13.2 Quality Control, Material Test Reports (MTRs), Weld Mapping & Traceability
NCCER Boilermaker Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The Assessment, Boilermaker Craft, Safety, Tools & Crew Leadership
1.1 The NCCER Boilermaker Assessments: Format, Content Domains, Scoring & Credentials 1.2 Craft Fundamentals, Professional Roles & Industrial Safety 1.3 Confined Space Entry, Lockout/Tagout (LOTO) & Atmospheric Testing 1.4 Hand, Pneumatic, Electric & Hydraulic Boilermaker Tools 1.5 Crew Leadership, Job Planning, Production Tracking & Jobsite Communication
2 Chapter 2: Metallurgy, Base Materials, Oxyfuel, Air Carbon Arc & Plasma Cutting
2.1 Industrial Boiler Materials, Carbon & Alloy Steels, ASME Material Specs & Markings 2.2 Base Metal Surface Preparation, Joint Beveling & Fit-Up Cleanliness 2.3 Oxyfuel Cutting Principles, Equipment Setup, Torch Angles & Piercing Techniques 2.4 Air Carbon Arc Cutting and Gouging (CAC-A): Electrodes, Current, Air Supply, Technique & Defects 2.5 Plasma Arc Cutting (PAC): Torch Anatomy, Consumables, Gas Selection, Cut Quality & Safety
3 Chapter 3: Boiler Types, Steam Generation, Feedwater & Combustion Systems
3.1 Firetube Boiler Designs, Circulation Patterns & Operating Principles 3.2 Watertube Boiler Configurations, Natural & Forced Circulation, Drum Internals 3.3 Superheaters, Reheaters, Economizers & Air Heaters 3.4 Feedwater Systems, Deaerators, Condensate Return & Boiler Water Treatment 3.5 Combustion Systems: Burners, Stokers, Pulverizers, Fans & Draft Control
4 Chapter 4: Boiler Pressure & Nonpressure Components
4.1 Steam Drums, Mud Drums, Headers & Waterwalls 4.2 Nonpressure Components: Casing, Breeching, Baffles, Buckstays & Expansion Joints 4.3 Boiler Auxiliaries: Soot Blowers, Safety Valves, Gage Glasses & Blowdown Systems
5 Chapter 5: Valves, Gaskets, Fasteners, Anchors & Pipe Support Systems
5.1 Industrial Valve Types, Markings, Operation & Ratings 5.2 Gasket Materials, Flange Facings, Bolt Torque Sequences & Joint Assembly 5.3 Gasket Layout, Cutting & Fitting for Field-Made Gaskets 5.4 Fasteners, Anchors & Threaded Connection Hardware 5.5 Pipe Hangers, Supports, Rigid Restraints & Spring Can Installation/Adjustment
6 Chapter 6: Blueprint Reading, Welding Symbols & Construction Drawings
6.1 AWS Welding Symbols, Joint Geometry, Contours & NDE Designators 6.2 Piping Schematics, P&IDs, Isometric Drawings & Spool Sheets 6.3 Pressure Vessel General Arrangement, Detail Sheets, Coordinates & Elevations
7 Chapter 7: Trade Mathematics & Pipe Layout Calculations
7.1 Boilermaker Mechanical Trade Math: Offsets, Rolling Offsets & Travel Calculations 7.2 Vessel Volume, Surface Area, Circumference & Head Layout Computations 7.3 Mitered Turns, Segment Layout, Cutbacks & Branch Connections
8 Chapter 8: Pipe Fabrication - Socket Weld, Butt Weld, Threaded, Grooved & Spool Work
8.1 Pipe Materials, Nominal Pipe Size, Wall Schedules & Fitting Standards 8.2 Socket Weld Pipe Fabrication: The 1/16 in. Gap, Fillet Sizing & Cut Lengths 8.3 Butt Weld Pipe Fabrication: End Preparation, Alignment, Fit-Up & Cut Lengths 8.4 Pipe Layout Tools, Wrap-Arounds, Flange Squaring & Fabrication Tolerances 8.5 Threaded and Grooved Pipe Joining Systems 8.6 Spool Fabrication Workflow, Shop Versus Field Welds & Advanced Pipe Fabrication
