1.2 Practical Tasks and Examination-Specific Rules

NCCCO Rigger Level II Exam

Track your progress as you read

Finished sections get a check mark.

1 Certification and Exam Preparation

1.1 Current Exam, Eligibility and Scheduling 1.2 Practical Tasks and Examination-Specific Rules 1.3 Study Method, References and Recertification

2 Identify and Measure the Load

2.1 Load Identity, Dimensions and Units 2.2 Load Weight, Density and Complete Inventories 2.3 Composition, Structural Integrity and Special Handling

3 Center of Gravity and Support Geometry

3.1 Center of Gravity and Suspended Stability 3.2 Attachment Points and Complete Force Paths 3.3 Final Position, Landing Supports and Derigging Access

4 Route and Site Hazards

4.1 Travel Path, Clearance and Work-Zone Control 4.2 Power Lines, Clearance Options and Electrical Response 4.3 Weather, Temperature and Ground Conditions

5 Team Duties and Communications

5.1 Signalperson Duties and Reliable Signals 5.2 Equipment Operator Duties and Capacity Decisions 5.3 Lift Director, Qualified Rigger and Hazard Communication

6 Equipment Requirements and Lift Planning

6.1 Determine Equipment Requirements and Compatibility 6.2 Written Plans, Sequence and Change Control 6.3 Critical-Lift Criteria, Risk and Contingencies

7 Balanced Sling Forces

7.1 Two-Leg Tension and Angle Reference 7.2 Length-to-Height Geometry and Headroom 7.3 Horizontal Forces and Attachment Demand

8 Composite and Unequal Loads

8.1 Composite Center of Gravity by Moments 8.2 Off-Center Reactions and Compatible Sling Geometry 8.3 Three- and Four-Leg Assemblies and Load Sharing

9 Wire Rope, Chain and Metal Mesh Slings

9.1 Select and Use Wire-Rope Slings 9.2 Alloy-Chain Assemblies and Approved Adjustment 9.3 Metal-Mesh Slings: Selection, Contact and Removal

10 Synthetic Rope, Web and Roundslings

10.1 Synthetic-Rope Slings and Approved Splices 10.2 Synthetic-Web Slings and Material Compatibility 10.3 Roundslings, Core Protection and Performance Fibers

11 Hitch Application and Sling Protection

11.1 Vertical and Basket Hitch Capacity 11.2 Choker Hitches, Choke Angle and Bundles 11.3 Softeners, Bend Protection and Cut Protection

12 Shackles, Hooks and Collector Hardware

12.1 Shackle Types, Pin Seating and Side Loading 12.2 Hooks, Latches and Permitted Load Seating 12.3 Master Links, Rings and Swivels

13 Threaded Points and Adjustable Hardware

13.1 Eyebolts, Shoulder Seating and Angular Demand 13.2 Swivel Hoist Rings and Installation Torque 13.3 Turnbuckles and Chain Hardware in Adjustable Systems

14 Compression Hardware and Rigging Blocks

14.1 Wire-Rope Clips and Permitted Terminations 14.2 Wedge Sockets, Rope Alignment and Tail Security 14.3 Rigging Blocks, Resultants and Reeving

15 Manual, Lever and Powered Hoists

15.1 Manual Chain Falls and Vertical Hoisting 15.2 Lever Hoists, Pulling Direction and Controlled Adjustment 15.3 Air and Electric Hoists: Supply, Duty and Controls

16 Jacks, Rollers and Portable Supports

16.1 Jacks, Toe Ratings and Positive Support 16.2 Dollies, Skates, Rollers and Horizontal Control 16.3 A-Frames, Gantries and Trolley Compatibility

17 Structural Lifters and Clamps

17.1 Lifting Beams, Spreaders and Configuration Ratings 17.2 Plate Clamps, Material Limits and Grip Conditions 17.3 Beam Clamps as Attachments and Beam/Girder Lifters

18 Mechanical, Vacuum and Magnetic Devices

18.1 Mechanical and Vacuum Lifting Devices 18.2 Close-Proximity and Remotely Operated Lifting Magnets 18.3 Scrap and Material-Handling Grapples

19 Inspection, Removal and Records

19.1 Inspecting All Six Sling Families 19.2 Hook and Rigging-Hardware Inspection 19.3 Below-the-Hook Device Inspection and Testing

20 Lift Control, Rotation and Completion

20.1 Take-Up, Trial Lift and Load Control 20.2 Controlled Rotation, Upending and Multiple-Crane Lifts 20.3 Secure the Load, Remove Rigging and Stow Equipment

21 Technical Standards and Crane Capacity

21.1 Apply the Correct Standard and Regulatory Scope 21.2 Crane Charts, Suspended Weight and Capacity Deductions 21.3 Personnel Hoisting Under OSHA 1926.1431

1.2 Practical Tasks and Examination-Specific Rules

Key Takeaways Explain This Topic AI

The level lift permits two attempts and requires a final level position within one degree.

