1 Introduction & Exam Overview

1.1 About the NCCCO Rigger Level I Exam 1.2 Level I vs Level II Scope 1.3 Eligibility, Fees, and Recertification

2 Scope: Load Path and Characteristics

2.1 Identifying the Load Travel Path 2.2 Load Weight and Center of Gravity 2.3 Attachment Points and Lift Points

3 Scope: Hazards and Unsafe Practices

3.1 Special Handling Requirements 3.2 Pinch Points and Softeners 3.3 Load Stability, Shock Load, and Side Loading 3.4 Electrical Hazards, Body Positioning, and Hazard Communication

4 Technical Knowledge: ASME Standards

4.1 ASME B30.9 Slings and B30.10 Hooks 4.2 ASME B30.26 Hardware and B30.20 Below-the-Hook

5 Technical Knowledge: OSHA Regulations

5.1 OSHA 1910.184 and 1926.251 5.2 OSHA 1926.1401 Qualified Rigger 5.3 OSHA 1926.1431 Hoisting Personnel

6 Inspection: Foundations, Wire Rope, and Chain

6.1 Frequent vs Periodic Inspection 6.2 Wire Rope Sling Inspection and Removal Criteria 6.3 Chain Sling Inspection and Removal Criteria

7 Inspection: Synthetic and Specialty Slings

7.1 Synthetic Web Sling Inspection 7.2 Synthetic Round Sling Inspection 7.3 Metal Mesh and Synthetic Rope Sling Inspection

8 Inspection: Hooks, Hardware, and Below-the-Hook Devices

8.1 Hook Inspection (ASME B30.10) 8.2 Shackles, Eyebolts, and Hardware Inspection 8.3 Below-the-Hook Device Inspection

9 Execution: Sling Types and Identification

9.1 Chain and Wire Rope Sling Use 9.2 Synthetic Web and Round Sling Use 9.3 Sling Identification Tags and WLL

10 Execution: Hitches, Angles, and Capacity

10.1 Vertical, Choker, and Basket Hitches 10.2 Sling Angle Factors 10.3 Hitch Capacity Calculations 10.4 Edge Protection and D/d Ratio

11 Execution: Rigging Hardware in Use

11.1 Shackles and Hooks in Use 11.2 Eyebolts and Swivel Hoist Rings 11.3 Wire Rope Clips and Compression Hardware 11.4 Blocks, Beam Clamps, Softeners, and Related Gear

12 Execution: Below-the-Hook Devices, Tag Lines, and Knots

12.1 Below-the-Hook Lifting Devices 12.2 Tag Line Use and Load Control 12.3 Basic Knots for Riggers

13 Execution: Post-Lift Activities and Communication

13.1 Securing, Disconnecting, and Stowing Gear 13.3 Stop Authority and Lift Communication

14 Practical Exam Prep and Study Strategy

14.1 Level I Practical Exam Tasks 14.2 Study Strategy and Exam Day

6.2 Wire Rope Sling Inspection and Removal Criteria

Key Takeaways Explain This Topic AI

Inspect the full rope body, eyes/splices, and end fittings every use; broken wires, birdcaging, kinks, crushing, heat damage, severe corrosion, core protrusion, and missing tags are core rejection drivers.

Classic exam-level broken-wire criteria for many wire rope slings align with OSHA/ASME language: ten randomly distributed broken wires in one rope lay, or five broken wires in one strand in one lay (know the concept; follow manufacturer and current standard for product type).

Distortion (birdcage, kink, crush) and heat damage remove a sling from service even when broken-wire counts are not yet met.

Eyes, mechanical splices, poured/swaged sockets, and thimbles must be free of cracks, severe wear, and deformation; never use a sling with unreadable identification.

Last updated: July 2026

6.2 Wire Rope Sling Inspection and Removal Criteria

Quick Answer: Remove a wire rope sling from service for broken wires beyond criteria , birdcaging/kinks/crushing , heat damage , severe corrosion , core protrusion , damaged eyes or fittings , or a missing/illegible ID tag . Do not “use it carefully” or cut the WLL by half in the field— quarantine it .

