Study guide

9.5 Post-Construction Stormwater, SCMs & the NCDEQ Stormwater Design Manual

North Carolina Land Surveyor NC PLS

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: North Carolina Statutory Authority & Board Administration (G.S. 89C & 21 NCAC 56)

1.1 The North Carolina State-Specific Exam: Format, Blueprint & Approved References 1.2 Statutory Framework & Board Organization (G.S. 89C & 21 NCAC 56) 1.3 Licensure Qualifications, Education & Experience Pathways (G.S. 89C-13(b)) 1.4 Professional Entity Organization, Firm Licensure & Business Rules 1.5 Continuing Professional Competency (CPC) & License Renewal

2 Chapter 2: Professional Conduct, Standard of Care & Board Enforcement

2.1 Rules of Professional Conduct (21 NCAC 56 .0701) & Advertising (.0702) 2.2 Responsible Charge, Direct Supervisory Control & Sealing (21 NCAC 56 .0701(d), .1101-.1103) 2.3 Qualifications-Based Selection (QBS) & Public Contracting (G.S. 143-64.31) 2.4 Disciplinary Procedures, Board Enforcement Powers & Penalties (G.S. 89C-21 & 89C-22)

3 Chapter 3: NC Standards of Practice for Land Surveying (21 NCAC 56.1600)

3.1 Surveying Procedures & the Record Examination Duty (21 NCAC 56 .1602(a)-(c)) 3.2 Classification of Boundary Surveys, Closure & Positional Accuracy (21 NCAC 56 .1603) 3.3 Monumentation, Tie Lines & Mapping Requirements (21 NCAC 56 .1602(d)-(h) & .1604) 3.4 Vertical Control, Topographic & Planimetric Mapping (21 NCAC 56 .1605 & .1606)

4 Chapter 4: North Carolina Plat Recording Laws & Review Officer Procedures (G.S. 47-30)

4.1 Plat Size, Reproducible Form, Title Contents & Required Plat Information (G.S. 47-30(a)-(f)) 4.2 The Surveyor Certificate, the Five (f)(11) Statements & Recording Exceptions 4.3 Review Officer Statutory Role, Powers & Certification Process (G.S. 47-30.2) 4.4 Geodetic Ties, Grid Coordinates & NC SPCS Connection (G.S. 47-30(f)(9) & 21 NCAC 56 .1602(g))

5 Chapter 5: North Carolina Boundary Law, Priority of Calls & Title History

5.1 The North Carolina Priority of Calls Hierarchy (Cherry v. Slade) 5.2 North Carolina Real Property History, Colonial Grants & the Granville District 5.3 Metes & Bounds Descriptions, Ambiguities & Deed Construction Rules 5.4 Processioning Proceedings & Boundary Dispute Resolution (G.S. Chapter 38)

6 Chapter 6: Adverse Possession, Easements, Rights-of-Way & Title Doctrines in NC

6.1 Adverse Possession & Color of Title under North Carolina Law (G.S. 1-38 & 1-40) 6.2 Real Property Claims Against the State & Public Prescriptive Immunity (G.S. 1-35) 6.3 Easements: Prescription, Implication, Necessity & Statutory Cartways (G.S. 136-68) 6.4 Public Road Dedication, Maintenance & Statutory Abandonment (G.S. 136-96)

7 Chapter 7: Riparian Rights, Water Boundaries & Coastal Surveying in North Carolina

7.1 Navigability, The Public Trust Doctrine & Riparian Rights (G.S. Chapter 146) 7.2 Non-Navigable Waters, Thread of the Stream (Filum Aquae) & Submerged Lands 7.3 Coastal Boundaries, Mean High Water Mark & Coastal Area Management Act (CAMA) 7.4 Water Boundary Movement: Accretion, Reliction, Erosion & Avulsion

8 Chapter 8: Geodetic Surveying, the NC Coordinate System & LIS/GIS Standards

8.1 The North Carolina State Plane Coordinate System (G.S. Chapter 102) & Grid Reductions 8.2 NCGS Real-Time Network & GNSS Survey Standards (21 NCAC 56 .1607) 8.3 Datums, Geoid Models & NSRS Modernization (NATRF2022 / NAPGD2022) 8.4 LIS/GIS Surveys, Classifications & the Board GIS Guidelines (21 NCAC 56 .1608)

