Study guide
6.2 Grease Interceptors, Oil Separators & Sand Traps
North Carolina Plumbing Contractor Exam Class I & Class II
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Exam Overview, Administration & General Code Regulations
1.1 NC Plumbing Licensing, Board Rules & Exam Structure 1.2 General Regulations, Piping Support, Trenching & Protection 1.3 Plumbing Mathematics, Grade Calculations & Isometric Plan Reading 1.4 Permits, Plan Review, Required Inspections & Code-Mandated Tests 1.5 Approved Materials, Standards, Joints & Connections
2 Chapter 2: Fixtures, Faucets, Fixture Fittings & Water Heaters
2.1 Minimum Fixture Requirements, Accessibility (ADA) & Rough-In Spacing 2.2 Fixture Installation, Setting Clearances & Flushometer Valves 2.3 Water Heater Sizing, Temperature & Pressure Relief (T&P) Valves & Safety Devices
3 Chapter 3: Water Supply and Distribution & Backflow Prevention
3.1 Water Service Sizing, Materials & Pressure Regulation 3.2 Water Supply Fixture Units (WSFU) & Pipe Sizing Methods 3.3 Cross-Connection Control, Backflow Prevention Devices & Hazards 3.4 Hot and Cold Water Distribution Design & Pressure Loss Calculations
4 Chapter 4: Sanitary Drainage, Indirect Waste, Sumps & Ejectors
4.1 Drainage System Principles, Flow Velocities & Minimum Slope Requirements 4.2 Drainage Fixture Unit (DFU) Sizing for Building Drains, Sewers & Stacks 4.3 Cleanout Sizing, Locations, Clearances & Installation Standards 4.4 Sewage Sumps, Macerating Systems & Indirect/Special Waste 4.5 Building Sewers, Sewer Connections & Private Sewage Disposal
5 Chapter 5: Vents and Venting Systems
5.1 Venting Principles, Termination & Minimum Sizing 5.2 Wet Venting, Common Venting & Stack Vent Systems 5.3 Circuit & Loop Venting, Combination Waste & Vent Systems 5.4 Island Fixture Venting & Air Admittance Valves (AAVs)
6 Chapter 6: Traps, Interceptors, Separators & Storm Drainage
6.1 Trap Design, Prohibited Traps & Trap Arm Developed Lengths 6.2 Grease Interceptors, Oil Separators & Sand Traps 6.3 Storm Drainage Sizing, Roof Drains & Secondary (Emergency) Overflow Systems
7 Chapter 7: Fuel Gas Piping & Appliance Venting (NC IFGC)
7.1 Fuel Gas Fundamentals, Materials, Jointing & Mandatory Pressure Testing 7.2 Fuel Gas Pipe Sizing: Longest Length & Branch Sizing Methods 7.3 Combustion Air Requirements: Indoor, Outdoor & Engineered Openings 7.4 Fuel Gas Appliance Venting: Category I–IV Systems, Chimneys & Clearances
8 Chapter 8: Safety, Excavation & Jobsite Practices (OSHA 1926)
8.1 OSHA Standards for Plumbing: PPE, Fall Protection & Hazard Communication 8.2 Trenching, Shoring, Soil Classifications & Confined Space Safety 8.3 Soldering, Brazing, Hot Work Permits & Jobsite Fire Prevention
9 Chapter 9: NC Contractor Business Law, Project Management & Liens (NASCLA / 21 NCAC 50)
9.1 NC Board Laws (NCGS 87-2), Administrative Rules (21 NCAC 50) & Disciplinary Actions 9.2 Estimating, Job Costing, Bidding & Contract Administration 9.3 North Carolina Mechanics' Lien Laws, Payment Bonds & Dispute Resolution 9.4 Financial Management, Tax Compliance, Workers' Compensation & Business Insurance 9.5 Business Formation, Entity Licensing & Startup Compliance in North Carolina 9.6 Employment Law, Payroll Compliance & Workforce Management 9.7 Project Management: Scheduling, Submittals, Documentation & Closeout 9.8 Surety Bonding, Risk Transfer & Claims Management 9.9 Environmental, Erosion Control & Jobsite Regulatory Compliance
10 Chapter 10: NC Residential Code Plumbing (Class II & Dwelling Practice)
10.1 NC Residential Code Scope, Administration, Materials & Water Supply for Dwellings 10.2 NC Residential Code DWV, Venting, Traps & Fuel Gas Provisions for Dwellings
6.2 Grease Interceptors, Oil Separators & Sand Traps
Key Takeaways Explain This Topic AI
Interceptors and separators are required for commercial and industrial waste streams containing fats, oils, grease (FOG), petroleum oils, flammable liquids, sand, or solids that could foul public sewers or endanger treatment systems.