9 Chapter 9: Tube Fabrication, Bending & Rolling
9.1 Boiler Tube Removal, Inspection, Wall Thinning & Replacement Criteria 9.2 Tube Preparation, Bending Radii, Ovality & Alignment Tolerances 9.3 Tube Expanding Mechanics, Rolling Torque Calculations, Wall Reduction & Flaring/Beading
10 Chapter 10: Welding Processes, Preheat & Stress Relieving
10.1 SMAW, GTAW & FCAW Welding Processes in Pressure Vessel Applications 10.2 Electrode Selection, Storage, Baking & AWS Filler Metal Classifications 10.3 Preheating Standards, Interpass Temperature Control & Post-Weld Heat Treatment (PWHT)
11 Chapter 11: Rigging Equipment, Hardware & Crane Operations
11.1 Rigging Hardware: Slings, Shackles, Eye Bolts & Inspection Criteria 11.2 Rigging Math: Sling Angles, Tension Calculations & Center of Gravity 11.3 Crane Signals, Load Charts, Boom Angle Deratings & Critical Lift Planning
12 Chapter 12: Towers, Heat Exchangers & Refractory/BRIL Systems
12.1 Shell-and-Tube Heat Exchangers: Bundles, Baffles & Floating Heads 12.2 Fractionation Towers, Trays, Downcomers, Packing & Vessel Hardware 12.3 Refractory Materials (Brick, Castable, Ceramic Fiber), Anchoring & Lagging (BRIL)
13 Chapter 13: ASME Codes, Quality Assurance, NDE, Pressure Testing & System Cleaning
13.1 ASME Boiler & Pressure Vessel Code (Sections I, VIII, IX) & NBIC Standards 13.2 Quality Control, Material Test Reports (MTRs), Weld Mapping & Traceability 13.3 Nondestructive Examination (NDE): VT, PT, MT, UT, RT & Discontinuity Evaluation 13.4 Hydrostatic and Pneumatic Testing Procedures, Safety Precautions & MAWP Validation 13.5 System Flushing, Chemical Cleaning, Boil-Out, Steam Blows & Service Leak Testing
13.2 Quality Control, Material Test Reports (MTRs), Weld Mapping & Traceability
Key Takeaways Explain This Topic AI
An ASME-accredited Quality Control (QC) System requires a formal QC Manual defining organizational authority, documented travelers/router sheets, and designated hold points where work cannot proceed without Authorized Inspector (AI) or QC sign-off.
Mill Test Reports (MTRs / CMTRs) verify the chemical composition and mechanical properties (yield, tensile, elongation, and Charpy V-notch impact toughness) of pressure-retaining materials, keyed to unique heat numbers.
Positive material identification and physical heat number traceability must be preserved throughout cutting and fabrication using low-stress dot-matrix, round-nose vibro-etching, or paint stenciling to prevent localized stress risers.
Weld mapping logs track joint locations, assigned Weld Procedure Specifications (WPS), welder identification stencils, and filler metal lot/heat numbers, while Non-Conformance Reports (NCRs) formally document deviations and corrective dispositions.
Last updated: August 2026
12.2 Quality Control, Material Test Reports (MTRs), Weld Mapping & Traceability
Core Trade Concept: Quality Control (QC) in boilermaking is the systematic process of ensuring that every piece of plate, pipe, forging, filler metal, and welded joint meets rigid engineering and Code specifications. A failure in material identification or welding documentation can result in catastrophic in-service ruptures. Boilermakers must understand Quality Control Systems , Certified Mill Test Reports (CMTRs) , low-stress material marking , weld mapping , and Non-Conformance Reporting (NCR) .
