Study guide
10.1 Waterproofing, Dampproofing, and Below-Grade Protection
NASCLA Contractor Study Guide Exam
Track your progress as you read
Finished sections get a check mark.
1 Coverage Map & Exam Overview
Coverage Map & Exam Overview
2 Business Organization, Licensing & Law
1.1 Business Entity Types and Formation 1.2 NASCLA Trade-Exam Waiver and Agency Licensing Boundaries 1.3 Construction Contract Law and Types of Contracts 1.4 Lien Law, Bond Claims, and Dispute Resolution
3 Financial Management, Tax & Labor Law
2.1 Financial Statements, Job Costing, and Cash Flow 2.2 Payroll, Federal/State Tax, and Recordkeeping 2.3 Labor & Employment Law (FLSA, immigration/I-9, EEO) 2.4 Insurance, Surety Bonds, and Risk Management
4 Estimating, Bidding & Plan Reading
3.1 Reading Construction Drawings and Specifications (CSI MasterFormat) 3.2 Quantity Takeoff and Material Estimating 3.3 Bidding, Markup, Overhead, and Profit 3.4 Change Orders, Allowances, and Unit Pricing
5 Project Management & Scheduling
4.1 Project Delivery Methods and the Submittal/RFI Process 4.2 Scheduling (CPM, Bar Charts, Critical Path) 4.3 Quality Control, Inspections, and Closeout 4.4 Permits, Codes, and the Inspection Process
6 Construction Safety & OSHA (29 CFR 1926)
5.1 OSHA Administration, Recordkeeping, and the General Duty Clause 5.2 Fall Protection, Scaffolds, and Ladders 5.3 Excavation/Trenching, Electrical, and Hazard Communication 5.4 PPE, Fire Protection, Cranes, and Confined Spaces
7 General Requirements & Sitework
6.1 Division 01 General Requirements and Temporary Facilities 6.2 Surveying, Site Layout, and Excavation 6.3 Soils, Compaction, and Erosion/Sediment Control 6.4 Foundations, Footings, and Site Drainage
8 Concrete (CSI Division 03)
7.1 Concrete Materials, Mix Design, and Water-Cement Ratio 7.2 Formwork and Reinforcement Placement 7.3 Placing, Finishing, Curing, and Testing (slump, cylinders) 7.4 Concrete Defects, Joints, and Cold-Weather Practices
9 Masonry (CSI Division 04)
8.1 Masonry Units, Mortar Types (M/S/N/O), and Grout 8.2 Brick and CMU Bonds, Reinforcement, and Coursing 8.3 Lintels, Control/Expansion Joints, and Flashing 8.4 Masonry Estimating and Cold/Hot Weather Construction
10 Metals & Wood (CSI Divisions 05 & 06)
9.1 Structural Steel, Connections, and Welding/Bolting 9.2 Light-Gauge Metal Framing 9.3 Wood Framing, Species/Grades, and Fasteners 9.4 Engineered Wood, Trusses, and Load Paths
11 Thermal & Moisture Protection (CSI Division 07)
10.1 Waterproofing, Dampproofing, and Below-Grade Protection 10.2 Insulation, R-Values, and Vapor Barriers 10.3 Roofing Systems (steep-slope and low-slope) and Underlayment 10.4 Flashing, Sealants, and Air Barriers
12 Openings & Finishes (CSI Divisions 08 & 09)
11.1 Doors, Windows, Glazing, and Hardware 11.2 Gypsum Board, Plaster, and Framing 11.3 Flooring, Tile, and Acoustical Ceilings 11.4 Painting, Coatings, and Finish Schedules
13 Mechanical, Plumbing & Electrical Overview
12.1 Plumbing Systems, Fixtures, and DWV/Supply Basics 12.2 HVAC Systems and Load Concepts 12.3 Electrical Systems, Service, and NEC Basics 12.4 Coordination, Rough-In, and Energy Code
10.1 Waterproofing, Dampproofing, and Below-Grade Protection
Key Takeaways Explain This Topic AI
Dampproofing (IBC 1805.2) resists moisture/capillary action; waterproofing (IBC 1805.3) resists liquid water under hydrostatic pressure.
A high groundwater table triggers waterproofing of walls and a slab designed for uplift (IBC 1805.1.2.1).
Masonry below-grade walls must be parged 3/8 in. with Portland cement before dampproofing.
Foundation drains need 6 in. of washed gravel surround, top below the slab bottom (IBC 1805.4.2).
Always convert granular takeoffs using 27 ft3 = 1 yd3 and round up.
Last updated: June 2026
Waterproofing vs. Dampproofing
The International Building Code (IBC) Section 1805 governs below-grade moisture control. This editorial section distinguishes two terms that sound alike but solve different problems. Dampproofing resists moisture (water vapor and capillary seepage) where no hydrostatic head is present. Waterproofing resists liquid water under hydrostatic pressure .
The decision driver is the groundwater table . Per IBC 1805.1.2.1, where a high water table or other hydrostatic conditions are known to exist, walls must be waterproofed and the floor must be designed to resist that pressure. Otherwise dampproofing of foundation walls enclosing habitable or usable space below grade is the minimum (IBC 1805.1.2).
Drainage check: A basement below the water table requires waterproofing , not dampproofing. Choosing dampproofing in that scenario is the classic wrong answer.
Dampproofing Materials & Application
IBC 1805.2 lists acceptable dampproofing applied to the exterior wall face below grade:
- Material Minimum Application
- Bituminous (asphalt) coating Mopped/brushed, exterior face
- 3 lb/yd2 acrylic-modified cement Troweled
- 1/8 in. Portland cement parging On masonry, then bituminous coat
- Surface-bonding cement Per ASTM C887
For masonry walls , IBC 1805.2.2 requires the wall be parged 3/8 in. (9.5 mm) with Portland cement, then coated with the dampproofing. Concrete walls may be coated directly.
Waterproofing Materials
IBC 1805.3 recognizes membranes that bridge cracks and resist head pressure:
- 2-ply hot-mopped felts (ASTM D226 Type I or II)
- 55 lb (25 kg) roll roofing
- 6 mil (0.15 mm) polyvinyl chloride (PVC)
- 6 mil (0.15 mm) polyethylene
- 40 mil (1 mm) polymer-modified asphalt
Joints in the membrane must be lapped and sealed. The membrane is applied from a point 6 in. (152 mm) above the maximum water-table elevation down over the footing.
Subsoil Drainage & Worked Example
IBC 1805.4.2 requires drains around foundations retaining earth and enclosing below-grade space (unless on well-drained ground per Table 1610.1, Group I soils). The drain (perforated pipe or gravel) sits alongside the footing , with the top of the drain below the bottom of the slab , surrounded by at least 6 in. (152 mm) of washed gravel extending 12 in. beyond the pipe.
Takeoff scenario: A rectangular foundation 40 ft x 30 ft needs a perimeter footing drain. Perimeter = 2(40+30) = 140 lin ft. With 10% waste for fittings and a cleanout, order 140 x 1.10 = 154 lin ft of perforated pipe.
Drainage Gravel Volume
Using that 140 lin ft trench at 12 in. wide x 12 in. deep of gravel surround: cross-section = 1 ft2, so volume = 140 ft3. Convert to cubic yards: 140 / 27 = 5.19 yd3 → order 6 yd3 (always round up for granular materials). Knowing 27 ft3 = 1 yd3 is reused throughout these editorial calculations.