4.3 Weather, Temperature and Ground Conditions
NCCCO Rigger Level II Exam
Track your progress as you read
Finished sections get a check mark.
1 Certification and Exam Preparation
1.1 Current Exam, Eligibility and Scheduling 1.2 Practical Tasks and Examination-Specific Rules 1.3 Study Method, References and Recertification
2 Identify and Measure the Load
2.1 Load Identity, Dimensions and Units 2.2 Load Weight, Density and Complete Inventories 2.3 Composition, Structural Integrity and Special Handling
3 Center of Gravity and Support Geometry
3.1 Center of Gravity and Suspended Stability 3.2 Attachment Points and Complete Force Paths 3.3 Final Position, Landing Supports and Derigging Access
4 Route and Site Hazards
4.1 Travel Path, Clearance and Work-Zone Control 4.2 Power Lines, Clearance Options and Electrical Response 4.3 Weather, Temperature and Ground Conditions
5 Team Duties and Communications
5.1 Signalperson Duties and Reliable Signals 5.2 Equipment Operator Duties and Capacity Decisions 5.3 Lift Director, Qualified Rigger and Hazard Communication
6 Equipment Requirements and Lift Planning
6.1 Determine Equipment Requirements and Compatibility 6.2 Written Plans, Sequence and Change Control 6.3 Critical-Lift Criteria, Risk and Contingencies
7 Balanced Sling Forces
7.1 Two-Leg Tension and Angle Reference 7.2 Length-to-Height Geometry and Headroom 7.3 Horizontal Forces and Attachment Demand
8 Composite and Unequal Loads
8.1 Composite Center of Gravity by Moments 8.2 Off-Center Reactions and Compatible Sling Geometry 8.3 Three- and Four-Leg Assemblies and Load Sharing
9 Wire Rope, Chain and Metal Mesh Slings
9.1 Select and Use Wire-Rope Slings 9.2 Alloy-Chain Assemblies and Approved Adjustment 9.3 Metal-Mesh Slings: Selection, Contact and Removal
10 Synthetic Rope, Web and Roundslings
10.1 Synthetic-Rope Slings and Approved Splices 10.2 Synthetic-Web Slings and Material Compatibility 10.3 Roundslings, Core Protection and Performance Fibers
11 Hitch Application and Sling Protection
11.1 Vertical and Basket Hitch Capacity 11.2 Choker Hitches, Choke Angle and Bundles 11.3 Softeners, Bend Protection and Cut Protection
12 Shackles, Hooks and Collector Hardware
12.1 Shackle Types, Pin Seating and Side Loading 12.2 Hooks, Latches and Permitted Load Seating 12.3 Master Links, Rings and Swivels
13 Threaded Points and Adjustable Hardware
13.1 Eyebolts, Shoulder Seating and Angular Demand 13.2 Swivel Hoist Rings and Installation Torque 13.3 Turnbuckles and Chain Hardware in Adjustable Systems
14 Compression Hardware and Rigging Blocks
14.1 Wire-Rope Clips and Permitted Terminations 14.2 Wedge Sockets, Rope Alignment and Tail Security 14.3 Rigging Blocks, Resultants and Reeving
15 Manual, Lever and Powered Hoists
15.1 Manual Chain Falls and Vertical Hoisting 15.2 Lever Hoists, Pulling Direction and Controlled Adjustment 15.3 Air and Electric Hoists: Supply, Duty and Controls
16 Jacks, Rollers and Portable Supports
16.1 Jacks, Toe Ratings and Positive Support 16.2 Dollies, Skates, Rollers and Horizontal Control 16.3 A-Frames, Gantries and Trolley Compatibility
17 Structural Lifters and Clamps
17.1 Lifting Beams, Spreaders and Configuration Ratings 17.2 Plate Clamps, Material Limits and Grip Conditions 17.3 Beam Clamps as Attachments and Beam/Girder Lifters
18 Mechanical, Vacuum and Magnetic Devices
18.1 Mechanical and Vacuum Lifting Devices 18.2 Close-Proximity and Remotely Operated Lifting Magnets 18.3 Scrap and Material-Handling Grapples
19 Inspection, Removal and Records
19.1 Inspecting All Six Sling Families 19.2 Hook and Rigging-Hardware Inspection 19.3 Below-the-Hook Device Inspection and Testing
20 Lift Control, Rotation and Completion
20.1 Take-Up, Trial Lift and Load Control 20.2 Controlled Rotation, Upending and Multiple-Crane Lifts 20.3 Secure the Load, Remove Rigging and Stow Equipment
21 Technical Standards and Crane Capacity
21.1 Apply the Correct Standard and Regulatory Scope 21.2 Crane Charts, Suspended Weight and Capacity Deductions 21.3 Personnel Hoisting Under OSHA 1926.1431
4.3 Weather, Temperature and Ground Conditions
Key Takeaways Explain This Topic AI
Wind-force sensitivity is approximately quadratic in a simplified fixed-shape model.