1. Quality Control System & Traveler Sheets
An ASME Certificate Holder must establish and maintain a documented Quality Control (QC) Manual that outlines organizational responsibilities, fabrication procedures, and examination protocols. QC SYSTEM ORGANIZATIONAL HIERARCHY
- +-----------------------+
- | Company Executive |
- | Management |
- +-----------------------+
- |
- +------------------+------------------+
- | |
- v v
- +---------------------+ +---------------------+
- | Production / Shop | | Quality Control |
- | Supervision | | Manager |
- +---------------------+ +---------------------+
- | |
- | v
- | +---------------------+
- | | QC Inspectors / |
- | | NDE Examiners |
- | +---------------------+
- | |
- +==================+==================+
- |
- v
- +-----------------------+
- | Authorized Inspector |
- | (AI / AIA) |
- +-----------------------+
- Key Principles of the QC System
Organizational Independence: The Quality Control department must operate with authority independent of production pressures. QC inspectors must have the direct authority to stop work, reject non-conforming materials, and enforce hold points.
Travelers / Process Router Sheets: The traveler (or route sheet) is the master tracking document that travels with a component through each stage of fabrication, welding, inspection, and testing. TYPICAL FABRICATION TRAVELER ENTRY
- +-----+-------------------------------+-------------+----------+-----------+
- | Op | Operation Description | QC Sign/Date| AI Sign | Hold/Wit. |
- +-----+-------------------------------+-------------+----------+-----------+
- | 10 | Material Verification & CMTR | JS 08/12/26 | -- | Review |
- | 20 | Cut & Bevel Shell Plates | JS 08/13/26 | -- | QC Point |
- | 30 | Fit-up & Root Gap Inspection | JS 08/14/26 | -- | QC Point |
- | 40 | Long. Seam Root Pass Weld | JS 08/14/26 | -- | In-Process|
- | 50 | 100% Radiographic Examination | TR 08/16/26 | AI 08/17 | Review |
- | 60 | Post-Weld Heat Treat (PWHT) | JS 08/18/26 | AI 08/19 | Hold Point|
- | 70 | Final Hydrostatic Test (900#) | JS 08/20/26 | AI 08/20 | HOLD POINT|
- +-----+-------------------------------+-------------+----------+-----------+
- Inspection Checkpoint Classifications
Hold Point: A critical mandatory milestone on the traveler. Fabrication CANNOT proceed past a Hold Point until the designated QC inspector or Authorized Inspector has physically inspected the work, verified compliance, and signed/dated the traveler.
Witness Point: A scheduled inspection milestone where the AI or owner's inspector is notified in advance. If the inspector is not present at the appointed time, fabrication may proceed only if prior written agreement exists.
Review Point: A documentary checkpoint where the inspector reviews examination records, radiographic films, heat treatment charts, or CMTRs prior to final equipment release.
2. Certified Mill Test Reports (CMTRs) & Metallurgical Properties
A Certified Material Test Report (CMTR) , or Mill Test Report (MTR) , is a certified legal document issued by the steel mill verifying that a specific batch of metal meets all chemical and mechanical requirements of the referenced ASME Section II material specification. CERTIFIED MILL TEST REPORT BREAKDOWN
- +-----------------------------------------------------------------------------+
- | TITAN STEEL MILLS CORP. CERTIFIED MATERIAL TEST REPORT |
- | Material: ASME SA-516 Grade 70 (PVQ Plate) Heat Number: H-847291 |
- | Dimensions: 1.500" x 96.0" x 240.0" Slab Number: SL-4402 |
- +-----------------------------------------------------------------------------+
- | CHEMICAL COMPOSITION (Weight %) |
- | C Mn P S Si Cr Mo Ni V CE (IIW) |
- | 0.22 1.15 0.012 0.004 0.28 0.04 0.02 0.03 0.005 0.43% |
- +-----------------------------------------------------------------------------+
- | MECHANICAL PROPERTIES |
- | Yield Strength (0.2% offset) : 48,500 psi (Spec Min: 38,000 psi) |
- | Tensile Strength : 76,200 psi (Spec: 70,000 - 90,000 psi) |
- | Elongation in 2" : 27.0 % (Spec Min: 21.0 %) |
- | Charpy V-Notch (-20°F Avg) : 34 ft-lbs (Spec Min: 20 ft-lbs) |
- +-----------------------------------------------------------------------------+
- Critical Elements on an MTR
Material Specification & Grade: Must explicitly match the ASME Section II designation (e.g., SA-516 Gr 70, SA-335 Gr P91, SA-106 Gr B).
