Study guide

8.2 Brick and CMU Bonds, Reinforcement, and Coursing

NASCLA Contractor Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Coverage Map & Exam Overview

Coverage Map & Exam Overview

2 Business Organization, Licensing & Law

1.1 Business Entity Types and Formation 1.2 NASCLA Trade-Exam Waiver and Agency Licensing Boundaries 1.3 Construction Contract Law and Types of Contracts 1.4 Lien Law, Bond Claims, and Dispute Resolution

3 Financial Management, Tax & Labor Law

2.1 Financial Statements, Job Costing, and Cash Flow 2.2 Payroll, Federal/State Tax, and Recordkeeping 2.3 Labor & Employment Law (FLSA, immigration/I-9, EEO) 2.4 Insurance, Surety Bonds, and Risk Management

4 Estimating, Bidding & Plan Reading

3.1 Reading Construction Drawings and Specifications (CSI MasterFormat) 3.2 Quantity Takeoff and Material Estimating 3.3 Bidding, Markup, Overhead, and Profit 3.4 Change Orders, Allowances, and Unit Pricing

5 Project Management & Scheduling

4.1 Project Delivery Methods and the Submittal/RFI Process 4.2 Scheduling (CPM, Bar Charts, Critical Path) 4.3 Quality Control, Inspections, and Closeout 4.4 Permits, Codes, and the Inspection Process

6 Construction Safety & OSHA (29 CFR 1926)

5.1 OSHA Administration, Recordkeeping, and the General Duty Clause 5.2 Fall Protection, Scaffolds, and Ladders 5.3 Excavation/Trenching, Electrical, and Hazard Communication 5.4 PPE, Fire Protection, Cranes, and Confined Spaces

7 General Requirements & Sitework

6.1 Division 01 General Requirements and Temporary Facilities 6.2 Surveying, Site Layout, and Excavation 6.3 Soils, Compaction, and Erosion/Sediment Control 6.4 Foundations, Footings, and Site Drainage

8 Concrete (CSI Division 03)

7.1 Concrete Materials, Mix Design, and Water-Cement Ratio 7.2 Formwork and Reinforcement Placement 7.3 Placing, Finishing, Curing, and Testing (slump, cylinders) 7.4 Concrete Defects, Joints, and Cold-Weather Practices

9 Masonry (CSI Division 04)

8.1 Masonry Units, Mortar Types (M/S/N/O), and Grout 8.2 Brick and CMU Bonds, Reinforcement, and Coursing 8.3 Lintels, Control/Expansion Joints, and Flashing 8.4 Masonry Estimating and Cold/Hot Weather Construction

10 Metals & Wood (CSI Divisions 05 & 06)

9.1 Structural Steel, Connections, and Welding/Bolting 9.2 Light-Gauge Metal Framing 9.3 Wood Framing, Species/Grades, and Fasteners 9.4 Engineered Wood, Trusses, and Load Paths

11 Thermal & Moisture Protection (CSI Division 07)

10.1 Waterproofing, Dampproofing, and Below-Grade Protection 10.2 Insulation, R-Values, and Vapor Barriers 10.3 Roofing Systems (steep-slope and low-slope) and Underlayment 10.4 Flashing, Sealants, and Air Barriers

12 Openings & Finishes (CSI Divisions 08 & 09)

11.1 Doors, Windows, Glazing, and Hardware 11.2 Gypsum Board, Plaster, and Framing 11.3 Flooring, Tile, and Acoustical Ceilings 11.4 Painting, Coatings, and Finish Schedules

13 Mechanical, Plumbing & Electrical Overview

12.1 Plumbing Systems, Fixtures, and DWV/Supply Basics 12.2 HVAC Systems and Load Concepts 12.3 Electrical Systems, Service, and NEC Basics 12.4 Coordination, Rough-In, and Energy Code

8.2 Brick and CMU Bonds, Reinforcement, and Coursing

Key Takeaways Explain This Topic AI

Brick positions (stretcher, header, soldier, rowlock, sailor) control both appearance and structural tying; headers tie multi-wythe walls.

Running bond is standard; stack bond is weakest and requires added horizontal joint reinforcement (min 0.0007 of gross area, max 16 in spacing).

Nominal CMU height is 8 inches: 3 courses = 24 inches; divide wall height by 8 to count courses.

Three brick courses equal 8 inches, letting brick veneer align with CMU backup every 8 inches.

Bond beams carry horizontal rebar; vertical bar lap splices are typically 48 bar diameters with full grout surround.

Last updated: June 2026

Bonds, Reinforcement, and Coursing

A masonry bond is the pattern in which units are laid; it determines both appearance and how loads transfer between units. Editorial questions here contrast the difference between structural bonding (units actually interlock to tie wythes) and pattern bonding (purely visual face arrangement).

Know the names of the brick positions and orientations because plans and the reference text use them constantly.

Brick Positions

  • Position Description
  • Stretcher Laid flat, long face exposed (most common)
  • Header Laid flat, short end exposed; ties wythes together
  • Soldier Standing vertical, narrow face out (lintels, accents)
  • Rowlock On edge, end exposed (sills, caps)
  • Sailor Standing vertical, broad face out
  • Shiner / Rowlock stretcher On edge, broad face out

Header courses are the key to structural bonding in solid multi-wythe walls — they physically tie front and back wythes. The soldier course is the classic detail above windows and doors.

Common Bond Patterns

Running bond: each unit offset 1/2 unit from the course below; no headers. Standard for veneer and CMU.

Common (American) bond: running bond with a full header course every 5th, 6th, or 7th course to tie wythes.

Flemish bond: alternating stretchers and headers in every course.

English bond: alternating full courses of stretchers and headers.

Stack bond: units aligned vertically (no offset). Weak — requires horizontal joint reinforcement because there is no natural overlap.

Drainage check: stack bond has the lowest lateral strength and the IBC requires added joint reinforcement (minimum area of horizontal reinforcement of 0.0007 times the gross cross-sectional area of the wall, spaced not over 16 inches).

Reinforcement and Coursing Math

Horizontal joint reinforcement (ladder or truss type, ASTM A951) is laid in bed joints, typically every 16 inches (every other CMU course). Vertical reinforcement is rebar grouted into cells.

Coursing uses the nominal 8-inch CMU height: 3 courses = 24 inches (2 feet) , so a wall is built to multiples of 8 inches. To find courses in a wall, divide wall height (inches) by 8.

Worked example: an 8 ft (96 in) CMU wall = 96 / 8 = 12 courses .

Brick modular coursing: 3 brick courses = 8 inches (each course = 2-2/3 inches with a 3/8-inch joint), so brick and CMU align every 8 inches — important when brick veneers a CMU backup.

Grouting and Cell Reinforcement Rules

Per IBC Chapter 21 / TMS 402 (The Masonry Society code) :

Minimum grout space for fine grout is roughly 3/4 inch ; coarse grout needs more clearance around bars.

Vertical bars must have grout fully surrounding them; lap splices are commonly 48 bar diameters unless engineered otherwise.

Bond beams (CMU with a notched/knockout web) carry horizontal rebar and act as continuous tie courses, often at the top of wall and at floor lines.

Reinforcement clear cover in masonry is typically 1-1/2 inches for bars exposed to weather, 3/4 inch otherwise.