6.2 Written Plans, Sequence and Change Control
NCCCO Rigger Level II Exam
Track your progress as you read
Finished sections get a check mark.
1 Certification and Exam Preparation
1.1 Current Exam, Eligibility and Scheduling 1.2 Practical Tasks and Examination-Specific Rules 1.3 Study Method, References and Recertification
2 Identify and Measure the Load
2.1 Load Identity, Dimensions and Units 2.2 Load Weight, Density and Complete Inventories 2.3 Composition, Structural Integrity and Special Handling
3 Center of Gravity and Support Geometry
3.1 Center of Gravity and Suspended Stability 3.2 Attachment Points and Complete Force Paths 3.3 Final Position, Landing Supports and Derigging Access
4 Route and Site Hazards
4.1 Travel Path, Clearance and Work-Zone Control 4.2 Power Lines, Clearance Options and Electrical Response 4.3 Weather, Temperature and Ground Conditions
5 Team Duties and Communications
5.1 Signalperson Duties and Reliable Signals 5.2 Equipment Operator Duties and Capacity Decisions 5.3 Lift Director, Qualified Rigger and Hazard Communication
6 Equipment Requirements and Lift Planning
6.1 Determine Equipment Requirements and Compatibility 6.2 Written Plans, Sequence and Change Control 6.3 Critical-Lift Criteria, Risk and Contingencies
7 Balanced Sling Forces
7.1 Two-Leg Tension and Angle Reference 7.2 Length-to-Height Geometry and Headroom 7.3 Horizontal Forces and Attachment Demand
8 Composite and Unequal Loads
8.1 Composite Center of Gravity by Moments 8.2 Off-Center Reactions and Compatible Sling Geometry 8.3 Three- and Four-Leg Assemblies and Load Sharing
9 Wire Rope, Chain and Metal Mesh Slings
9.1 Select and Use Wire-Rope Slings 9.2 Alloy-Chain Assemblies and Approved Adjustment 9.3 Metal-Mesh Slings: Selection, Contact and Removal
10 Synthetic Rope, Web and Roundslings
10.1 Synthetic-Rope Slings and Approved Splices 10.2 Synthetic-Web Slings and Material Compatibility 10.3 Roundslings, Core Protection and Performance Fibers
11 Hitch Application and Sling Protection
11.1 Vertical and Basket Hitch Capacity 11.2 Choker Hitches, Choke Angle and Bundles 11.3 Softeners, Bend Protection and Cut Protection
12 Shackles, Hooks and Collector Hardware
12.1 Shackle Types, Pin Seating and Side Loading 12.2 Hooks, Latches and Permitted Load Seating 12.3 Master Links, Rings and Swivels
13 Threaded Points and Adjustable Hardware
13.1 Eyebolts, Shoulder Seating and Angular Demand 13.2 Swivel Hoist Rings and Installation Torque 13.3 Turnbuckles and Chain Hardware in Adjustable Systems
14 Compression Hardware and Rigging Blocks
14.1 Wire-Rope Clips and Permitted Terminations 14.2 Wedge Sockets, Rope Alignment and Tail Security 14.3 Rigging Blocks, Resultants and Reeving
15 Manual, Lever and Powered Hoists
15.1 Manual Chain Falls and Vertical Hoisting 15.2 Lever Hoists, Pulling Direction and Controlled Adjustment 15.3 Air and Electric Hoists: Supply, Duty and Controls
16 Jacks, Rollers and Portable Supports
16.1 Jacks, Toe Ratings and Positive Support 16.2 Dollies, Skates, Rollers and Horizontal Control 16.3 A-Frames, Gantries and Trolley Compatibility
17 Structural Lifters and Clamps
17.1 Lifting Beams, Spreaders and Configuration Ratings 17.2 Plate Clamps, Material Limits and Grip Conditions 17.3 Beam Clamps as Attachments and Beam/Girder Lifters
18 Mechanical, Vacuum and Magnetic Devices
18.1 Mechanical and Vacuum Lifting Devices 18.2 Close-Proximity and Remotely Operated Lifting Magnets 18.3 Scrap and Material-Handling Grapples
19 Inspection, Removal and Records
19.1 Inspecting All Six Sling Families 19.2 Hook and Rigging-Hardware Inspection 19.3 Below-the-Hook Device Inspection and Testing
20 Lift Control, Rotation and Completion
20.1 Take-Up, Trial Lift and Load Control 20.2 Controlled Rotation, Upending and Multiple-Crane Lifts 20.3 Secure the Load, Remove Rigging and Stow Equipment
21 Technical Standards and Crane Capacity
21.1 Apply the Correct Standard and Regulatory Scope 21.2 Crane Charts, Suspended Weight and Capacity Deductions 21.3 Personnel Hoisting Under OSHA 1926.1431
6.2 Written Plans, Sequence and Change Control
Key Takeaways Explain This Topic AI
A required plan’s form and approval depend on the applicable operation and policy.
