6.1 Division 01 General Requirements and Temporary Facilities

NASCLA Contractor Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Coverage Map & Exam Overview

Coverage Map & Exam Overview

2 Business Organization, Licensing & Law

1.1 Business Entity Types and Formation 1.2 NASCLA Trade-Exam Waiver and Agency Licensing Boundaries 1.3 Construction Contract Law and Types of Contracts 1.4 Lien Law, Bond Claims, and Dispute Resolution

3 Financial Management, Tax & Labor Law

2.1 Financial Statements, Job Costing, and Cash Flow 2.2 Payroll, Federal/State Tax, and Recordkeeping 2.3 Labor & Employment Law (FLSA, immigration/I-9, EEO) 2.4 Insurance, Surety Bonds, and Risk Management

4 Estimating, Bidding & Plan Reading

3.1 Reading Construction Drawings and Specifications (CSI MasterFormat) 3.2 Quantity Takeoff and Material Estimating 3.3 Bidding, Markup, Overhead, and Profit 3.4 Change Orders, Allowances, and Unit Pricing

5 Project Management & Scheduling

4.1 Project Delivery Methods and the Submittal/RFI Process 4.2 Scheduling (CPM, Bar Charts, Critical Path) 4.3 Quality Control, Inspections, and Closeout 4.4 Permits, Codes, and the Inspection Process

6 Construction Safety & OSHA (29 CFR 1926)

5.1 OSHA Administration, Recordkeeping, and the General Duty Clause 5.2 Fall Protection, Scaffolds, and Ladders 5.3 Excavation/Trenching, Electrical, and Hazard Communication 5.4 PPE, Fire Protection, Cranes, and Confined Spaces

7 General Requirements & Sitework

6.1 Division 01 General Requirements and Temporary Facilities 6.2 Surveying, Site Layout, and Excavation 6.3 Soils, Compaction, and Erosion/Sediment Control 6.4 Foundations, Footings, and Site Drainage

8 Concrete (CSI Division 03)

7.1 Concrete Materials, Mix Design, and Water-Cement Ratio 7.2 Formwork and Reinforcement Placement 7.3 Placing, Finishing, Curing, and Testing (slump, cylinders) 7.4 Concrete Defects, Joints, and Cold-Weather Practices

9 Masonry (CSI Division 04)

8.1 Masonry Units, Mortar Types (M/S/N/O), and Grout 8.2 Brick and CMU Bonds, Reinforcement, and Coursing 8.3 Lintels, Control/Expansion Joints, and Flashing 8.4 Masonry Estimating and Cold/Hot Weather Construction

10 Metals & Wood (CSI Divisions 05 & 06)

9.1 Structural Steel, Connections, and Welding/Bolting 9.2 Light-Gauge Metal Framing 9.3 Wood Framing, Species/Grades, and Fasteners 9.4 Engineered Wood, Trusses, and Load Paths

11 Thermal & Moisture Protection (CSI Division 07)

10.1 Waterproofing, Dampproofing, and Below-Grade Protection 10.2 Insulation, R-Values, and Vapor Barriers 10.3 Roofing Systems (steep-slope and low-slope) and Underlayment 10.4 Flashing, Sealants, and Air Barriers

12 Openings & Finishes (CSI Divisions 08 & 09)

11.1 Doors, Windows, Glazing, and Hardware 11.2 Gypsum Board, Plaster, and Framing 11.3 Flooring, Tile, and Acoustical Ceilings 11.4 Painting, Coatings, and Finish Schedules

13 Mechanical, Plumbing & Electrical Overview

12.1 Plumbing Systems, Fixtures, and DWV/Supply Basics 12.2 HVAC Systems and Load Concepts 12.3 Electrical Systems, Service, and NEC Basics 12.4 Coordination, Rough-In, and Energy Code

6.1 Division 01 General Requirements and Temporary Facilities

Key Takeaways Explain This Topic AI

Division 01 General Requirements covers project-wide General Conditions costs that must be priced into every bid.

Markup is a percent of cost; margin is a percent of price — use Price = Cost ÷ (1 − margin) for a target margin.

A 20% markup on cost yields only a 16.7% margin; mixing the two is a useful practice check.

OSHA 1926.51 sets sanitation minimums: one toilet for 20 or fewer workers, marked potable water, no common cup.

Temporary power follows NEC Article 590 and requires GFCI protection per 1926.404(b)(1).

Last updated: June 2026

Division 01 General Requirements and Temporary Facilities

Division 01 of the CSI MasterFormat is where the general contractor's overhead, coordination, and project-wide obligations live. In the NASCLA reference framework these costs are classified as General Conditions — expenses that benefit the whole job, not a single trade. Examples: site supervision, the field office, temporary power, dumpsters, cleanup, surveys, and the project schedule. They are real, recoverable costs that must appear in the bid.

What lives in Division 01

Key subdivisions to recognize during open-book navigation:

  • Section Title Typical content
  • 01 10 00 Summary Work scope, phasing, owner-occupied areas
  • 01 20 00 Price and Payment Allowances, schedule of values, applications for payment
  • 01 30 00 Administrative RFIs, submittals, coordination, meetings
  • 01 50 00 Temporary Facilities Power, water, sanitation, fencing, hoists
  • 01 70 00 Execution and Closeout Cleaning, punch list, record documents, warranties

The Schedule of Values in 01 20 00 breaks the contract sum into line items so the architect can verify each monthly Application for Payment (typically AIA G702/G703 ).

Markup versus margin (a recurring trap)

Candidates routinely confuse markup with margin . Markup is a percentage added to cost; margin is profit expressed as a percentage of the selling price.

  • Markup % = (Price − Cost) ÷ Cost
  • Margin % = (Price − Cost) ÷ Price

Worked example: cost = $100,000 , you want a 20% margin . Do not multiply by 1.20. Instead divide: Price = Cost ÷ (1 − margin) = $100,000 ÷ (1 − 0.20) = $100,000 ÷ 0.80 = $125,000 . The required markup is therefore 25% , not 20%. Marking up cost by 20% yields only a 16.7% margin — the common practical mistake.

Temporary facilities and OSHA sanitation

Temporary facilities are governed by both the contract and OSHA 29 CFR 1926 . Key field-office obligations:

Toilets — 1926.51(c) : provide one toilet for 20 or fewer workers; one toilet seat and one urinal per 40 workers above that.

Potable water — 1926.51(a) : clearly marked; single-use cups; no common drinking cup.

Temporary power — must follow NEC Article 590 and use Ground-Fault Circuit Interrupter (GFCI) protection per 1926.404(b)(1) .

Housekeeping — 1926.25 : scrap, forms with protruding nails, and debris removed regularly.

These are flat General Conditions costs, so they are usually estimated by duration (per month) rather than by unit of work.