3.4 Change Orders, Allowances, and Unit Pricing
NASCLA Contractor Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Coverage Map & Exam Overview
Coverage Map & Exam Overview
2 Business Organization, Licensing & Law
1.1 Business Entity Types and Formation 1.2 NASCLA Trade-Exam Waiver and Agency Licensing Boundaries 1.3 Construction Contract Law and Types of Contracts 1.4 Lien Law, Bond Claims, and Dispute Resolution
3 Financial Management, Tax & Labor Law
2.1 Financial Statements, Job Costing, and Cash Flow 2.2 Payroll, Federal/State Tax, and Recordkeeping 2.3 Labor & Employment Law (FLSA, immigration/I-9, EEO) 2.4 Insurance, Surety Bonds, and Risk Management
4 Estimating, Bidding & Plan Reading
3.1 Reading Construction Drawings and Specifications (CSI MasterFormat) 3.2 Quantity Takeoff and Material Estimating 3.3 Bidding, Markup, Overhead, and Profit 3.4 Change Orders, Allowances, and Unit Pricing
5 Project Management & Scheduling
4.1 Project Delivery Methods and the Submittal/RFI Process 4.2 Scheduling (CPM, Bar Charts, Critical Path) 4.3 Quality Control, Inspections, and Closeout 4.4 Permits, Codes, and the Inspection Process
6 Construction Safety & OSHA (29 CFR 1926)
5.1 OSHA Administration, Recordkeeping, and the General Duty Clause 5.2 Fall Protection, Scaffolds, and Ladders 5.3 Excavation/Trenching, Electrical, and Hazard Communication 5.4 PPE, Fire Protection, Cranes, and Confined Spaces
7 General Requirements & Sitework
6.1 Division 01 General Requirements and Temporary Facilities 6.2 Surveying, Site Layout, and Excavation 6.3 Soils, Compaction, and Erosion/Sediment Control 6.4 Foundations, Footings, and Site Drainage
8 Concrete (CSI Division 03)
7.1 Concrete Materials, Mix Design, and Water-Cement Ratio 7.2 Formwork and Reinforcement Placement 7.3 Placing, Finishing, Curing, and Testing (slump, cylinders) 7.4 Concrete Defects, Joints, and Cold-Weather Practices
9 Masonry (CSI Division 04)
8.1 Masonry Units, Mortar Types (M/S/N/O), and Grout 8.2 Brick and CMU Bonds, Reinforcement, and Coursing 8.3 Lintels, Control/Expansion Joints, and Flashing 8.4 Masonry Estimating and Cold/Hot Weather Construction
10 Metals & Wood (CSI Divisions 05 & 06)
9.1 Structural Steel, Connections, and Welding/Bolting 9.2 Light-Gauge Metal Framing 9.3 Wood Framing, Species/Grades, and Fasteners 9.4 Engineered Wood, Trusses, and Load Paths
11 Thermal & Moisture Protection (CSI Division 07)
10.1 Waterproofing, Dampproofing, and Below-Grade Protection 10.2 Insulation, R-Values, and Vapor Barriers 10.3 Roofing Systems (steep-slope and low-slope) and Underlayment 10.4 Flashing, Sealants, and Air Barriers
12 Openings & Finishes (CSI Divisions 08 & 09)
11.1 Doors, Windows, Glazing, and Hardware 11.2 Gypsum Board, Plaster, and Framing 11.3 Flooring, Tile, and Acoustical Ceilings 11.4 Painting, Coatings, and Finish Schedules
13 Mechanical, Plumbing & Electrical Overview
12.1 Plumbing Systems, Fixtures, and DWV/Supply Basics 12.2 HVAC Systems and Load Concepts 12.3 Electrical Systems, Service, and NEC Basics 12.4 Coordination, Rough-In, and Energy Code
3.4 Change Orders, Allowances, and Unit Pricing
Key Takeaways Explain This Topic AI
A change order is a written, signed amendment; never perform extra work on a verbal direction if you expect to be paid.
Change-order pricing is direct cost plus contract-capped overhead and profit, often 10 percent each on self-performed work.
An allowance is a placeholder dollar sum for material cost; install labor, overhead, and profit usually stay in the base bid.
Unit prices pay the actual installed quantity at the bid rate and may allow renegotiation when quantities swing beyond about 15 to 25 percent.
Distinguish allowance (dollar placeholder), unit price (rate per unit), and contingency (reserve for the unforeseen).
Last updated: June 2026
Change Orders, Allowances, and Unit Pricing
Few commercial projects finish exactly as bid. Contracts therefore build in mechanisms to price changed, undefined, or variable-quantity work: the change order , the allowance , and unit pricing . The local exercises practice both the contract mechanics and the arithmetic, because mishandling these is a leading source of disputes and unpaid work.
Change Orders
A change order (CO) is a written, signed amendment to the contract that modifies the scope, price, or schedule. The governing rule: get it in writing and signed before performing the work. Verbal directions and unsigned field tickets are the top cause of payment disputes.
A CO price typically equals direct cost of the change + agreed overhead and profit markup . Contracts often cap CO markup, for example 10 percent overhead plus 10 percent profit on self-performed work and a lower percentage on subcontracted change work (commonly 5 percent on a sub's marked-up price).
Constructive Changes and the Paper Trail
Not all changes arrive as tidy COs. A constructive change occurs when the owner's act or direction effectively changes the work without a formal order, for example requiring inspection beyond the spec. Protect entitlement with the documents in order:
- Document Purpose
- RFI (Request for Information) Resolve a drawing/spec conflict
- CCD (Construction Change Directive) Owner orders work to proceed before price is settled
- Change Order Final signed price/time/scope amendment
Always follow the notice provisions and time limits in the contract or claims may be waived.
Allowances
An allowance is a dollar amount placed in the bid for work or materials not yet selected , such as a 12,000 lighting allowance or a 6 dollar per SF flooring allowance. The contractor includes that figure in the contract sum and reconciles it when the owner makes the actual selection.
Editorial practice point: the standard allowance covers material/equipment cost delivered to the site ; labor to install, overhead, and profit are normally carried in the base bid , not the allowance, unless the contract says otherwise. When actual cost differs, a CO adjusts the contract sum up or down by the difference.
Unit Pricing
A unit price is a pre-agreed price per unit of work used when the exact quantity is unknown at bid time, common for earthwork, rock excavation, undercut/import fill, and piling . The owner pays for the quantity actually installed at the bid unit rate.
Worked example: Unit price for rock excavation = 45 dollars per CY . The plan estimated 200 CY but field conditions yield 260 CY. Payment = 260 x 45 = 11,700 , an increase of 60 CY x 45 = 2,700 over the estimated 9,000. Many contracts allow renegotiation if actual quantity varies beyond a threshold (often +/- 15 to 25 percent ) of the estimate.
Allowance vs. Unit Price vs. Contingency
These three are easy to confuse in practice:
Allowance = a placeholder dollar sum for an undefined material/selection, reconciled by CO.
Unit price = a fixed rate per measured unit , paid on actual installed quantity.
Contingency = the contractor's or owner's reserve for unforeseen costs , not tied to a specific selection or unit.
A practice question gives an allowance overrun and asks for the adjustment: the contract sum changes only by the difference between the allowance and the actual reconciled cost , processed as a change order.