Formwork Loads, Shoring, Reshoring & Stripping
NCCER Carpenter Commercial Carpenter
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
About the NCCER Carpenter Assessment How to Use This Study Guide NCCER Registry, Credentials & Apprenticeship Path Exam Logistics, Calculator Rules & Study Strategy
2 Construction Safety for Carpenters
Construction Site Safety Orientation Fall Protection, Ladders & Scaffolds PPE, Hand/Power Tool & Nailer Safety Material Handling & Jobsite Housekeeping
3 Building Materials, Fasteners & Tools
Lumber Grades & Engineered Wood Products Fasteners, Anchors & Adhesives Carpenter Hand Tools Portable Power Tools
4 Floor Systems
Floor System Components & Layout Joists, Beams, Girders & Bridging Subfloor Installation & Engineered Floor Systems
5 Wall Systems & Building Envelope
Wall Framing Components & Layout Openings, Headers, Cripples & Bracing Wall Assembly, Plumb/Square & Sheathing Building Envelope, Moisture Control & Insulation Basics
6 Construction Drawings, Measurement & Site Layout
Plans, Elevations, Sections & Details Specifications, Codes, Symbols & Abbreviations Site Layout, Batter Boards & the 3-4-5 Method Leveling Instruments & Building Layout Construction Math, Scale Conversions & Material Takeoffs
7 Stair Systems
Stair Types & Components Rise, Run, Headroom & Code Requirements Stringers, Finished Stairs & Commercial Stair Systems
8 Roofing Applications & Systems
Roof Types, Underlayment & Thermal/Moisture Protection Residential Shingle Installation Sequence Commercial Roofing, Flashing & Ventilation Roof Framing Basics (Pitch, Common Rafters & Trusses)
9 Cold-Formed Steel Framing
CFS Materials, Gauges & Components Installing CFS Walls, Loadbearing vs Nonbearing
10 Drywall Installation & Finishing
Gypsum Board Types & Fastening Methods Installing Drywall on Walls & Ceilings Finishing Levels & Fire/Sound-Rated Assemblies
11 Interior Finish: Doors, Trim, Cabinets & Ceilings
Doors & Door Hardware Window, Door, Floor & Ceiling Trim Cabinet & Countertop Installation Suspended & Acoustical Ceilings Commercial Door Frames, Fire-Rated Assemblies & Hardware Sets
12 Exterior Finish & Trim
Exterior Siding Materials & Installation Flashing, House Wrap & Weather Barriers Exterior Trim, Soffit & Fascia
13 Rigging for Carpenters
Rigging Equipment, Hardware & Inspection Sling Angles, Hitches & Load Control Crane Awareness & Lift Planning for Carpenters
14 Concrete Properties, Reinforcement & Placement
Concrete Properties, Mixes & Curing Reinforcing Steel Selection & Placement Handling, Placing, Finishing & Joints
15 Foundations & Formwork
Foundations & Slab-on-Grade Forms Vertical & Horizontal Formwork Systems Tilt-Up Wall Construction Overview Formwork Loads, Shoring, Reshoring & Stripping
Formwork Loads, Shoring, Reshoring & Stripping
Key Takeaways Explain This Topic AI
Normal-weight concrete weighs about 150 pounds per cubic foot, so a 6-inch elevated slab alone imposes roughly 75 pounds per square foot of dead load.
ACI 347 sets a minimum construction live load of 50 psf (75 psf with motorized carts) and a minimum total design load of 100 psf (125 psf with carts).
OSHA 29 CFR 1926.703 requires formwork to be designed, fabricated, erected, supported, braced, and maintained to carry all vertical and lateral loads.
Reshores are installed after original shores are removed and the slab has deflected under its own weight; backshores never allow the slab to carry its full load.
Forms and shores come out only when the concrete reaches the strength the engineer or specification requires — never on a calendar guess.
Last updated: August 2026
Formwork Loads, Shoring, Reshoring & Stripping
Quick Answer: Formwork carries dead load (concrete at about 150 pcf plus the forms themselves) and construction live load (workers, tools, buggies). ACI 347 sets minimums of 50 psf live load — 75 psf with motorized carts — and a 100 psf total design load ( 125 psf with carts). OSHA 1926.703 requires formwork to be designed and maintained for all vertical and lateral loads. Shores support fresh concrete; reshores are re-installed after the slab has taken its own weight; backshores never let the slab deflect fully. Strip only when the specified strength is verified — never on a calendar.
Foundations and Formwork is a 10-item domain, and formwork collapse is one of the highest-consequence failures in commercial construction. The previous section covered the components of vertical and horizontal systems. This section covers the loads and the sequence — the reasoning that decides whether those components are adequate and when they can safely come out.
Where formwork loads come from
- Load Source Typical magnitude
- Concrete dead load Plastic concrete in the form About 150 pcf normal weight ( 145 pcf plain, plus reinforcing)
- Formwork dead load Sheathing, joists, stringers, shores Often assumed around 5-15 psf
- Construction live load Crew, tools, hoses, stored material 50 psf minimum (ACI 347)
- Motorized cart allowance Power buggies on the deck 75 psf minimum live load
Lateral concrete pressure Fluid head on vertical forms Rises with pour height , rate of placement , cooler temperatures
Lateral wind/impact Wind on formwork, equipment strikes Per design and jurisdiction
Slab dead-load example. How much dead load does a 6-inch normal-weight elevated slab put on the deck forms?
- Thickness in feet: 6 / 12 = 0.5 ft
- Dead load: 0.5 x 150 = 75 psf from the concrete alone
Add formwork self-weight and the 50 psf minimum live load and the deck is designing to roughly 130-140 psf — comfortably above the 100 psf ACI minimum, which is exactly why the minimum is a floor , not a target.
