15.4 Soil Classification Systems (USCS & AASHTO) and Soil Effects on Equipment
NCCER Heavy Equipment Operations Certification Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: NCCER Credentials, Trade Orientation, Safety & Equipment Classification
1.1 NCCER Heavy Equipment Operations Credentials, Curriculum & Assessments 1.2 Heavy Equipment Industry & Operator Responsibilities 1.3 OSHA & MSHA Regulatory Standards (29 CFR 1926 & 30 CFR) 1.4 Machine Safety Systems: ROPS, FOPS, Seatbelts & Interlocks 1.5 Classifying Heavy Equipment: Machine Families, Mining Machines, Drive Systems & Hydraulics
2 Chapter 2: Pre-Operation Inspection & Preventative Maintenance
2.1 Walk-Around Inspection Procedures & Daily Checklists 2.2 Fluid Levels, Hydraulic Inspection & Filter Maintenance 2.3 Undercarriage, Tires, Tracks & Ground Engaging Tools (GET) 2.4 Engine Systems, Startup & Warm-Up, and Hybrid and Electric Equipment Readiness
3 Chapter 3: Safe Operating Practices & Site Hazards
3.1 Mounting, Dismounting (Three-Point Contact) & Cab Safety 3.2 Electrical Power Line Clearances & Overhead Hazards 3.3 Blind Spots, Swing Radii, Spotters & Hand Signals
4 Chapter 4: Refueling, Parking, Shutdown & Equipment Transport
4.1 Engine Cooldown, Safe Parking & Lockout/Tagout Procedures 4.2 Fueling Safety, Fire Prevention & Environmental Controls 4.3 Heavy Equipment Transport, Rigging & Securement / Tie-Down
5 Chapter 5: Excavator Types, Components & Hydraulics
5.1 Excavator Classifications, Tracked vs. Wheeled Configurations 5.2 House, Boom, Stick, Bucket & Hydraulic Flow Systems 5.3 Quick-Couplers, Attachments & Operational Safety
6 Chapter 6: Excavator Operations, Trenching & Lifting
6.1 Excavator Positioning, Travel & Stable Working Platforms 6.2 Trenching Techniques, Bench Cutting & Production Digging 6.3 Lifting Operations, Rigging Capacities & Load Charts
7 Chapter 7: Backhoe Loader Components & Controls
7.1 Backhoe Loader Anatomy: Loader End vs. Backhoe End 7.2 Operator Station, Pilot vs. Wobble Stick Controls & Instruments 7.3 Stabilizer Deployment, Machine Levelling & Setup on Slopes
8 Chapter 8: Backhoe Loader Operational Techniques
8.1 Backhoe Digging, Spoiling, Truck Loading & Cycle Efficiency 8.2 Front-End Loader Operations with Backhoe Loaders 8.3 Backhoe Road Travel, Transport Safety & Boom Locking
9 Chapter 9: Bulldozer Types, Powertrains & Blade Configurations
9.1 Crawler Dozer Classifications, Undercarriages & Ground Pressure 9.2 Drivetrains: Torque Converters, Powershift & Hydrostatic Drives 9.3 Blade Types: Straight (S), Universal (U), Semi-Universal (SU) & Angle Blades
10 Chapter 10: Bulldozer Earthmoving Operations
10.1 Straight Dozing, Slot Dozing & Production Pushing 10.2 Push-Loading Scrapers & Multi-Machine Earthmoving 10.3 Stockpiling, Berm Construction & Material Spreading
11 Chapter 11: Dozer Slope Work, Ripping & Clearing
11.1 Sidehill Operations, Working Up and Down Steep Slopes 11.2 Ripper Attachments: Single Shank, Multi-Shank & Ripping Techniques 11.3 Site Clearing, Tree Felling & Stumping Precautions
12 Chapter 12: Wheel Loaders & Track Loaders
12.1 Wheel Loader Anatomy, Articulated Steering & Z-Bar Linkage 12.2 Loading Patterns: V-Pattern, I-Pattern & Truck Placement 12.3 Excavation, Stockpile Management & Carry Operations
13 Chapter 13: Motor Grader Anatomy & Blade Geometry
13.1 Motor Grader Components: Tandem Drive, Articulation & Front Wheel Lean 13.2 Moldboard Mechanics: Pitch, Angle, Lift & Side-Shift 13.3 Grader Safety, Operating Speeds & Reversing Precautions
