Study guide
14.1 Wire-Rope Clips and Permitted Terminations
NCCCO Rigger Level II Exam
Track your progress as you read
Finished sections get a check mark.
1 Certification and Exam Preparation
1.1 Current Exam, Eligibility and Scheduling 1.2 Practical Tasks and Examination-Specific Rules 1.3 Study Method, References and Recertification
2 Identify and Measure the Load
2.1 Load Identity, Dimensions and Units 2.2 Load Weight, Density and Complete Inventories 2.3 Composition, Structural Integrity and Special Handling
3 Center of Gravity and Support Geometry
3.1 Center of Gravity and Suspended Stability 3.2 Attachment Points and Complete Force Paths 3.3 Final Position, Landing Supports and Derigging Access
4 Route and Site Hazards
4.1 Travel Path, Clearance and Work-Zone Control 4.2 Power Lines, Clearance Options and Electrical Response 4.3 Weather, Temperature and Ground Conditions
5 Team Duties and Communications
5.1 Signalperson Duties and Reliable Signals 5.2 Equipment Operator Duties and Capacity Decisions 5.3 Lift Director, Qualified Rigger and Hazard Communication
6 Equipment Requirements and Lift Planning
6.1 Determine Equipment Requirements and Compatibility 6.2 Written Plans, Sequence and Change Control 6.3 Critical-Lift Criteria, Risk and Contingencies
7 Balanced Sling Forces
7.1 Two-Leg Tension and Angle Reference 7.2 Length-to-Height Geometry and Headroom 7.3 Horizontal Forces and Attachment Demand
8 Composite and Unequal Loads
8.1 Composite Center of Gravity by Moments 8.2 Off-Center Reactions and Compatible Sling Geometry 8.3 Three- and Four-Leg Assemblies and Load Sharing
9 Wire Rope, Chain and Metal Mesh Slings
9.1 Select and Use Wire-Rope Slings 9.2 Alloy-Chain Assemblies and Approved Adjustment 9.3 Metal-Mesh Slings: Selection, Contact and Removal
10 Synthetic Rope, Web and Roundslings
10.1 Synthetic-Rope Slings and Approved Splices 10.2 Synthetic-Web Slings and Material Compatibility 10.3 Roundslings, Core Protection and Performance Fibers
11 Hitch Application and Sling Protection
11.1 Vertical and Basket Hitch Capacity 11.2 Choker Hitches, Choke Angle and Bundles 11.3 Softeners, Bend Protection and Cut Protection
12 Shackles, Hooks and Collector Hardware
12.1 Shackle Types, Pin Seating and Side Loading 12.2 Hooks, Latches and Permitted Load Seating 12.3 Master Links, Rings and Swivels
13 Threaded Points and Adjustable Hardware
13.1 Eyebolts, Shoulder Seating and Angular Demand 13.2 Swivel Hoist Rings and Installation Torque 13.3 Turnbuckles and Chain Hardware in Adjustable Systems
14 Compression Hardware and Rigging Blocks
14.1 Wire-Rope Clips and Permitted Terminations 14.2 Wedge Sockets, Rope Alignment and Tail Security 14.3 Rigging Blocks, Resultants and Reeving
15 Manual, Lever and Powered Hoists
15.1 Manual Chain Falls and Vertical Hoisting 15.2 Lever Hoists, Pulling Direction and Controlled Adjustment 15.3 Air and Electric Hoists: Supply, Duty and Controls
16 Jacks, Rollers and Portable Supports
16.1 Jacks, Toe Ratings and Positive Support 16.2 Dollies, Skates, Rollers and Horizontal Control 16.3 A-Frames, Gantries and Trolley Compatibility
17 Structural Lifters and Clamps
17.1 Lifting Beams, Spreaders and Configuration Ratings 17.2 Plate Clamps, Material Limits and Grip Conditions 17.3 Beam Clamps as Attachments and Beam/Girder Lifters
18 Mechanical, Vacuum and Magnetic Devices
18.1 Mechanical and Vacuum Lifting Devices 18.2 Close-Proximity and Remotely Operated Lifting Magnets 18.3 Scrap and Material-Handling Grapples
19 Inspection, Removal and Records
19.1 Inspecting All Six Sling Families 19.2 Hook and Rigging-Hardware Inspection 19.3 Below-the-Hook Device Inspection and Testing
20 Lift Control, Rotation and Completion
20.1 Take-Up, Trial Lift and Load Control 20.2 Controlled Rotation, Upending and Multiple-Crane Lifts 20.3 Secure the Load, Remove Rigging and Stow Equipment
21 Technical Standards and Crane Capacity
21.1 Apply the Correct Standard and Regulatory Scope 21.2 Crane Charts, Suspended Weight and Capacity Deductions 21.3 Personnel Hoisting Under OSHA 1926.1431
14.1 Wire-Rope Clips and Permitted Terminations
Key Takeaways Explain This Topic AI
OSHA 1926.251 prohibits clip-formed sling or bridle eyes.