ACI 347 minimums to remember:
- Construction live load : not less than 50 psf
- With motorized carts : not less than 75 psf
- Total design load (dead + live): not less than 100 psf
- Total design load with motorized carts : not less than 125 psf
- Lateral pressure on vertical forms
Fresh concrete behaves like a heavy fluid until it stiffens. Lateral pressure against wall and column forms increases when:
- The rate of placement is faster (concrete stays plastic deeper into the pour)
- The pour height is greater
- Temperatures are cooler (slower set keeps concrete fluid longer)
- Superplasticizers or high-slump mixes delay stiffening
- Vibration is applied deeper than the current lift
It decreases with warmer temperatures, slower placement, and mixes that stiffen quickly. The practical control is the rate of placement specified in the form design — pouring faster than the forms were designed for is a leading cause of blowouts, and it is a decision made by the crew, not the engineer.
Never compute a pressure from memory on the job. ACI 347 publishes formulas with limits of applicability; the form design drawing states the assumed rate and temperature. Your responsibility is to place within those assumptions and to stop if conditions change.
Shoring, reshoring, and backshoring
These three terms are frequently confused and are a reliable source of exam items.
Term Definition Load state of the slab
Shores Original vertical supports carrying the fresh pour and its forms Slab carries nothing ; shores carry everything
Reshores Supports placed after forms and original shores are removed Slab has already deflected and carries its own dead load
Backshores Original shores removed and replaced one at a time Slab is never allowed to deflect fully or carry full load
The distinction matters structurally. A reshore is installed snug but not preloaded, so the slab below it is not asked to carry the new slab's dead load — the reshore only picks up subsequent construction loads. A backshore keeps the slab supported continuously, which is used when a young slab must not be allowed to take its own weight.
Multi-story load path. When a new deck is poured, its weight travels down through shores into the slab below, then through reshores into the slabs below that, until enough levels share the load that no single young slab is overstressed. The number of levels of shoring and reshoring is an engineering decision shown on the shoring drawings. Removing a level early because it is in the way of a delivery is how a progressive collapse starts.
What OSHA requires — 29 CFR 1926 Subpart Q
Subpart Q covers concrete and masonry construction; 1926.703 addresses formwork specifically.
Formwork must be designed, fabricated, erected, supported, braced, and maintained to support all vertical and lateral loads that may reasonably be anticipated.
Drawings or plans for the jack layout, formwork, shoring, working decks, and scaffolds must be available at the jobsite.
Shoring equipment must be inspected before, during, and immediately after the pour; damaged or weakened equipment is removed from service .
Reshoring must be erected as the original forms and shores are removed, and must be capable of supporting the loads imposed.
Forms and shores may not be removed until the employer determines the concrete has gained sufficient strength to support its own weight and superimposed loads — that determination is based on compliance with the design drawings/specifications or on tests (field-cured cylinders or in-place testing) showing the concrete has reached the required strength.
Single-post shores in more than one tier must be designed, spliced to prevent misalignment, and laterally braced.
Vertical slip forms , lift-slab operations, and precast erection carry their own specific requirements.
Stripping: criteria before sequence
The criterion is strength, not time. "We always strip at three days" is not an acceptable answer on an assessment or in an incident investigation. Acceptable bases include:
The specification or engineer's stated stripping strength or time, when the design provides one.
Field-cured test cylinders broken to confirm the required compressive strength — field-cured, because they experience the same conditions as the structure, unlike standard lab-cured cylinders used for acceptance.
In-place methods such as maturity or pullout testing where specified and calibrated.
Cold weather, poor curing, low cement content, or admixture problems all delay strength gain. The concrete does not know what the schedule promised.
Stripping sequence
Order Element Reasoning
1 Non-loadbearing vertical forms — wall and column sides These forms only resisted lateral pressure; the element supports itself
2 Beam sides Same logic — sides carry no gravity load
3 Slab soffits and beam bottoms These carry gravity load; strip only at verified strength, with reshoring plan in place
4 Shores under long spans and cantilevers Highest deflection sensitivity; strip last and reshore per drawings
Cantilevers are the classic trap. A cantilevered slab or balcony has no backspan support once the shores are gone, and its critical stress is at the support, not midspan. Cantilever shores stay in longer and are removed strictly per the engineer's direction.
Additional stripping discipline:
Do not drop or pry recklessly — damaged panels become tomorrow's failure, and falling forms are a struck-by hazard.
Apply release agent properly on the previous cycle so panels come away cleanly instead of tearing the concrete face.
Protect green concrete edges and corners; arrises chip easily at early ages.
Keep exclusion zones below any stripping operation.
Clean, inspect, and repair panels, ties, and shores before the next cycle; bent shores and elongated tie holes are rejected, not reused.
Failure modes carpenters control
Failure Root cause Control
Wall form blowout Placement rate exceeded design assumption Pour to the specified rate; monitor ties and walers
- Deck collapse Shores removed early or reshores omitted Verify strength; follow shoring drawings
- Shore punch-through Inadequate mudsill or soft subgrade Sound bearing, proper sills, level base
- Progressive collapse Too few shored/reshored levels Engineering decision; never field-modified
- Tie failure Wrong tie capacity or damaged hardware Match tie to design; inspect and reject damaged hardware
Formwork is temporary structure that carries permanent-structure loads at the moment the permanent structure is weakest. That is why the Foundations and Formwork domain rewards candidates who can explain why a shore stays in — not just what it is called.