Heat Number: A unique tracking number assigned to a specific batch of molten steel in the mill's furnace ladle. Every plate or pipe rolled from that ladle shares this heat number.
Chemical Composition: Details weight percentages of alloying elements:
Carbon ( C C C ): Primary strengthening element; higher carbon increases hardness and tensile strength but reduces ductility and weldability.
Manganese ( M n Mn M n ): Increases strength and toughness; scavenges sulfur.
Phosphorus ( P P P ) & Sulfur ( S S S ): Harmful impurities that cause hot-shortness, lamellar tearing, and embrittlement. ASME specifications set strict maximum thresholds (e.g., P ≤ 0.025 % P \le 0.025\% P ≤ 0.025% , S ≤ 0.015 % S \le 0.015\% S ≤ 0.015% ).
Chromium ( C r Cr C r ) & Molybdenum ( M o Mo M o ): Enhance high-temperature creep strength, oxidation resistance, and corrosion resistance.
Carbon Equivalent (CE) & Weldability
The Carbon Equivalent (CE) formula evaluates the combined hardenability of steel and its susceptibility to Hydrogen-Induced Cracking (HIC) in the Heat-Affected Zone (HAZ): C E = % C + % M n + % S i 6 + % C r + % M o + % V 5 + % N i + % C u 15 CE = \%C + \frac{\%Mn + \%Si}{6} + \frac{\%Cr + \%Mo + \%V}{5} + \frac{\%Ni + \%Cu}{15} CE = % C + 6 % M n + % S i + 5 % C r + % M o + % V + 15 % N i + % C u Engineering Rule: C E > 0.40 % requires elevated preheat; C E > 0.45 % requires strict preheat and low-hydrogen filler metals. \text{Engineering Rule: } CE > 0.40\% \text{ requires elevated preheat; } CE > 0.45\% \text{ requires strict preheat and low-hydrogen filler metals. } Engineering Rule: CE > 0.40% requires elevated preheat; CE > 0.45% requires strict preheat and low-hydrogen filler metals.
Mechanical Properties
Yield Strength ( S y S_y S y ): The stress level at which the steel permanently deforms plastically.
Tensile Strength ( S u S_u S u ): The maximum engineering stress the material can sustain before necking and fracture.
Elongation (% in 2 inches): Measures ductility—the ability of the steel to deform plastically without tearing.
Charpy V-Notch (CVN) Impact Energy: Measures notch toughness (absorbed energy in ft-lbs \text{ft-lbs} ft-lbs or Joules) at a designated test temperature (e.g., − 20 ∘ F -20^\circ\text{F} − 2 0 ∘ F or − 50 ∘ F -50^\circ\text{F} − 5 0 ∘ F ). High CVN values confirm the steel will not suffer catastrophic brittle fracture under low operating temperatures or high impact shock.