The frame rotation permits three attempts and requires a controlled 90-degree turn with final level within two degrees.

Never add, adjust or remove rigging while the test frame is suspended.

Hand-tightening and omission of softeners are examination-specific instructions.

Last updated: October 2026

Separate the course rules from field practice

The Level II practical examination assesses a level lift and a controlled frame rotation. It is a defined test course with selected equipment, time limits and scoring instructions. Its exceptions are not permission to disregard manufacturer installation procedures on a job. In particular, the handbook’s hand-tightening and softener instructions belong to this examination only.

Before testing, read the Level II practical outline in the current handbook rather than applying the Level I outline. Level I includes separate pre-use inspection and connection tasks. For Level II, the provided slings and hardware are approved for use and do not require pre-use inspection during the exam . Candidates receive up to three minutes to evaluate the gear before starting. This familiarization period is time to identify available components and plan the task, not a substitute for learning the equipment beforehand.

An unsafe act is an uncontrolled or reckless action sufficient to create concern for persons or property. The proctor may stop the test for safety. Disqualification for an unsafe act prevents additional practical examinations that day. Do not invent a complete list of automatic failures from field anecdotes; learn the actual handbook instructions and ask the proctor about an unclear direction before the task begins.

Task 1: Level Lift

The level lift is performed first. On the proctor’s start indication, timing begins and the candidate selects and applies slings or hardware to the frame. The objective is a suspended position within one degree of true level . The larger measurement in the two planes is used for final level evaluation after the candidate says “Done.” A result outside the stated tolerance on the final attempt produces a performance deduction.

The candidate has a maximum of 15 minutes and two lifting attempts . If the first attempt is unsuccessful, the frame must return to the original starting position before another attempt. Any frame movement caused by hoisting counts as a lifting attempt. Taking tension until the frame moves and then calling it “only a check” does not erase that attempt.

Use at least three and no more than four sling legs on the frame. The second chain-fall hoist may not be used for this task. Select attachment points and sling lengths before requesting motion; an off-center center of gravity makes equal sling lengths an unreliable assumption for a level frame. Use the same moment and geometry reasoning taught in the calculation chapters, within the permitted equipment and course constraints.

Task 2: Rigging Frame Rotation

For rotation, lift the frame clear of the ground and rotate it 90 degrees under control . A rope tied on the frame marks the required final “up” side. The final frame must be within two degrees of true level , with a maximum of three attempts and 30 minutes . This is not an unrestricted 180-degree turnover task.

Begin with three or four slings and finish with tension on at least two pick points. The second chain-fall hoist may be used for rotation. Its load chain must remain straight throughout the attempt; failing that instruction is an unsafe act. Consider how the selected slings change position, tension and contact as the frame rotates, instead of checking only the starting arrangement.

An unsuccessful attempt requires return to the original starting position. If the frame touches the ground during the first or second rotation attempt, return to the original starting position before the next attempt. Ground contact during the third attempt ends the task. Before the frame leaves the ground, rotation on the ground may not exceed 15 degrees.

  • Practical feature Level lift Frame rotation
  • Time limit 15 minutes 30 minutes
  • Maximum attempts Two Three
  • Final level tolerance One degree Two degrees
  • Second chain-fall Not permitted Permitted
  • Required motion Level suspension Controlled 90-degree rotation
  • Instructions that apply to both tasks

The frame starts on either side in its “L” position. Do not attach rigging at the center of gravity or within 12 inches of it. Do not climb on the frame, point-load rigging over its corner while freely suspended, or add, adjust or remove rigging while the load is suspended. An adjustment requires an appropriate set-down, not reaching into tensioned hardware.

The handbook directs candidates to hand-tighten hardware and nuts only and states that softeners are not used or provided for these tasks. In field service, a hoist ring may require specified installation torque, and a sling may require selected edge protection. Follow those field instructions outside the practical course. Memorizing the exception without its examination context would teach an unsafe habit.

After each task, break down the rigging and return components to the rigging table. The handbook addresses additional scoring details such as tag location, twists, binding and contact between the hook and chain-fall housing. Binding means hardware is prevented from aligning with the applied force. Evaluate the connection through the entire maneuver so a freely moving shackle at the start does not wedge against the frame during rotation.

A preparation decision

A candidate practicing with a suspended frame notices that a sling has trapped an adjustment device against an edge. The useful response is to stop, safely return to the starting support, and redesign the connection. Pushing the fitting into alignment by hand while the frame hangs is inconsistent with the no-adjustment rule and places the candidate near a pinch point. Practice should build a predictable sequence of planning, connecting, clearing personnel, moving, evaluating and setting down.

Source: CCO Rigger Candidate Handbook, Level II practical outline .