Wire rope slings are common on construction and industrial sites because they handle abrasion and heat better than many synthetics and offer high strength in a compact package. They still fail catastrophically when outer wires break, the core protrudes, or the rope structure is distorted. NCCCO Level I inspection questions lean heavily on recognizing defects and applying removal criteria in the language of ASME B30.9 and OSHA (e.g., 1910.184 / 1926.251 concepts).

How to Inspect a Wire Rope Sling (Frequent Check)

Work systematically so you do not miss localized damage:

Identification — Read the tag. Confirm rated load for the hitch type you plan to use (vertical, choker, basket ratings may differ). No tag or unreadable tag → out of service.

Entire length of each leg — Walk the rope slowly. Pay special attention to areas that were previously choked, sat on edges, or rubbed fittings.

Outer wires and strands — Look for broken wires (ends may be needle-sharp—use care), worn flats, and corrosion between strands.

Rope structure — Check for birdcaging, kinks, crushed sections, waviness, core protrusion, or unlaying.

Eyes and splices — Flemish eyes, mechanical splices, hand tucks (where used), thimbles, and seizing.

End fittings — Sockets, sleeves, master links, hooks attached as part of the sling assembly.

Disposition — Accept, or tag and remove.

Lighting matters. Mud, grease, and paint can hide broken wires; clean enough of the rope to see the wires you are judging. Do not spin a dirty rope against bare skin—broken wire ends cut deeply.

  • Defect Catalog — What You Are Looking For
  • Broken Wires

Broken wires are the classic wire-rope rejection topic. They often concentrate where the rope bends over a hook, pin, or load edge, or where a choker hitch has worked the same zone repeatedly.

Exam-level criteria (widely tested OSHA / B30-style language for many running ropes and wire rope slings):

  • Criterion Typical threshold concept
  • Random broken wires in one rope lay 10 randomly distributed broken wires in one rope lay
  • Broken wires in one strand in one lay 5 broken wires in one strand in one rope lay

Localized damage Severe localized clustering, even if “count math” is debated—remove when structural integrity is compromised

Valley breaks / severe wear Broken wires in the valleys or wear that removes substantial outer-wire diameter—treat as critical

A rope lay is the length along the rope in which one strand makes one complete turn around the core. You do not need to be a metallurgist on the written exam, but you must know that broken-wire counts are measured in a lay length , not “somewhere on the whole sling,” and that one strand with five breaks can condemn the sling even if total breaks on the rope are under ten.

Product-type note: Braided multi-part slings and some specialty constructions can have additional or different criteria in the governing B30.9 section and manufacturer instructions. On the exam, when a scenario cites the classic “10 in one lay / 5 in one strand” language, apply that concept. In the field, follow the manufacturer and current standard for that exact sling type .

Birdcaging

Birdcaging is a distortion where outer strands open outward like a birdcage, often from sudden release of tension, shock unloading, or forced rotation against a fixed end. It indicates the rope’s geometry is permanently disrupted. Remove from service —you cannot “massage” strands back into a load-rated rope.

Kinks

A kink is a sharp permanent bend where strands and wires are permanently deformed. Kinks often form when a loop is pulled tight or when the rope is improperly uncoiled. A kinked section is a stress riser and a rejection condition for sling service.

Crushing and Flattening

Crushing flattens the rope’s cross-section—common when a load sets down on a sling, a vehicle runs over it, or the rope is pinched in a sheave or under a load corner. Crushed rope has lost structural shape; remaining strength is not something a rigger field-calculates. Remove from service.

Heat Damage

Heat damage may show as blueing, blackening, fused wires, loss of lubricant with scorched appearance, or nearby evidence of welding/cutting sparks. Wire rope that has been heated beyond manufacturer limits can lose strength without dramatic broken-wire counts. Evidence of heat damage → remove from service.