Hydro-mechanical Grease Interceptors (HGIs / ASME A112.14.3 / PDI G101) are compact point-of-use units sized by fixture flow rate (GPM) with a grease retention capacity in pounds equal to at least twice the flow rating ( l b s = 2 × G P M lbs = 2 \times GPM l b s = 2 × GPM ).
HGIs require an external or internal vented flow control fitting with an air intake to regulate velocity and entrain micro-bubbles that enhance grease flotation separation.
Commercial food waste disposers are prohibited from discharging directly into grease interceptors unless preceded by an approved solids interceptor; sanitary waste from toilets or urinals can never pass through grease traps.
Oil/water separators for automotive repair garages and parking facilities require vapor-tight construction, a minimum liquid capacity of 6 cu ft plus 1 cu ft per 100 sq ft of vehicle storage area, and an independent 2-inch vent extended separately through the roof.
Last updated: September 2026
6.2 Grease Interceptors, Oil Separators & Sand Traps
Quick Answer: Under North Carolina Plumbing Code (NCPC) Chapter 10 , interceptors and separators are mandatory whenever waste streams carry harmful or hazardous constituents including fats, oils, and grease (FOG), petroleum distillates, sand, or solids. Hydro-mechanical Grease Interceptors (HGIs) are sized based on flow rate in Gallons Per Minute (GPM) and must provide a grease retention capacity in pounds equal to at least twice the GPM rating ( l b s = 2 × G P M lbs = 2 \times GPM l b s = 2 × GPM ) . HGIs mandate an approved flow control fitting with a vented air intake . Oil/water separators for automotive facilities require a minimum base capacity of 6 cubic feet (45 gallons) for the first 100 sq ft plus 1 cubic foot (7.48 gal) for each additional 100 sq ft of drained area, vented independently to the atmosphere with a minimum 2-inch dedicated vent .
Interceptor Classifications: HGIs vs. Gravity Grease Interceptors (GGIs)
Commercial food service facilities produce large volumes of animal fats, vegetable oils, and grease (FOG). Left untreated, FOG solidifies in municipal sewer mains, causing severe sanitary sewer overflows (SSOs). The code categorizes grease recovery into two primary engineering technologies:
Loading diagram...
Technical Comparison: HGI vs. GGI
- Engineering Parameter Hydro-mechanical Grease Interceptors (HGI) Gravity Grease Interceptors (GGI)
- Governing Standards ASME A112.14.3 / PDI G101 / CSA B481 IAPMO/ANSI Z1001 / NCPC 1003.3.4
Installation Location Indoors, directly adjacent to fixtures or recessed in floor Outdoors, underground below grade (accessible to pumper trucks)
Primary Separation Mechanism Flow restriction, internal baffling, and air-entrainment flotation Long hydraulic retention time ( t ≥ 30 minutes t \ge 30\text{ minutes} t ≥ 30 minutes ) under laminar gravity flow
Sizing Metric Flow Rate in GPM (10, 15, 20, 25, 35, 50, 75, 100 GPM) Total Liquid Volume in Gallons (typically 500–2,500+ gal)
Grease Capacity Standard Minimum 2 × GPM Flow Rating 2 \times \text{GPM Flow Rating} 2 × GPM Flow Rating in pounds of grease Governed by internal vault volume and 25% sludge/grease depth rule
Flow Control Device Mandatory: Vented flow control fitting with atmospheric air intake Not used (direct gravity influent pipe)
- Piping Material Schedule 40 PVC/CPVC, Cast Iron, Stainless Steel Schedule 40 PVC DWV, SDR-35, Cast Iron
- HGI Sizing Calculations & Fixture Flow Rate Math
Hydro-mechanical interceptors are sized by calculating the total peak drainage flow from all connected fixtures.
