Study guide
11.3 Flooring, Tile, and Acoustical Ceilings
NASCLA Contractor Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Coverage Map & Exam Overview
Coverage Map & Exam Overview
2 Business Organization, Licensing & Law
1.1 Business Entity Types and Formation 1.2 NASCLA Trade-Exam Waiver and Agency Licensing Boundaries 1.3 Construction Contract Law and Types of Contracts 1.4 Lien Law, Bond Claims, and Dispute Resolution
3 Financial Management, Tax & Labor Law
2.1 Financial Statements, Job Costing, and Cash Flow 2.2 Payroll, Federal/State Tax, and Recordkeeping 2.3 Labor & Employment Law (FLSA, immigration/I-9, EEO) 2.4 Insurance, Surety Bonds, and Risk Management
4 Estimating, Bidding & Plan Reading
3.1 Reading Construction Drawings and Specifications (CSI MasterFormat) 3.2 Quantity Takeoff and Material Estimating 3.3 Bidding, Markup, Overhead, and Profit 3.4 Change Orders, Allowances, and Unit Pricing
5 Project Management & Scheduling
4.1 Project Delivery Methods and the Submittal/RFI Process 4.2 Scheduling (CPM, Bar Charts, Critical Path) 4.3 Quality Control, Inspections, and Closeout 4.4 Permits, Codes, and the Inspection Process
6 Construction Safety & OSHA (29 CFR 1926)
5.1 OSHA Administration, Recordkeeping, and the General Duty Clause 5.2 Fall Protection, Scaffolds, and Ladders 5.3 Excavation/Trenching, Electrical, and Hazard Communication 5.4 PPE, Fire Protection, Cranes, and Confined Spaces
7 General Requirements & Sitework
6.1 Division 01 General Requirements and Temporary Facilities 6.2 Surveying, Site Layout, and Excavation 6.3 Soils, Compaction, and Erosion/Sediment Control 6.4 Foundations, Footings, and Site Drainage
8 Concrete (CSI Division 03)
7.1 Concrete Materials, Mix Design, and Water-Cement Ratio 7.2 Formwork and Reinforcement Placement 7.3 Placing, Finishing, Curing, and Testing (slump, cylinders) 7.4 Concrete Defects, Joints, and Cold-Weather Practices
9 Masonry (CSI Division 04)
8.1 Masonry Units, Mortar Types (M/S/N/O), and Grout 8.2 Brick and CMU Bonds, Reinforcement, and Coursing 8.3 Lintels, Control/Expansion Joints, and Flashing 8.4 Masonry Estimating and Cold/Hot Weather Construction
10 Metals & Wood (CSI Divisions 05 & 06)
9.1 Structural Steel, Connections, and Welding/Bolting 9.2 Light-Gauge Metal Framing 9.3 Wood Framing, Species/Grades, and Fasteners 9.4 Engineered Wood, Trusses, and Load Paths
11 Thermal & Moisture Protection (CSI Division 07)
10.1 Waterproofing, Dampproofing, and Below-Grade Protection 10.2 Insulation, R-Values, and Vapor Barriers 10.3 Roofing Systems (steep-slope and low-slope) and Underlayment 10.4 Flashing, Sealants, and Air Barriers
12 Openings & Finishes (CSI Divisions 08 & 09)
11.1 Doors, Windows, Glazing, and Hardware 11.2 Gypsum Board, Plaster, and Framing 11.3 Flooring, Tile, and Acoustical Ceilings 11.4 Painting, Coatings, and Finish Schedules
13 Mechanical, Plumbing & Electrical Overview
12.1 Plumbing Systems, Fixtures, and DWV/Supply Basics 12.2 HVAC Systems and Load Concepts 12.3 Electrical Systems, Service, and NEC Basics 12.4 Coordination, Rough-In, and Energy Code
11.3 Flooring, Tile, and Acoustical Ceilings
Key Takeaways Explain This Topic AI
Test concrete moisture before resilient flooring: ASTM F2170 RH (typically 75-85 percent max) is more reliable than ASTM F1869 calcium chloride MVER (3-5 lb).
Thinset coverage must reach 80 percent dry / 95 percent wet; large-format tile (over 15 inches) needs medium-bed/LHT mortar to limit lippage.
Estimate tile area plus waste: 10 percent straight-lay, 15 percent diagonal or large-format; always round up to full cartons.
NRC measures in-room absorption; CAC measures sound blocked between rooms; high NRC does not provide speech privacy.
Seismic Design Categories D-F require ASTM E580 heavy-duty grid, bracing wires, compression posts, and two-wall attachment with perimeter clearance.
Last updated: June 2026
Flooring, Tile, and Acoustical Ceilings
This Division 09 group covers resilient flooring, ceramic tile, and suspended acoustical ceilings . Reference standards include the Tile Council of North America (TCNA) Handbook , ANSI A108/A118 (installation and materials), ASTM F710 (concrete moisture for flooring), and ASTM E1264 (acoustical ceiling classification). Sequence matters: most finish flooring goes in late to avoid damage.
Concrete substrate moisture (ASTM F2170, F1869)
Resilient flooring and adhesives fail when the slab is too wet. Two tests dominate:
ASTM F2170 — in-situ relative humidity (RH) probes: acceptance is typically 75 percent to 85 percent RH maximum per the flooring manufacturer.
ASTM F1869 — calcium chloride MVER: limit often 3 to 5 pounds per 1,000 square feet per 24 hours .
A standard slab needs roughly 28 days of cure before testing. Practice check: passing a calcium chloride test does not guarantee an RH pass — RH is the more reliable indicator and manufacturers increasingly require it.
Tile setting methods and mortar
Thinset (dry-set / modified, ANSI A118.1 / A118.4) is the standard bond mortar; trowel notch size is matched to tile size so coverage reaches 80 percent (dry) / 95 percent (wet or exterior) . Large-format tile (any side over 15 inches) requires a medium-bed or LHT (large-and-heavy-tile) mortar to prevent lippage.
Membranes: ANSI A118.10 waterproofing and A118.12 crack isolation. A trap: omitting a crack-isolation membrane over a control joint telegraphs cracks straight through the tile.
Tile takeoff scenario
Estimate tile quantity by area plus waste:
Field area: 30 ft x 20 ft = 600 square feet .
Waste factor: 10 percent straight-lay, 15 percent diagonal/large-format.
Order: 600 x 1.10 = 660 square feet .
For grout and thinset, follow coverage charts; coverage drops with larger trowel notches. Always round up to full carton/box quantities — partial cartons are not sold.
Acoustical ceiling performance (ASTM E1264, E1414)
Suspended acoustical tile is rated by two distinct numbers — do not confuse them:
- Metric Measures Better when
- NRC (Noise Reduction Coefficient) Sound absorbed within the room Higher (toward 1.00)
- CAC (Ceiling Attenuation Class) Sound blocked between rooms over a wall Higher (35+ for privacy)
A tile can have high NRC but low CAC , allowing speech to pass over a partition through the plenum. Open-plan offices want high NRC; private offices need high CAC.
Suspension grid and seismic
The main runners and cross tees form the grid; perimeter wall molding supports the edge. In Seismic Design Categories D, E, and F , ASTM E580 requires heavier (intermediate/heavy-duty) grid, wall attachment on two adjacent walls with clearance at the opposite two , splay/bracing wires every 12 feet, and compression posts . Ceilings over 144 square feet require lateral bracing in higher seismic categories.