Study guide

6.3 Soils, Compaction, and Erosion/Sediment Control

NASCLA Contractor Study Guide Exam

Track your progress as you read

Finished sections get a check mark.

1 Coverage Map & Exam Overview

Coverage Map & Exam Overview

2 Business Organization, Licensing & Law

1.1 Business Entity Types and Formation 1.2 NASCLA Trade-Exam Waiver and Agency Licensing Boundaries 1.3 Construction Contract Law and Types of Contracts 1.4 Lien Law, Bond Claims, and Dispute Resolution

3 Financial Management, Tax & Labor Law

2.1 Financial Statements, Job Costing, and Cash Flow 2.2 Payroll, Federal/State Tax, and Recordkeeping 2.3 Labor & Employment Law (FLSA, immigration/I-9, EEO) 2.4 Insurance, Surety Bonds, and Risk Management

4 Estimating, Bidding & Plan Reading

3.1 Reading Construction Drawings and Specifications (CSI MasterFormat) 3.2 Quantity Takeoff and Material Estimating 3.3 Bidding, Markup, Overhead, and Profit 3.4 Change Orders, Allowances, and Unit Pricing

5 Project Management & Scheduling

4.1 Project Delivery Methods and the Submittal/RFI Process 4.2 Scheduling (CPM, Bar Charts, Critical Path) 4.3 Quality Control, Inspections, and Closeout 4.4 Permits, Codes, and the Inspection Process

6 Construction Safety & OSHA (29 CFR 1926)

5.1 OSHA Administration, Recordkeeping, and the General Duty Clause 5.2 Fall Protection, Scaffolds, and Ladders 5.3 Excavation/Trenching, Electrical, and Hazard Communication 5.4 PPE, Fire Protection, Cranes, and Confined Spaces

7 General Requirements & Sitework

6.1 Division 01 General Requirements and Temporary Facilities 6.2 Surveying, Site Layout, and Excavation 6.3 Soils, Compaction, and Erosion/Sediment Control 6.4 Foundations, Footings, and Site Drainage

8 Concrete (CSI Division 03)

7.1 Concrete Materials, Mix Design, and Water-Cement Ratio 7.2 Formwork and Reinforcement Placement 7.3 Placing, Finishing, Curing, and Testing (slump, cylinders) 7.4 Concrete Defects, Joints, and Cold-Weather Practices

9 Masonry (CSI Division 04)

8.1 Masonry Units, Mortar Types (M/S/N/O), and Grout 8.2 Brick and CMU Bonds, Reinforcement, and Coursing 8.3 Lintels, Control/Expansion Joints, and Flashing 8.4 Masonry Estimating and Cold/Hot Weather Construction

10 Metals & Wood (CSI Divisions 05 & 06)

9.1 Structural Steel, Connections, and Welding/Bolting 9.2 Light-Gauge Metal Framing 9.3 Wood Framing, Species/Grades, and Fasteners 9.4 Engineered Wood, Trusses, and Load Paths

11 Thermal & Moisture Protection (CSI Division 07)

10.1 Waterproofing, Dampproofing, and Below-Grade Protection 10.2 Insulation, R-Values, and Vapor Barriers 10.3 Roofing Systems (steep-slope and low-slope) and Underlayment 10.4 Flashing, Sealants, and Air Barriers

12 Openings & Finishes (CSI Divisions 08 & 09)

11.1 Doors, Windows, Glazing, and Hardware 11.2 Gypsum Board, Plaster, and Framing 11.3 Flooring, Tile, and Acoustical Ceilings 11.4 Painting, Coatings, and Finish Schedules

13 Mechanical, Plumbing & Electrical Overview

12.1 Plumbing Systems, Fixtures, and DWV/Supply Basics 12.2 HVAC Systems and Load Concepts 12.3 Electrical Systems, Service, and NEC Basics 12.4 Coordination, Rough-In, and Energy Code

6.3 Soils, Compaction, and Erosion/Sediment Control

Key Takeaways Explain This Topic AI

IBC Table 1806.2 presumptive bearing values: bedrock ~12,000 psf, sandy gravel ~3,000 psf, clay/silt ~1,500 psf.

Footing capacity = allowable bearing (psf) × footing area (sq ft); size footings to keep load at or below capacity.

Standard Proctor is ASTM D698; modified Proctor is ASTM D1557; structural fill is usually 95% of modified Proctor.

Compact fill in 6–12 in lifts near optimum moisture; too wet or too dry soil will not reach target density.

Disturbing 1 acre or more requires an NPDES Construction General Permit and a written SWPPP with BMPs like silt fence.

Last updated: June 2026

Soils, Compaction, and Erosion/Sediment Control

The bearing capacity and stability of a building depend on the soil beneath it. The International Building Code (IBC) Table 1806.2 gives presumptive load-bearing values when no geotechnical report is available. Crystalline bedrock carries about 12,000 psf , sand and gravel about 3,000 psf , and clay/silt about 1,500 psf . Expansive (high-clay) soils swell and shrink with moisture and are flagged under IBC 1803.5.3 for special investigation.

Presumptive load-bearing values (IBC Table 1806.2)

  • Material class Allowable bearing (psf)
  • Crystalline bedrock 12,000
  • Sedimentary/foliated rock 4,000
  • Sandy gravel / gravel (GW, GP) 3,000
  • Sand, silty sand, clayey sand (SW, SP, SM, SC) 2,000
  • Clay, sandy clay, silty clay (CL, ML) 1,500

These values use the Unified Soil Classification System (USCS) . Quick check: a 2,000 psf soil under a 2 ft × 2 ft isolated footing (4 sq ft) supports 8,000 lb before exceeding bearing — a typical worked footing-sizing question.

Compaction and the Proctor test

Fill is compacted in lifts and verified against a laboratory maximum dry density.

Standard Proctor — ASTM D698 establishes the baseline maximum dry density and optimum moisture content .

Modified Proctor — ASTM D1557 uses higher compactive energy for heavier loads (roads, structural fill).

Field density — ASTM D6938 (nuclear gauge) or sand-cone confirms percent compaction.

Structural fill is typically specified at 95% of modified Proctor ; landscaped or non-structural fill may accept 90% . Compact in 6–12 in lifts and keep moisture near optimum — soil too wet or too dry will not reach target density, a frequent inspection-failure scenario.

Erosion and sediment control (NPDES / EPA)

Sites disturbing 1 acre or more need a Construction General Permit (CGP) under the federal NPDES stormwater program and a written Stormwater Pollution Prevention Plan (SWPPP) .

Common Best Management Practices ( BMPs ):

Silt fence — perimeter sediment barrier on the down-slope edge; trench in the toe.

Stabilized construction entrance — crushed stone to knock mud off tires.

Inlet protection — keeps sediment out of storm drains.

Sediment basin — required for 10+ acres draining to a common point.

Controls must be inspected after rain events and maintained until the site is permanently stabilized with vegetation or pavement.