2.1 Financial Statements, Job Costing, and Cash Flow

NASCLA Contractor Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Coverage Map & Exam Overview

Coverage Map & Exam Overview

2 Business Organization, Licensing & Law

1.1 Business Entity Types and Formation 1.2 NASCLA Trade-Exam Waiver and Agency Licensing Boundaries 1.3 Construction Contract Law and Types of Contracts 1.4 Lien Law, Bond Claims, and Dispute Resolution

3 Financial Management, Tax & Labor Law

2.1 Financial Statements, Job Costing, and Cash Flow 2.2 Payroll, Federal/State Tax, and Recordkeeping 2.3 Labor & Employment Law (FLSA, immigration/I-9, EEO) 2.4 Insurance, Surety Bonds, and Risk Management

4 Estimating, Bidding & Plan Reading

3.1 Reading Construction Drawings and Specifications (CSI MasterFormat) 3.2 Quantity Takeoff and Material Estimating 3.3 Bidding, Markup, Overhead, and Profit 3.4 Change Orders, Allowances, and Unit Pricing

5 Project Management & Scheduling

4.1 Project Delivery Methods and the Submittal/RFI Process 4.2 Scheduling (CPM, Bar Charts, Critical Path) 4.3 Quality Control, Inspections, and Closeout 4.4 Permits, Codes, and the Inspection Process

6 Construction Safety & OSHA (29 CFR 1926)

5.1 OSHA Administration, Recordkeeping, and the General Duty Clause 5.2 Fall Protection, Scaffolds, and Ladders 5.3 Excavation/Trenching, Electrical, and Hazard Communication 5.4 PPE, Fire Protection, Cranes, and Confined Spaces

7 General Requirements & Sitework

6.1 Division 01 General Requirements and Temporary Facilities 6.2 Surveying, Site Layout, and Excavation 6.3 Soils, Compaction, and Erosion/Sediment Control 6.4 Foundations, Footings, and Site Drainage

8 Concrete (CSI Division 03)

7.1 Concrete Materials, Mix Design, and Water-Cement Ratio 7.2 Formwork and Reinforcement Placement 7.3 Placing, Finishing, Curing, and Testing (slump, cylinders) 7.4 Concrete Defects, Joints, and Cold-Weather Practices

9 Masonry (CSI Division 04)

8.1 Masonry Units, Mortar Types (M/S/N/O), and Grout 8.2 Brick and CMU Bonds, Reinforcement, and Coursing 8.3 Lintels, Control/Expansion Joints, and Flashing 8.4 Masonry Estimating and Cold/Hot Weather Construction

10 Metals & Wood (CSI Divisions 05 & 06)

9.1 Structural Steel, Connections, and Welding/Bolting 9.2 Light-Gauge Metal Framing 9.3 Wood Framing, Species/Grades, and Fasteners 9.4 Engineered Wood, Trusses, and Load Paths

11 Thermal & Moisture Protection (CSI Division 07)

10.1 Waterproofing, Dampproofing, and Below-Grade Protection 10.2 Insulation, R-Values, and Vapor Barriers 10.3 Roofing Systems (steep-slope and low-slope) and Underlayment 10.4 Flashing, Sealants, and Air Barriers

12 Openings & Finishes (CSI Divisions 08 & 09)

11.1 Doors, Windows, Glazing, and Hardware 11.2 Gypsum Board, Plaster, and Framing 11.3 Flooring, Tile, and Acoustical Ceilings 11.4 Painting, Coatings, and Finish Schedules

13 Mechanical, Plumbing & Electrical Overview

12.1 Plumbing Systems, Fixtures, and DWV/Supply Basics 12.2 HVAC Systems and Load Concepts 12.3 Electrical Systems, Service, and NEC Basics 12.4 Coordination, Rough-In, and Energy Code

2.1 Financial Statements, Job Costing, and Cash Flow

Key Takeaways Explain This Topic AI

Balance Sheet follows Assets = Liabilities + Owner's Equity; sureties expect a current ratio of about 1.5:1 and a quick ratio near 1.0:1.

Markup is on cost, margin is on selling price: a 25% markup equals only a 20% margin—convert margin to price with Cost / (1 − margin).

Job costing separates direct from indirect costs; allocate general overhead via a burden rate such as overhead / direct labor.

Retainage (typically 5%–10%) and underbilling drain cash even on profitable jobs; the WIP schedule reveals over/underbilling.

Percentage of completion = costs to date / total estimated costs, the basis for progress billings.

Last updated: June 2026

Financial Statements, Job Costing, and Cash Flow

The NASCLA Contractor's Guide to Business, Law and Project Management treats financial control as a central part of contractor operations. This editorial section explains three core reports: the Balance Sheet (assets = liabilities + owner's equity, a snapshot in time), the Income Statement (revenue minus expenses over a period, also called the Profit and Loss or P&L), and the Cash Flow Statement (actual cash in and out). Confusing profitability with liquidity is the common practical mistake.

Reading the Balance Sheet

The accounting equation never changes: Assets = Liabilities + Owner's Equity . Current assets (cash, accounts receivable, materials inventory) convert to cash within one year. Current liabilities (accounts payable, accrued payroll, the current portion of loans) are due within one year.

Two liquidity ratios appear repeatedly:

Current Ratio = Current Assets / Current Liabilities. A bonding company typically wants 1.5:1 or higher .

Quick (Acid-Test) Ratio = (Current Assets minus Inventory) / Current Liabilities; 1.0:1 is a common floor.

Markup vs. Margin (the #1 numeric trap)

These are NOT the same number. Markup is added to cost ; margin is a percentage of the selling price .

  • Term Formula Example (cost = $80,000)
  • Markup % (Price − Cost) / Cost 25% markup → price $100,000
  • Margin % (Price − Cost) / Price $100,000 price → 20% margin

A 25% markup equals only a 20% margin. To convert a desired margin to a markup multiplier, divide cost by (1 − margin). For a 20% margin on $80,000: $80,000 / (1 − 0.20) = $80,000 / 0.80 = $100,000 . Marking up cost by 20% would yield only $96,000 and undercut the job.

Job Costing and Overhead Allocation

Job costing assigns labor, material, equipment, and subcontractor costs to a specific project so you can compare actual to estimated. Direct costs tie to one job; indirect costs / general overhead (office rent, owner salary, insurance) must be spread across all jobs.

A common allocation method: overhead rate = total annual overhead / total annual direct labor cost. If overhead is $300,000 and direct labor is $1,200,000, the burden rate is 25% —add $0.25 of overhead to every $1.00 of field labor when bidding.

Cash Flow, Retainage, and the WIP Schedule

A profitable contractor can still fail from negative cash flow . Retainage (commonly 5%–10% withheld by the owner until completion) ties up cash you have already earned. The Work-in-Progress (WIP) schedule reconciles billings to costs:

Underbilling (costs/earnings exceed billings) = you are financing the owner; a red flag to sureties.

Overbilling (billings exceed earnings) = front-loaded cash, but it is a liability you owe in future work.

Percentage of completion = costs incurred to date / total estimated costs. If you have spent $400,000 of a $1,000,000 estimate, you are 40% complete and may bill 40% of the contract, less retainage.