3. Material Traceability & Physical Marking Requirements
Positive Material Identification (PMI) and complete heat number traceability must be maintained from raw warehouse stock through completed boiler commissioning. HEAT NUMBER TRANSFER BEFORE CUTTING
- Raw Steel Plate (Heat H-847291) Cut Sections (Traceability Preserved)
- +-------------------------------+ +---------------+ +---------------+
- | [H-847291] | | [H-847291] | | [H-847291] |
- | SA-516 Gr 70 | =====> | SA-516 Gr 70 | | SA-516 Gr 70 |
- | | Cut Line | (Transferred) | | (Transferred) |
- +-------------------------------+ +---------------+ +---------------+
- Heat Number Transfer Rules
Mandatory Code Rule: Before cutting, burning, or shearing any pressure vessel plate or pipe, the original mill heat number, specification, and grade must be transferred to all cutoff sections using an approved marking method. If traceability is lost, the material is deemed non-conforming and cannot be used in pressure boundary fabrication.
Approved Marking Techniques vs. Prohibited Sharp Stamps APPROVED VS. PROHIBITED MARKING TOOLS
- PROHIBITED ON PRESSURE BOUNDARY APPROVED LOW-STRESS MARKING
- Sharp "V-Notch" Die Stamp Dot-Matrix / Radiused Die Stamp
| | : :
| | : :
- \ / ( )
- \ _ / \ _ /
- (Creates Sharp Notch; (Blunt Spherical Indentation;
- Initiates Fatigue Cracks) Prevents Stress Risers)
Prohibited Sharp "V-Notch" Die Stamps: Conventional sharp-bottom steel stamps create deep, microscopic V-shaped notches in the metal surface. Under cyclic pressure loading and thermal fatigue, these notches act as severe stress concentrations (stress risers) that initiate rapid crack propagation.
Approved Low-Stress Stamping:
Low-Stress Dot-Matrix Stamps: Form characters from rounded micro-dots.
Round-Nose (Radiused) Die Stamps: Character edges have a minimum radius of 0.010 in. 0.010\text{ in.} 0.010 in. ( 0.25 mm 0.25\text{ mm} 0.25 mm ) to produce smooth, spherical indentations without sharp root notches.
Vibro-Etching / Electrochemical Etching: High-frequency reciprocating carbide styluses or chemical etching that produce shallow, non-stress-concentrating markings.
Paint Stenciling: High-visibility, chloride-free, low-sulfur industrial paint markers (mandatory on austenitic stainless steels and high-nickel alloys).
- 4. Weld Mapping, Welder Identification & Filler Metal Control
- Weld Mapping Architecture
A weld map is a detailed fabrication drawing or isometric schematic that assigns a unique, sequential identification number to every pressure boundary weld on a vessel or piping system. BOILER DRUM WELD MAP SCHEMATIC
- W-01 (Circ Seam) W-03 (Circ Seam)
- | |
- +---------v-------+--------------------+-------v---------+
- | HEAD 1 | SHELL COURSE | HEAD 2 |
- | | | |
- | | W-02 (Long Seam)| |
- | +====================+ |
- +---------+-------+----------+---------+-------+---------+
- | | |
- W-04 (Nozzle) W-05 (Manway) W-06 (Nozzle)
- The Weld Tracking Record (Weld Log)
Each weld number on the weld map links directly to a row in the master Weld Record Log :
Weld ID Joint Type Base Metals (P-No) Thickness Assigned WPS Welder Symbol Filler Lot # Visual (VT) NDE Method / Result
W-01 Circumferential Butt P1 to P1 (SA-516-70) 2.500 in. 2.500\text{ in.} 2.500 in. WPS-101 B-44 (Smith) Lot 9482 PASS (08/14) 100% RT / ACCEPT
W-02 Longitudinal Butt P1 to P1 (SA-516-70) 2.500 in. 2.500\text{ in.} 2.500 in. WPS-101 B-12 (Jones) Lot 9482 PASS (08/14) 100% RT / ACCEPT
W-04 Set-in Nozzle P1 to P1 (SA-106-B) 1.250 in. 1.250\text{ in.} 1.250 in. WPS-104 B-44 (Smith) Lot 8812 PASS (08/15) 100% UT / ACCEPT
Welder Identification Stenciling
Under ASME Section I (PW-28) and Section VIII (UW-29), each certified welder is assigned a unique identifying number, letter, or symbol.