1. Fixture Volumetric Sizing Formula
To determine the required GPM rating for a commercial fixture (such as a 3-compartment sink), calculate its internal volume in cubic inches, convert to liquid gallons, apply the 75% load factor, and divide by the drain-down period (typically 1 minute or 2 minutes ): Total Compartment Volume (cu in) = Length (in) × Width (in) × Depth (in) × ( Number of Compartments ) \text{Total Compartment Volume (cu in)} = \text{Length (in)} \times \text{Width (in)} \times \text{Depth (in)} \times (\text{Number of Compartments}) Total Compartment Volume (cu in) = Length (in) × Width (in) × Depth (in) × ( Number of Compartments ) Total Liquid Capacity (Gallons) = Total Volume (cu in) 231 cu in/gal \text{Total Liquid Capacity (Gallons)} = \frac{\text{Total Volume (cu in)}}{231\text{ cu in/gal}} Total Liquid Capacity (Gallons) = 231 cu in/gal Total Volume (cu in) Design Drainage Load (75% Fill) = Total Capacity (Gallons) × 0.75 \text{Design Drainage Load (75\% Fill)} = \text{Total Capacity (Gallons)} \times 0.75 Design Drainage Load (75% Fill) = Total Capacity (Gallons) × 0.75 Required Flow Rate (GPM) = Design Drainage Load (Gallons) Drain-down Time (1 or 2 Minutes) \mathbf{\text{Required Flow Rate (GPM)}} = \frac{\text{Design Drainage Load (Gallons)}}{\text{Drain-down Time (1 or 2 Minutes)}} Required Flow Rate (GPM) = Drain-down Time (1 or 2 Minutes) Design Drainage Load (Gallons) Minimum Grease Retention Capacity (lbs) = Required Flow Rate (GPM) × 2 \mathbf{\text{Minimum Grease Retention Capacity (lbs)}} = \text{Required Flow Rate (GPM)} \times \mathbf{2} Minimum Grease Retention Capacity (lbs) = Required Flow Rate (GPM) × 2
Worked Step-by-Step Problem: Sizing a 3-Compartment Pot Sink HGI
Scenario: A restaurant installs a commercial 3-compartment stainless steel pot sink. Each compartment measures 24 inches long, 24 inches wide, and 14 inches deep . Determine the required HGI flow rate (GPM) and grease retention capacity (lbs) based on a 1-minute drain-down time .
Calculate Total Volume in Cubic Inches: Volume per Compartment = 24 " × 24 " × 14 " = 8 , 064 cu in \text{Volume per Compartment} = 24" \times 24" \times 14" = 8,064\text{ cu in} Volume per Compartment = 24" × 24" × 14" = 8 , 064 cu in Total Volume (3 Compartments) = 8 , 064 × 3 = 24 , 192 cu in \text{Total Volume (3 Compartments)} = 8,064 \times 3 = \mathbf{24,192\text{ cu in}} Total Volume (3 Compartments) = 8 , 064 × 3 = 24 , 192 cu in
Convert to Liquid Gallons ( 231 cu in/gal 231\text{ cu in/gal} 231 cu in/gal ): Total Capacity = 24 , 192 231 = 104.73 gallons \text{Total Capacity} = \frac{24,192}{231} = \mathbf{104.73\text{ gallons}} Total Capacity = 231 24 , 192 = 104.73 gallons
Apply the 75% Displacement / Fill Factor: Design Load = 104.73 × 0.75 = 78.55 gallons \text{Design Load} = 104.73 \times 0.75 = \mathbf{78.55\text{ gallons}} Design Load = 104.73 × 0.75 = 78.55 gallons
Calculate Flow Rate for 1-Minute Drainage: Flow Rate = 78.55 gal 1 min = 78.55 GPM \text{Flow Rate} = \frac{78.55\text{ gal}}{1\text{ min}} = \mathbf{78.55\text{ GPM}} Flow Rate = 1 min 78.55 gal = 78.55 GPM (Rounding up to the next standard commercial HGI size yields a 100 GPM interceptor, or 50 GPM if evaluated under a 2-minute drain-down schedule: 78.55 / 2 = 39.28 GPM ⟹ 50 GPM 78.55 / 2 = 39.28\text{ GPM} \implies 50\text{ GPM} 78.55/2 = 39.28 GPM ⟹ 50 GPM ) .