Include securing and rigging removal in the sequence.
Equal WLL does not establish a substitute’s geometric compatibility.
Last updated: October 2026
Write the assumptions needed for execution
A written rigging or lift plan turns the proposed movement into a reviewable sequence. Its required form and approval depend on the operation, applicable law and owner or project policy. It is incorrect to claim that every routine lift has the same mandatory engineer-stamped document. It is equally incorrect to treat a required written plan as optional because the crew has performed similar work before.
A useful plan identifies the load and its configuration, weight and CG information, pick locations, selected equipment and capacities, route, destination supports, personnel roles and hold points. It also states the assumptions that make the calculations valid. If the calculation uses a level load, equal-height picks and a particular hook location, the field team needs to know those conditions.
Plans should identify the evidence behind their inputs: drawing revision, manufacturer information, weighing method, equipment chart or supplied assembly rating. A precise calculated answer based on an uncertain dry weight remains uncertain. Establish how unresolved inputs will be resolved before execution instead of concealing them in a rounded total.
Include the entire operating sequence
Describe initial support, connection, take-up, trial lift, travel or rotation, final landing, securing and removal. Specify who gives signals and who verifies each hold point. An instruction to “lift and set” omits the stages where changes in support and force are most likely.
- Plan element Example of useful specificity
- Load Identifier, actual configuration and retained contents
- Rigging Assembly identifiers, hitch, geometry and applicable WLL
- Machine Correct chart, setup, maximum radius and movement restrictions
- Route Swept envelope, obstacles and work-zone controls
- Destination Approved support points and required restraints
- Hold points Condition, observer and permission to continue
- Communication Signal source, method, handoffs and stop procedure
The plan must account for rigging removal. If slings pass beneath the payload, specify clearance or an approved removal method. If connections become inaccessible at the destination, revise the arrangement before the pick. Release of rigging is a planned operation with its own falling-object and pinch hazards.
Keep different limits distinguishable
A manufacturer limit, OSHA requirement and owner criterion may all apply, but they have different purposes. A site might require special review above a stated utilization percentage. That threshold does not automatically become the crane’s new manufacturer rating or a nationwide critical-lift definition. Identify the source and consequence of each limit.
Likewise, a plan may specify fully extended outriggers because that is the selected chart condition. Do not convert this selection into a claim that all partial-outrigger operation is forbidden. The field setup must match the approved plan and manufacturer procedures. A different permitted setup still needs a new capacity review.
The calculation inventory should distinguish physical suspended masses from chart-specific deductions. A stowed attachment might impose a chart adjustment without hanging in a lower sling. Record it in the appropriate capacity calculation without adding it to a lower-leg force that does not carry it.
Define changes that require review
A change is a departure from an assumption or selected condition. Examples include a different sling material, revised attachment location, additional contents, altered crane configuration, changed route or weather outside the approved condition. Record the proposed change, identify affected calculations and get approval from the designated authority.
A substitute shackle with the same WLL may have different pin dimensions or side-load permission. A longer sling may clear an obstruction while reducing angle. An added lifting beam may solve a fit problem while consuming crane capacity. “Equivalent” must be established for the full function, not assumed from a single rating.
Change-control example
The original plan uses two vertical lower slings beneath a beam. At the site, a narrower beam is substituted and the slings incline inward. The lower tension increases and the payload attachments now receive horizontal forces. Even if the substituted beam carries the same rated load, the lower system has changed. The crew must revise geometry, component checks and attachment approval before loading it.
Make the plan usable at the work location
Use clear sketches and labels that match field identifiers. Put units beside dimensions and forces. Separate the sequence from supporting calculations so a person giving signals can find the relevant hold point without searching a long derivation. Provide the equipment procedures and chart notes necessary for the selected operation.
Before the lift, review the plan with the involved workers and confirm they understand their responsibilities. For covered multiple-crane lifts, OSHA 1926.1432 specifically requires the lift director’s review with all workers involved. Personnel hoisting has its own pre-lift meeting requirements. Do not conflate these specific rules into an invented identical legal meeting requirement for every operation.
The plan remains a live control during work. If a trial lift contradicts it, stop and resolve the discrepancy. A signed page does not make an unexpected condition safe, and an experienced crew does not eliminate the need to follow the approved sequence.
Sources: OSHA multiple-crane planning , CCO reference materials .