9 Chapter 9: Incidental Streets, Drainage, Erosion Control & Stormwater (16% of the Exam)

9.1 Scope of Incidental Street & Storm Sewer Design (G.S. 89C-3(7) & the Board Guidelines) 9.2 Hydrology for Incidental Drainage: The Rational Method 9.3 Hydraulics: Sizing Swales, Ditches & Storm Conduits 9.4 Erosion & Sediment Control: The Sedimentation Pollution Control Act & 15A NCAC 04 9.5 Post-Construction Stormwater, SCMs & the NCDEQ Stormwater Design Manual 9.6 NCDOT Subdivision Roads Minimum Construction Standards

9.5 Post-Construction Stormwater, SCMs & the NCDEQ Stormwater Design Manual

Key Takeaways Explain This Topic AI

Post-construction stormwater is governed by 15A NCAC 02H .1000, with project-level design requirements in .1003 and Minimum Design Criteria for Stormwater Control Measures in .1050 through .1062.

A project is either low density, meeting the criteria of .1003(2) with vegetated conveyances, or high density, which must achieve either runoff treatment or runoff volume match through Stormwater Control Measures.

For high density projects designed to achieve runoff treatment, the required storm depth is one inch; coastal projects draining to SA or ORW waters carry the more stringent 1.5-inch requirement.

Vegetated setbacks from perennial waterbodies, perennial streams, and intermittent streams shall be at least 30 feet wide for both low and high density development.

The Board Guidelines exclude dams, retaining walls, structures requiring special or structural design, and pumping stations, so an engineered SCM with a structural outlet or an embankment meeting dam criteria is beyond a land surveyor's incidental authority.

Last updated: August 2026

9.5 Post-Construction Stormwater, SCMs & the NCDEQ Stormwater Design Manual

The Board's reference list names the NCDEQ Stormwater BMP Manual — now published as the NCDEQ Stormwater Design Manual — as a state-specific exam resource. Post-construction stormwater is a different regulatory program from erosion control: erosion control governs the construction period and is administered by the Sedimentation Control Commission, while post-construction stormwater governs the completed development in perpetuity and is administered by the Environmental Management Commission through the Division of Energy, Mineral, and Land Resources.

The rules were comprehensively readopted effective January 1, 2017 , replacing the old "BMP" vocabulary with Stormwater Control Measure (SCM) and consolidating the design requirements into Minimum Design Criteria (MDC) .

1. Where the Rules Live

  • Rule Subject
  • 15A NCAC 02H .1002 Definitions, including runoff treatment, runoff volume match, built-upon area
  • 15A NCAC 02H .1003 Design requirements for low density and high density projects, and vegetated setbacks

15A NCAC 02H .1019 - .1021 Coastal county and other program-specific requirements, including the coastal storm depth

  • 15A NCAC 02H .1050 MDC for all Stormwater Control Measures — applies to every SCM
  • 15A NCAC 02H .1051 - .1062 MDC for specific SCM types

Rule .1050 opens with the sizing principle that governs everything downstream: "The design volume of SCMs shall take into account the runoff at build out from all surfaces draining to the system . Drainage from off-site areas may be bypassed. The combined design volume of all SCMs on the project shall be sufficient to handle the required storm."

2. The Low Density / High Density Fork

Every regulated project takes one of two paths. +-----------------------------------------------------------------------------+

  • | 15A NCAC 02H .1003 - THE FORK |
  • | |
  • | LOW DENSITY (.1003(2)) HIGH DENSITY (.1003(3)) |
  • | ------------------------ --------------------------- |
  • | Built-upon area at or below the Any project that does not |
  • | applicable density threshold conform to the low density |
  • | criteria |
  • | Stormwater conveyed primarily by |
  • | VEGETATED CONVEYANCES: Must achieve either |
  • | - trapezoidal, min bottom width 2 ft RUNOFF TREATMENT or |
  • | - side slopes no steeper than 3:1 RUNOFF VOLUME MATCH |
  • | - minimum length 100 ft through engineered SCMs |
  • | - or treatment swales per .1061 |
  • | SCMs must meet the MDC in |
  • | No engineered SCM required .1050 and the type-specific |
  • | rules in .1051 - .1062 |
  • +-----------------------------------------------------------------------------+

The density threshold is not a single statewide number — it varies by program, watershed, and local ordinance. Greenville, for example, applies a 24 percent built-upon-area threshold. The design decision on a subdivision is therefore always a two-part question: what program applies here, and what threshold does it set?