For conventional U-bolt clips, the saddle bears on the live rope.
Use the actual manufacturer table rather than universal spacing or torque values.
Last updated: October 2026
Identify whether clips are permitted
Wire-rope clips clamp a rope’s returned end to form certain permitted terminations. Their suitability depends on the application, rope construction and manufacturer instructions. The CCO blueprint’s clip topic does not waive OSHA restrictions: 1926.251 prohibits forming sling or bridle eyes with wire-rope clips or knots . Determine the intended rope use before discussing how to install a clip.
An approved rope termination on particular equipment is different from a field-made lifting sling. Personnel-platform wire-rope eyes also have specific requirements. Do not use a clip assembly wherever an eye is needed merely because its calculation appears adequate. The applicable regulation and equipment instructions must permit the termination.
Use the identified clip type and material specified for the application. Common lifting-equipment guidance calls for appropriate forged products rather than unapproved malleable utility clips. Avoid claims that visual forge marks alone establish grade, rating or shock resistance. Identification and manufacturer documentation determine what the product is.
Orient a U-bolt clip correctly
For a conventional U-bolt clip, the saddle bears on the live rope and the U-bolt bears on the dead returned end. The live rope is the continuing load-bearing part; the dead end is the returned tail. This orientation distributes bearing appropriately on the live portion.
Do not alternate orientation to “balance” the clamp. Both strands may appear connected, but placing the U-bolt on the live line can damage the principal load-bearing rope. Double-saddle clips use their own installation instructions and should not be described as identical U-bolt products.
- Installation input Source to use
- Clip size Actual rope size and permitted construction
- Minimum number Manufacturer’s table for the product and rope
- Turnback length Manufacturer’s specified eye and tail arrangement
- Spacing Actual product instructions
- Torque Specified value and tightening procedure
- Retightening Manufacturer’s initial-load and subsequent-check instructions
There is no universal table of clip count, torque or exactly six-diameter spacing valid for all sizes and brands. Obtain the exact installation chart for the identified product.
Follow the complete tightening sequence
Manufacturer instructions specify clip placement near the tail and eye, installation of intermediate clips, tightening and any initial-load retorque process. The rope can settle or change diameter as tension develops. Required retightening is part of the approved termination procedure, not an optional step after a production lift.
Apply torque with the correct tool and method where specified. More torque is not necessarily safer; it can damage parts or crush the rope. Lubrication conditions may affect the specified torque and must match the instructions. Do not add an extension handle to compensate for uncertain numbers.
A thimble may be required or appropriate to preserve the eye’s bearing geometry. Its size and fit must suit the rope and connection. An undersized thimble or forced fitting can create local bending even when the clips were installed correctly.
Efficiency is not a sling rating
A termination efficiency describes the fraction of rope breaking strength retained under stated conditions. It is product and rope dependent. Some clip terminations are rated around 80% under their specified assembly conditions, while others have different data. Do not state that every clip arrangement has one exact efficiency.
Even a known efficiency does not establish WLL by itself. The approved equipment design, design factor, rope rating and operating conditions must determine allowable use. A field calculation dividing adjusted breaking strength by an arbitrary number does not authorize a prohibited sling eye.
Installation-data example
Assume an approved application’s manufacturer chart requires three clips, a stated turnback and a stated torque. The crew has only two clips available. Increasing torque on two does not satisfy the chart or create an equivalent termination. Supply the correct parts and complete the prescribed installation before use.
Inspect and preserve the arrangement
Check clips for identification, cracks, deformation, corrosion, damaged threads, missing nuts and correct placement. Inspect the rope for crushing, broken wires and movement at the termination. Marking or inspection methods can help identify slip where specified, but a visual mark does not replace the required assembly procedure.
Do not use damaged clips, substitute nuts or mix parts without manufacturer approval. If the termination has moved or its installation cannot be established, stop use and obtain authorized assessment. Retorquing a damaged or prohibited assembly does not cure the original defect.
The examination approach is two-stage: first decide whether the termination is permitted, then apply its exact installation rules. Remembering the saddle orientation is necessary but incomplete. Correct count, tail, torque, rope compatibility and the governing application all remain part of the decision.
Sources: OSHA construction rigging , CCO compression-hardware topic , Crosby termination manual .