Nylon and polyester web slings may not be used above 180°F under the cited OSHA rules.
Fiber-core wire-rope slings exposed above 200°F must be permanently removed.
Bearing-area arithmetic alone does not approve a mat or soil support system.
Last updated: October 2026
Environmental conditions change the demand
A rigging plan must account for weather, visibility, temperature, chemicals and supporting ground. These conditions can change forces, capacity or the ability to control movement. A rated load limit is based on specified conditions; it does not automatically apply to extreme heat, an incompatible chemical or a crane set over an underground void.
Wind affects both the suspended load and lifting equipment. A broad light panel can be difficult to control even when its weight uses little crane capacity. Gusts, projected area, orientation and the manufacturer’s limits all matter. There is no universal safe wind speed of 20 or 30 mph for every load. Use the approved equipment and load-specific limits, then stop when the conditions exceed them or control becomes inadequate.
For the same shape, orientation and aerodynamic coefficient in a simplified model, wind force varies approximately with the square of wind speed . Doubling speed from 10 to 20 units can multiply force by four. This is a relationship useful for understanding sensitivity, not a field design calculation or permission to use a generic coefficient for a delicate panel.
Visibility and precipitation
Fog, glare, darkness and heavy rain can prevent effective signaling or hide a hazard. Ice can affect load surfaces, sling flexibility, walking conditions and footing. Wind-blown dust can impair sight and contaminate moving mechanisms. The relevant question is whether the required observations and controls remain effective, not whether work has traditionally continued in similar weather.
Set weather monitoring and decision responsibility in the plan. If measured conditions differ between ground level and the load’s working elevation, address the controlling exposure. Avoid a universal instruction that one anemometer location proves conditions everywhere. The manufacturer or approved project method determines how the required monitoring is performed.
Temperature limits are material and assembly specific
OSHA 1910.184 and 1926.251 identify several sling-temperature restrictions. Fiber-core wire-rope slings exposed above 200°F must be permanently removed from service. For non-fiber-core wire rope used above 400°F or below −60°F, manufacturer recommendations apply. These requirements are not a general derating table for all steel-core sling assemblies.
For nylon and polyester web slings, OSHA prohibits use above 180°F . Polypropylene web slings have a separate 200°F restriction. A polymer’s melting point is not its permitted sling operating temperature. Damage or strength loss can occur well below melting, and fittings or protective components may introduce additional limits.
Alloy chain exposure also requires the applicable standard and manufacturer’s instructions. Under OSHA 1910.184, chain slings heated above 1,000°F must be permanently removed, and use above 600°F requires manufacturer-recommended capacity reductions. A particular chain grade or assembly may have stricter limits. Do not transfer a temperature chart from one grade, brand or fitting to another.
- Exposure Planning response
- Hot payload Identify actual contact temperature and approved sling/fitting limits
- Very cold service Obtain applicable manufacturer restrictions and approved handling conditions
- Acid or caustic environment Identify substance, concentration, temperature and material compatibility
- Poor visibility Restore effective observation and signaling before movement
- Gusting wind Apply the approved load/equipment limits and stop criteria
- Chemical compatibility is not a color choice
OSHA prohibits nylon web slings where acids or phenolics are present. Polyester and polypropylene web slings cannot be used where caustics are present, and aluminum fittings have their own caustic restriction. A broad claim that polyester is “acid resistant” is insufficient to authorize a particular exposure. Consult the manufacturer for the actual substance and conditions.
Unknown exposure is a reason to remove affected gear from use pending evaluation. Discoloration, stiffness, embrittlement or burns may indicate damage, but absence of visible change does not prove chemical safety. Do not try to restore capacity with an improvised rinse, coating or field heat treatment.
Ground support is a system
For construction cranes, OSHA 1926.1402 addresses ground conditions and responsibilities, including the controlling entity’s preparation duties and information about known underground hazards. The operator and responsible personnel must establish suitable support for the actual configuration. A mat spreads load only to the extent that it has adequate rigidity, effective contact and supported bearing area.
A simplified area calculation divides a supplied support reaction by an approved allowable bearing pressure. If reaction is 80,000 lb and the given pressure is 2,000 lb/ft², the theoretical area is 40 ft². That calculation does not prove a 40-ft² timber panel works. Mat bending, soil layers, slope, voids and effective contact still require evaluation. Do not round a required dimension downward or invent a generic soil capacity from appearance.
Stop condition
During a trial lift, one support settles unexpectedly. Stop safely and return the load to a controlled supported condition. The movement may signal soil failure, a void or inadequate distribution. Continuing because the crane display remains below capacity ignores the support condition that makes its rating valid.
Sources: OSHA 1910.184 , 1926.251 , ground conditions .