Calculate Minimum Grease Retention Capacity for a 50 GPM Unit: Grease Retention Capacity = 50 GPM × 2 = 100 lbs of grease \text{Grease Retention Capacity} = 50\text{ GPM} \times 2 = \mathbf{100\text{ lbs of grease}} Grease Retention Capacity = 50 GPM × 2 = 100 lbs of grease
The Flow Control Fitting & Air Intake Mechanism
A critical requirement of ASME A112.14.3 / PDI G101 hydro-mechanical grease interceptors is the flow control fitting with an air intake : [Fixture Drain] ──► [Flow Control Orifice] ──► [Air Intake Vent] ──► [HGI Inlet]
- │ │
- Regulates GPM Entrains Air Bubbles
- to match rating for Grease Flotation
Flow Regulation: Without a flow control fitting, a surge from a filled sink would overwhelm the interceptor at 60+ GPM, causing turbulence that flushes accumulated grease out into the building sewer.
Air Entrainment Flotation: The air intake pulls atmospheric air into the flowing stream via venturi effect. The resulting microscopic air bubbles adhere to lightweight grease droplets, rapidly floating them to the surface grease mat before wastewater escapes under the downstream baffle.
Air Intake Venting: The air intake of the flow control device must be extended to the atmosphere or connect to the sanitary vent system at an elevation higher than the fixture flood level rim.
Fixture Connection Rules & Prohibitions (NCPC 1003.3)
Connected Fixture Category Code Status & Connection Requirements Technical Justification
Pot Sinks & 3-Compartment Sinks Mandatory Connection: Must discharge directly to grease interceptor. Primary source of heavy cooking oils, animal fat, and grease wash water.
Commercial Dishwashers Mandatory Connection (unless local sewer authority directs otherwise). Discharges high-temperature water ( 180 ∘ F 180^{\circ}\text{F} 18 0 ∘ F ) and emulsified grease; requires high-capacity interceptor.
Wok Ranges & Tilt Skillets Mandatory Connection: Drain troughs and floor sinks must route to HGI/GGI. Heavy grease and oil residue from high-heat frying.
Kitchen Floor Drains & Sinks Mandatory Connection: All floor drains in cooking and food prep zones. Captures mop water, spills, and wash-down grease.
Commercial Food Waste Disposers PROHIBITED ahead of grease interceptors UNLESS preceded by an approved solids interceptor . Food waste shreds settle in the grease interceptor, causing rapid anaerobic putrefaction and destroying grease separation.
Sanitary Waste (Toilets/Urinals) STRICTLY PROHIBITED: Can never connect to or pass through any interceptor. Human waste introduces pathogens and raw solids, violating all public health standards.
Point-of-Use Temperature Rule Water entering HGI should ideally not exceed 140 ∘ F 140^{\circ}\text{F} 14 0 ∘ F unless engineered for hot service. High water temperatures ( > 150 ∘ F > 150^{\circ}\text{F} > 15 0 ∘ F ) melt grease, allowing it to pass through interceptor before congealing downstream.
Loading diagram... HGI Piping Assembly with Vented Flow Control
Oil/Water Separators for Automotive Facilities (NCPC 1003.4)
Automotive repair garages, gasoline service stations, car washes, and commercial parking structures generate oily runoff containing volatile hydrocarbons, lubricants, and transmission fluids that present severe fire, explosion, and environmental hazards.
1. Code Mandate & Sizing Formula (NCPC 1003.4)
Under NCPC Section 1003.4, an approved oil/water separator must be installed wherever oily and flammable liquid wastes are generated. The liquid capacity of the separator is mathematically calculated based on drained floor area: Minimum Base Capacity = 6.0 cubic feet (45.0 gallons) for the first 100 sq ft of floor area \mathbf{\text{Minimum Base Capacity}} = \mathbf{6.0\text{ cubic feet (45.0 gallons)}}\text{ for the first 100 sq ft of floor area} Minimum Base Capacity = 6.0 cubic feet (45.0 gallons) for the first 100 sq ft of floor area Additional Capacity = 1.0 cubic foot (7.48 gallons) for each additional 100 sq ft (or fraction thereof) \mathbf{\text{Additional Capacity}} = \mathbf{1.0\text{ cubic foot (7.48 gallons)}}\text{ for each additional 100 sq ft (or fraction thereof)} Additional Capacity = 1.0 cubic foot (7.48 gallons) for each additional 100 sq ft (or fraction thereof) Total Liquid Volume (cu ft) = 6.0 + ( Total Drained Floor Area (sq ft) − 100 100 ) \text{Total Liquid Volume (cu ft)} = 6.0 + \left(\frac{\text{Total Drained Floor Area (sq ft)} - 100}{100}\right) Total Liquid Volume (cu ft) = 6.0 + ( 100 Total Drained Floor Area (sq ft) − 100 ) Total Liquid Volume (Gallons) = Total Volume (cu ft) × 7.48 gal/cu ft \text{Total Liquid Volume (Gallons)} = \text{Total Volume (cu ft)} \times 7.48\text{ gal/cu ft} Total Liquid Volume (Gallons) = Total Volume (cu ft) × 7.48 gal/cu ft
Worked Step-by-Step Problem: Sizing an Auto Shop Oil Separator
Scenario: An automotive service garage in Charlotte, NC has a repair bay floor area of 1,600 square feet draining into floor drains. What is the minimum required liquid capacity of the oil separator in cubic feet and in gallons?