3. The Design Storm

  • Context Required storm depth
  • High density project designed to achieve runoff treatment One inch

Coastal county projects draining to SA (shellfishing) or ORW (Outstanding Resource Waters) 1.5 inches , with a comparison of pre- and post-development runoff for the 1-year 24-hour storm

The Simple Method (Schueler) is the conventional volume computation in the NCDEQ manual: V = 3630 ⋅ R D ⋅ R v ⋅ A V = 3630 \cdot R_D \cdot R_v \cdot A V = 3630 ⋅ R D ​ ⋅ R v ​ ⋅ A

where V is the design volume in cubic feet, R_D is the design storm rainfall depth in inches (typically 1.0 or 1.5), R_v is the dimensionless runoff coefficient derived from impervious fraction, and A is the drainage area in acres. The constant 3,630 converts acre-inches to cubic feet. If the discrete SCS Curve Number method yields a greater volume, that greater volume may be used.

Drawdown. Volume-based SCMs are conventionally designed to release the treatment volume over two to five days — long enough to provide treatment, short enough to restore storage before the next storm.

4. Vegetated Setbacks

Rule .1003 requires vegetated setbacks from perennial waterbodies, perennial streams, and intermittent streams of at least 30 feet in width , for both low and high density development.

This 30-foot setback is a stormwater requirement and is distinct from three other buffers a North Carolina surveyor encounters, all of which can apply to the same project simultaneously:

  • Buffer Source Width
  • Post-construction stormwater vegetated setback 15A NCAC 02H .1003 30 ft
  • Trout waters erosion-control buffer G.S. 113A-57(1) 25 ft undisturbed, or wider as needed

Nutrient-sensitive riparian buffers (Neuse, Tar-Pamlico, Jordan, Falls, Catawba, Randleman) EMC basin rules commonly 50 ft , in two zones

Coastal Area Management Act estuarine shoreline area of environmental concern CAMA rules under G.S. 113A-100 et seq. 75 ft (30 ft in some urban waterfronts)

Mapping all applicable buffers is the surveyor's job on a subdivision plat regardless of who designs the SCM.

5. Common SCM Types

The MDC rules address, among others, infiltration systems, bioretention cells, wet ponds, stormwater wetlands, permeable pavement, sand filters, rainwater harvesting, green roofs, level spreaders and filter strips, disconnected impervious surface, treatment swales, and dry ponds.

SCM Primary mechanism Typical constraint

Wet pond Settling in a permanent pool Requires reliable base flow or a high water table; embankment height matters

Bioretention cell Filtration through engineered media, plant uptake Media specification and underdrain design

Infiltration system Full infiltration into the soil profile Requires soils investigation and separation to seasonal high water table

Permeable pavement Infiltration through the surface course Subgrade infiltration rate; maintenance against clogging

  • Sand filter Filtration through a sand bed Structural chambers
  • Treatment swale (.1061) Conveyance with treatment The low-density workhorse
  • Level spreader / filter strip Diffuse flow into a vegetated filter Precise grading tolerances
  • 6. The Scope Line — Read This Before Designing an SCM

Post-construction SCM design is where a surveyor is most likely to drift out of the incidental exception without noticing. Run the Section 9.1 checklist:

Feature of the SCM Board Guideline consequence

An embankment impounding water Exclusion 4 — dams. And if it meets the jurisdictional criteria of the Dam Safety Law of 1967, it is a regulated dam requiring a PE.

A retaining wall forming any side of the facility Exclusion 4 — retaining walls

A structural outlet — riser and barrel, weir structure, engineered energy dissipator Exclusion 5 — special or structural design

  • A pump to move water into or out of the facility Exclusion 11 — pumping stations
  • Serving a large upstream drainage basin routed through the subdivision Exclusion 6
  • Serving a site that is not a subdivision Exclusion 3 , and G.S. 89C-3(7)b.(vi)
  • Anything the surveyor is not totally competent to design in all aspects Exclusion 2

Caution

A great many post-construction SCMs fail at least one of those tests. A wet detention pond with a riser-and-barrel outlet in an earthen embankment implicates exclusions 4 and 5 immediately. The realistic incidental scope is closer to vegetated conveyances, treatment swales, and simple grading-based measures — the low-density path — plus the survey, topography, drainage-area delineation, and plat work that any SCM project needs and that only a surveyor can provide.

That is not a small role. Delineating drainage areas, computing built-upon area, mapping buffers and setbacks, establishing SCM as-built geometry and elevations, and platting the drainage easements and access corridors that maintenance requires are all squarely within the practice of land surveying, and they are what most stormwater projects actually need from a PLS.

Loading diagram... Post-Construction Stormwater Path and the Incidental-Design Boundary