Study guide
8.3 Lintels, Control/Expansion Joints, and Flashing
NASCLA Contractor Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Coverage Map & Exam Overview
Coverage Map & Exam Overview
2 Business Organization, Licensing & Law
1.1 Business Entity Types and Formation 1.2 NASCLA Trade-Exam Waiver and Agency Licensing Boundaries 1.3 Construction Contract Law and Types of Contracts 1.4 Lien Law, Bond Claims, and Dispute Resolution
3 Financial Management, Tax & Labor Law
2.1 Financial Statements, Job Costing, and Cash Flow 2.2 Payroll, Federal/State Tax, and Recordkeeping 2.3 Labor & Employment Law (FLSA, immigration/I-9, EEO) 2.4 Insurance, Surety Bonds, and Risk Management
4 Estimating, Bidding & Plan Reading
3.1 Reading Construction Drawings and Specifications (CSI MasterFormat) 3.2 Quantity Takeoff and Material Estimating 3.3 Bidding, Markup, Overhead, and Profit 3.4 Change Orders, Allowances, and Unit Pricing
5 Project Management & Scheduling
4.1 Project Delivery Methods and the Submittal/RFI Process 4.2 Scheduling (CPM, Bar Charts, Critical Path) 4.3 Quality Control, Inspections, and Closeout 4.4 Permits, Codes, and the Inspection Process
6 Construction Safety & OSHA (29 CFR 1926)
5.1 OSHA Administration, Recordkeeping, and the General Duty Clause 5.2 Fall Protection, Scaffolds, and Ladders 5.3 Excavation/Trenching, Electrical, and Hazard Communication 5.4 PPE, Fire Protection, Cranes, and Confined Spaces
7 General Requirements & Sitework
6.1 Division 01 General Requirements and Temporary Facilities 6.2 Surveying, Site Layout, and Excavation 6.3 Soils, Compaction, and Erosion/Sediment Control 6.4 Foundations, Footings, and Site Drainage
8 Concrete (CSI Division 03)
7.1 Concrete Materials, Mix Design, and Water-Cement Ratio 7.2 Formwork and Reinforcement Placement 7.3 Placing, Finishing, Curing, and Testing (slump, cylinders) 7.4 Concrete Defects, Joints, and Cold-Weather Practices
9 Masonry (CSI Division 04)
8.1 Masonry Units, Mortar Types (M/S/N/O), and Grout 8.2 Brick and CMU Bonds, Reinforcement, and Coursing 8.3 Lintels, Control/Expansion Joints, and Flashing 8.4 Masonry Estimating and Cold/Hot Weather Construction
10 Metals & Wood (CSI Divisions 05 & 06)
9.1 Structural Steel, Connections, and Welding/Bolting 9.2 Light-Gauge Metal Framing 9.3 Wood Framing, Species/Grades, and Fasteners 9.4 Engineered Wood, Trusses, and Load Paths
11 Thermal & Moisture Protection (CSI Division 07)
10.1 Waterproofing, Dampproofing, and Below-Grade Protection 10.2 Insulation, R-Values, and Vapor Barriers 10.3 Roofing Systems (steep-slope and low-slope) and Underlayment 10.4 Flashing, Sealants, and Air Barriers
12 Openings & Finishes (CSI Divisions 08 & 09)
11.1 Doors, Windows, Glazing, and Hardware 11.2 Gypsum Board, Plaster, and Framing 11.3 Flooring, Tile, and Acoustical Ceilings 11.4 Painting, Coatings, and Finish Schedules
13 Mechanical, Plumbing & Electrical Overview
12.1 Plumbing Systems, Fixtures, and DWV/Supply Basics 12.2 HVAC Systems and Load Concepts 12.3 Electrical Systems, Service, and NEC Basics 12.4 Coordination, Rough-In, and Energy Code
8.3 Lintels, Control/Expansion Joints, and Flashing
Key Takeaways Explain This Topic AI
Lintels need minimum 4-inch bearing each end; add both ends to clear span to get total length (e.g., 72 + 4 + 4 = 80 in).
Control joints serve CMU (shrinkage); expansion joints serve clay brick (expansion) — CMU = Control is the memory aid.
CMU control-joint spacing is limited to the lesser of about 1.5x wall height or roughly 25 feet.
Through-wall flashing must turn up at least 8 inches and pair with weep holes at 24-33 inch spacing; neither works without the other.
Brick veneer ties allow a maximum of 1 tie per 2.67 sq ft, typically 32 in horizontal by 24 in vertical, with a 1-inch drainage air space.
Last updated: June 2026
Lintels, Movement Joints, and Flashing
Masonry must span openings, accommodate movement, and shed water. These three details — lintels , joints , and flashing — are common sources of field defects, so this editorial section focuses on them.
Lintels
A lintel carries masonry over an opening (door, window). Options:
Steel angle (loose lintel): common for brick veneer; sized by span and load. A typical light residential opening uses a L 3-1/2 x 3-1/2 x 1/4 inch angle.
Precast concrete lintel.
Reinforced masonry lintel (bond-beam lintel): CMU lintel block grouted with rebar.
Bearing: lintels must bear a minimum of 4 inches on each end per common code/reference practice (some require the greater of 4 inches or span/12 for masonry lintels).
Lintel Worked Example
For a reinforced masonry lintel over a 6 ft (72 in) clear opening:
Minimum bearing each end = 4 inches , so total lintel length = 72 + 4 + 4 = 80 inches .
The lintel depth is built in 8-inch course increments; a single-course bond beam = 8 inches nominal.
Reinforcement (e.g., 2 - #4 bars) sits in the bottom of the grouted lintel block with proper cover.
Always confirm bearing length first — under-bearing is a classic failure and a plausible distractor in editorial practice that gives only 2 or 3 inches of bearing.
Control Joints vs. Expansion Joints
These are opposites and they are easy to swap in practice.
- Feature Control Joint Expansion Joint
- Used in Concrete masonry (CMU) Clay brick
- Movement type Shrinkage (CMU shrinks as it cures/dries) Expansion (clay brick grows with moisture/heat)
- Purpose Allow controlled cracking Absorb expansion, prevent crushing
- Material Often left open with backer rod + sealant Compressible filler + sealant
Memory aid: C MU gets C ontrol joints (shrinks); clay brick gets e X pansion joints (e X pands). Vertical control-joint spacing in CMU is commonly limited to the lesser of 1.5 x wall height or about 25 feet .
Flashing and Weeps
Through-wall flashing collects water that penetrates the outer wythe and directs it out. It is required at the base of cavity walls , over lintels, under sills, and at shelf angles.
Flashing must turn up the backup wall at least 8 inches and extend through the face to form a drip.
Weep holes sit immediately above flashing to drain collected water; spacing is typically 24 to 33 inches on center (open head joints or wicks).
A clear cavity / drainage space of at least 1 inch (2 inches preferred) keeps mortar droppings off the flashing.
Drainage check: flashing without weep holes (or weeps without flashing) is useless — water gets trapped and causes efflorescence and freeze damage.
Anchorage and Veneer Ties
Brick veneer over wood/steel stud or CMU backup is held by corrugated metal ties or adjustable anchors :
Maximum 1 tie per 2.67 sq ft of wall area (IBC veneer provisions), reduced in high-wind/seismic zones.
Maximum tie spacing commonly 32 inches horizontal / 24 inches vertical .
Air space behind veneer is nominally 1 inch for drainage.
Proper anchor spacing is a useful quantity-takeoff and code-lookup exercise — note the area-per-tie limit, not just the spacing.