Base Capacity for First 100 sq ft: Base Volume = 6.0 cu ft \text{Base Volume} = 6.0\text{ cu ft} Base Volume = 6.0 cu ft
Calculate Remaining Floor Area: Remaining Area = 1 , 600 sq ft − 100 sq ft = 1 , 500 sq ft \text{Remaining Area} = 1,600\text{ sq ft} - 100\text{ sq ft} = 1,500\text{ sq ft} Remaining Area = 1 , 600 sq ft − 100 sq ft = 1 , 500 sq ft
Calculate Incremental Volume ( 1.0 cu ft per 100 sq ft 1.0\text{ cu ft per 100 sq ft} 1.0 cu ft per 100 sq ft ): Incremental Volume = 1 , 500 100 × 1.0 = 15.0 cu ft \text{Incremental Volume} = \frac{1,500}{100} \times 1.0 = 15.0\text{ cu ft} Incremental Volume = 100 1 , 500 × 1.0 = 15.0 cu ft
Calculate Total Volume in Cubic Feet: Total Volume = 6.0 cu ft + 15.0 cu ft = 21.0 cubic feet \text{Total Volume} = 6.0\text{ cu ft} + 15.0\text{ cu ft} = \mathbf{21.0\text{ cubic feet}} Total Volume = 6.0 cu ft + 15.0 cu ft = 21.0 cubic feet
Convert to Gallons ( 7.48 gal/cu ft 7.48\text{ gal/cu ft} 7.48 gal/cu ft ): Total Gallons = 21.0 cu ft × 7.48 gal/cu ft = 157.08 gallons \text{Total Gallons} = 21.0\text{ cu ft} \times 7.48\text{ gal/cu ft} = \mathbf{157.08\text{ gallons}} Total Gallons = 21.0 cu ft × 7.48 gal/cu ft = 157.08 gallons
Structural Construction & Dedicated Independent Venting Rules
Oil/water separators are subject to stringent construction and venting requirements due to explosive hydrocarbon vapor accumulation:
Loading diagram...
Vapor-Tight Enclosure: The separator body, access manholes, and inspection covers must be manufactured from non-combustible, corrosion-resistant cast iron, steel, or reinforced concrete sealed gas-tight and vapor-tight.
Deep Water Trap Seal: The discharge outlet must be configured with a submerged inverted elbow or baffle providing a water seal of not less than 4 inches (102 mm) to prevent flammable vapors from entering the public sewer.
Mandatory Independent 2-Inch Vent (NCPC 1003.4.2.2):
Every oil separator must be provided with an independent vent pipe not less than 2 inches (51 mm) in diameter.
The vent must connect to the vapor space above the liquid line inside the separator.
The vent must extend independently through the roof to the outer air and CANNOT be tied into any sanitary DWV vent or plumbing stack vent .
Why? Interconnecting oil separator vents with building sanitary vents could allow explosive gasoline vapors to migrate into building plumbing fixtures.
Sand, Grit & Solids Interceptors (NCPC 1003.5 / 1003.8)
Where wastewater contains heavy suspended mineral solids, sand, grit, glass, or lint, approved sand/solids interceptors are mandatory:
Automotive Wash Racks & Car Washes: Must be equipped with a sediment interceptor (sand trap pit) having a minimum liquid depth of 24 inches below the invert of the outlet pipe and a cleanout access opening of at least 2 square feet before discharging into an oil separator.
Commercial Laundries: Interceptors must be equipped with removable wire mesh lint screens or baskets with maximum 1/2-inch openings to capture fibrous lint before fouling drain mains.
Bottling Plants & Machine Shops: Interceptors must retain glass chips, metal shavings, and heavy grit.