Upon completing a joint, the welder must stamp or stencil their assigned ID within 1 to 2 inches 1\text{ to }2\text{ inches} 1 to 2 inches of the weld bead on the base plate using low-stress stamps.
If physical stamping is prohibited (e.g., thin-wall titanium or stainless tubing), the weld map traveler serves as the legal record of welder identification.
Filler Metal Control Protocols FILLER METAL STORAGE & ISSUE CYCLE
- +--------------------+ +--------------------+ +--------------------+
- | Sealed Mill Cans | | Holding Oven | | Heated Quivers |
- | Hermetically sealed| ===> | 250°F - 350°F | ===> | 150°F - 250°F |
- | dry warehouse | | Continuous bake | | 4-Hour Field Limit |
- +--------------------+ +--------------------+ +--------------------+
Low-Hydrogen SMAW Electrodes (E7018, E8018, E9018): Moisture absorption in electrode flux coatings releases atomic hydrogen into the molten weld puddle, causing delayed hydrogen underbead cracking. Electrodes must be stored in holding ovens maintained between 250 ∘ F and 350 ∘ F 250^\circ\text{F}\text{ and }350^\circ\text{F} 25 0 ∘ F and 35 0 ∘ F immediately after opening hermetically sealed cans.
4-Hour Field Exposure Rule: Once issued to boilermakers in portable heated rod quivers, low-hydrogen electrodes must be consumed within 4 hours (or returned to holding/rebaking ovens per manufacturer instructions).
5. Non-Conformance Reports (NCR) & Dispositioning
A Non-Conformance Report (NCR) is a formal quality document used to record, evaluate, and correct any condition in material, fabrication, or documentation that fails to meet drawings, technical specifications, or ASME Code requirements. NCR WORKFLOW & DISPOSITIONING
- +-------------------------------------------------------------+
- | 1. IDENTIFICATION |
- | Deviation detected (e.g., crack, mismatch, wrong filler). |
- | NCR issued; red 'HOLD' tag applied; part quarantined. |
- +-------------------------------------------------------------+
- |
- v
- +-------------------------------------------------------------+
- | 2. TECHNICAL EVALUATION & DISPOSITIONING |
- | QC, Engineering & AI evaluate severity and assign action: |
- | |
- | • REWORK : Bring into original drawing compliance. |
- | • REPAIR : Make acceptable using engineered procedure. |
- | • ACCEPT-AS-IS: Engineering calculation verifies safety. |
- | • SCRAP : Unsalvageable; destroy and discard. |
- +-------------------------------------------------------------+
- |
- v
- +-------------------------------------------------------------+
- | 3. ROOT CAUSE CORRECTIVE ACTION (RCCA) |
- | Perform 5-Why analysis, retrain welders, close NCR. |
- +-------------------------------------------------------------+
- The Four Standard Dispositions
Rework: Making the non-conforming item conform to original drawing and specification requirements using standard manufacturing procedures (e.g., adding weld metal to an undersized fillet weld leg, or re-machining a flange face to correct surface finish).
Repair: Making the item acceptable for its intended purpose, even though the final repaired condition does not conform to original blueprints. Requires an engineered repair procedure and concurrence from the Authorized Inspector (e.g., gouging out a deep crack, buttering the cavity, and applying a qualified temper-bead weld procedure).
Accept-As-Is (Use-As-Is): Leaving the non-conforming condition uncorrected after engineering evaluation and stress calculations prove that design margins, MAWP, and Code criteria are fully satisfied (requires formal engineering review and AI approval).
Scrap: The non-conformance cannot be safely repaired or used. The item is painted with red scrap markers, physically removed from the fabrication line, and quarantined to prevent inadvertent installation.