Barriers 10.3 Roofing Systems (steep-slope and low-slope) and Underlayment 10.4 Flashing, Sealants, and Air Barriers
12 Openings & Finishes (CSI Divisions 08 & 09)
11.1 Doors, Windows, Glazing, and Hardware 11.2 Gypsum Board, Plaster, and Framing 11.3 Flooring, Tile, and Acoustical Ceilings 11.4 Painting, Coatings, and Finish Schedules
13 Mechanical, Plumbing & Electrical Overview
12.1 Plumbing Systems, Fixtures, and DWV/Supply Basics 12.2 HVAC Systems and Load Concepts 12.3 Electrical Systems, Service, and NEC Basics 12.4 Coordination, Rough-In, and Energy Code
3.3 Bidding, Markup, Overhead, and Profit
Key Takeaways Explain This Topic AI
Separate job overhead (project-specific indirects) from general overhead (company-wide), and never charge the same cost twice.
Markup is a percent added to cost; margin is a percent of selling price, so 20 percent markup yields only a 16.7 percent margin.
To hit a target margin, divide cost by (1 minus the desired margin); a 20 percent margin needs a 25 percent markup.
Build the bid in order: direct cost, job overhead, general overhead share, profit, then contingency, bonds, and taxes.
Bid bonds run about 5 to 10 percent while performance bonds are typically 100 percent of the contract value.
Last updated: June 2026
Bidding, Markup, Overhead, and Profit
Once the takeoff is priced, the contractor converts direct costs into a bid price by adding overhead and profit. Direct costs are labor, material, equipment, and subcontractors for the project. Indirect costs ( overhead ) keep the business running. Profit is the return for risk and capital. Mishandling these is the fastest route to insolvency, so the NASCLA business-and-project-management material treats markup math heavily.
Overhead: Job vs. General
There are two overhead buckets in this guide:
Job (project) overhead is directly attributable to one project: temporary toilets, the site superintendent, the jobsite trailer, dumpsters, permits, project insurance. It is often estimated as a line item.
General (company) overhead is the cost of running the company regardless of any single job: office rent, estimator salaries, accounting, advertising, licensing. It is recovered as a percentage spread across all jobs , commonly 5 to 15 percent of revenue.
A classic trap: counting the same cost in both buckets, which double-charges the owner and loses the bid.
Markup Is Not the Same as Margin
This is a core estimating concept. Markup is a percentage added to cost . Margin (profit margin) is a percentage of the selling price . They are not equal.
- Selling price = Cost x (1 + markup)
- Margin = (Selling price - Cost) / Selling price
Worked example: Cost = 100,000. Apply a 20 percent markup : price = 100,000 x 1.20 = 120,000 . The margin is (120,000 - 100,000) / 120,000 = 16.7 percent , not 20 percent. To achieve a 20 percent margin you must mark up by 25 percent: 100,000 / (1 - 0.20) = 125,000.
Markup-to-Margin Conversion Table
Use the divide-by-(1 minus desired margin) method to hit a target margin. Common conversions:
- Desired margin Required markup on cost
- 10% 11.1%
- 15% 17.6%
- 20% 25.0%
- 25% 33.3%
- 33.3% 50.0%
- 50% 100%
Reading it backward: a 50 percent markup only yields a 33.3 percent margin . The local practice questions contrast the two terms.
Building Up the Bid
A clean bid stacks costs in order so each markup applies to the right base:
Direct costs (labor + material + equipment + subs).
Add job overhead (project-specific indirects).
Add a proportional share of general overhead .
Add profit as the final markup.
Add contingency , bonds , and taxes per the bid documents.
Worked example: Direct cost 200,000; job overhead 15,000; general overhead at 10 percent of (215,000) = 21,500; subtotal 236,500; profit at 10 percent = 23,650; bid = 260,150 before bond and tax.
Bid Documents, Bonds, and Errors
Public and large commercial bids require surety bonds : a bid bond (often 5 to 10 percent of the bid) guarantees the contractor will sign; a performance bond (typically 100 percent of the contract ) guarantees completion; a payment bond protects subs and suppliers. The lowest responsive, responsible bidder generally wins. If a clerical bid error is discovered before award, most laws let the bidder withdraw with proof rather than be forced into a losing contract.