Corrosion

Light surface rust after outdoor use may be cleaned and reassessed, but severe corrosion , deep pitting, or corrosion that freezes wires together and hides broken wires is a reject condition. Corrosion inside the rope (especially with fiber cores or poor lubrication history) can be worse than it looks. When corrosion raises doubt, remove from service and escalate to competent-person evaluation—do not guess remaining capacity.

Core Protrusion

Core protrusion (core popping out between strands or at ends) means the rope’s internal support is displaced. It is a serious structural defect. Remove from service.

Wear and Abrasion

Outer wires can wear into flat spots from rubbing on loads or structures. OSHA-style language often references wear or scraping of about one-third the original diameter of outside individual wires as a removal concept for wire rope. Severe abrasion that cuts or thins wires rapidly is treated the same as structural damage: out of service.

Missing or Illegible Tags

If you cannot read the sling’s rated load and required identification, you cannot select it legally or safely. Missing or illegible identification = remove from service.

Removal Criteria Quick Reference (Wire Rope Slings)

  • Defect / condition Action
  • 10 randomly distributed broken wires in one rope lay Remove from service
  • 5 broken wires in one strand in one rope lay Remove from service
  • Birdcaging, kinking, crushing, or other structural distortion Remove from service
  • Heat damage (discoloration, fused wires, arc damage) Remove from service
  • Severe corrosion or corrosion that creates doubt Remove from service
  • Core protrusion Remove from service
  • Severe abrasion / outer-wire wear beyond criteria Remove from service
  • Cracked, deformed, or worn end attachments Remove from service
  • Missing or illegible ID Remove from service
  • Any condition that creates doubt as to continued use Remove from service pending evaluation
  • Eyes, Splices, and Fittings

Wire rope slings commonly use:

  • Feature Inspection focus
  • Eye / loop Distortion, broken wires at the crotch of the eye, thimble seated and not cracked
  • Flemish eye with mechanical sleeve Sleeve cracks, severe wear, movement, improper installation signs
  • Hand-spliced eyes (where permitted by design) Pulled tucks, broken wires at splice, unlaying
  • Poured / swaged sockets Cracks, bent shanks, worn pin holes, evidence of pull-out
  • Thimbles Collapse, cracks, thimble walking out of the eye
  • Master links / rings on multi-leg assemblies Stretch, cracks, wear at bearing points

Broken wires often concentrate at the eye crotch and at the entry to a sleeve or socket . Do not inspect only the middle of the leg.

Hooks that are part of a sling assembly follow hook removal ideas (throat opening increase, twist out of plane, cracks)—detailed in the hook inspection chapter. If the hook is defective, the assembly is out of service even if the rope body looks fine.

D/d, Edges, and Why Damage Starts

Wire rope is sensitive to tight bends. Choking on a small diameter or pulling over a sharp corner creates high localized bending stress and abrasion—exactly where broken wires and crushing appear. Edge protection and adequate pin/hook diameter (D/d awareness) are use topics, but they explain why inspection focuses on choke zones and contact points. After any lift where the rope was shock-loaded, side-loaded hard against a corner, or heated, re-inspect before reuse .

  • What Level I Does Not Do
  • Does not re-rate a damaged sling to a lower WLL by personal judgment

Does not cut out a bad section and re-eye a sling in the field unless working under manufacturer-authorized processes (generally not Level I scope)

  • Does not ignore a few broken wires because “it still looks strong”
  • Does not use a sling with no tag because “we know it’s a half-inch rope”
  • Storage and Care That Protect the Next Inspection
  • Store off the ground, away from chemicals and excessive heat
  • Avoid running over slings with equipment
  • Uncoil and handle rope to prevent kinks
  • Keep incompatible chemicals and weld spatter off the rope
  • Return slings to designated racks so damaged units can be segregated
  • Exam Focus

Written items often give a short defect description (“birdcage after shock unload,” “five broken wires in one strand in one lay,” “tag unreadable,” “blue heat marks near the eye”) and ask for the correct action. The safe, testable answer is almost always remove from service . Distractors include continuing at reduced load, waiting for the annual periodic date, or repairing with wire and tape. Choose the answer that matches criteria-based removal and immediate segregation .