14 Chapter 14: Motor Grader Operations & Finish Grading
14.1 Ditching, Backsloping & Windrowing Techniques 14.2 Roadway Crown, Cross-Slope & Superelevation Creation 14.3 Fine Grading Tolerances, Blue Tops & Final Trimming
15 Chapter 15: Earthmoving Principles, Excavation Math, Soils & Planning
15.1 Soil Mechanics: Bank, Loose & Compacted Cubic Yards 15.2 Swell, Shrinkage & Load Factor Calculations 15.3 Slope Ratios, Percent Grade & Elevation Calculations 15.4 Soil Classification Systems (USCS & AASHTO) and Soil Effects on Equipment 15.5 Earthmoving Planning & Soil Stabilization Methods
16 Chapter 16: Civil Drawings, Staking, Layout, Pipe Laying & Machine Control
16.1 Reading Civil Engineering Site Plans, Contours & Profiles 16.2 Construction Stakes: Stationing, Offset, Cut & Fill Stakes 16.3 Laser Levels, GNSS/GPS Machine Control & 3D Telematics 16.4 Foundation Layout & Pipe Laying
17 Chapter 17: Soil Compaction Equipment & Methods
17.1 Principles of Soil Compaction & Optimum Moisture Content (Proctor Test) 17.2 Roller Types: Smooth Drum, Padfoot / Sheepsfoot, Pneumatic & Tamping 17.3 Lift Thickness, Pass Overlap & In-Place Density Testing
18 Chapter 18: OSHA 1926 Subpart P: Soil Classification & Cave-In Protection
18.1 OSHA Soil Mechanics: Type A, Type B & Type C Classification 18.2 Cave-In Protection Systems: Sloping, Benching, Shoring & Shielding 18.3 Duties of the OSHA Competent Person & Daily Trench Inspections
19 Chapter 19: Excavation Site Hazards & Underground Utilities
19.1 Utility Locating (811 Call Before You Dig) & Potholing Procedures 19.2 Safe Access, Egress (Ladders/Ramps) & Hazardous Atmospheres 19.3 Surface Water Diversion, Dewatering & Backfilling Requirements
20 Chapter 20: Specialized Equipment: Compact Loaders, Forklifts, Haulers & Tractors
20.1 Skid-Steer Loaders & Compact Track Loaders (CTLs): Controls & Stability 20.2 Rough-Terrain Forklifts & Telehandlers: Stability Triangle & Load Charts 20.3 Scrapers, Off-Road Articulated Dump Trucks & Utility Tractors 20.4 Dump Trucks: On-Road and Off-Road Operation 20.5 Utility Tractors: ROPS, Overturn Prevention, Ballast & Implement Hookup 20.6 Conventional (Sit-Down Counterbalanced) Forklifts
15.4 Soil Classification Systems (USCS & AASHTO) and Soil Effects on Equipment
Key Takeaways Explain This Topic AI
Engineering plans and soil reports classify soils by the Unified Soil Classification System (USCS) or AASHTO groups, which are separate from OSHA's Type A, B, and C excavation categories.
Gravel is retained on the No. 4 sieve, sand passes the No. 4 but is retained on the No. 200, and silt and clay (fines) pass the No. 200 sieve.
In the USCS, a soil is fine-grained when 50 percent or more passes the No. 200 sieve; a liquid limit of 50 separates low-plasticity (L) from high-plasticity (H) silts and clays.
AASHTO calls soils granular (A-1 to A-3) when 35 percent or less passes the No. 200 sieve and silt-clay (A-4 to A-7) when more than 35 percent passes.
Soil type changes traction and rolling resistance: Caterpillar lists tire traction of 0.55 on dry clay loam but 0.20 on dry sand, and rolling resistance from about 1.5 percent to 20 percent.
Last updated: October 2026
- Soil Classification Systems (USCS & AASHTO) and Soil Effects on Equipment
- Why Operators Need Classification Vocabulary
Plans, specifications, and geotechnical reports describe soils with standard group names. A specification might say "subgrade is A-6 clay; undercut 2 feet and replace with A-1-a material" or "no CH, OH, or PT soils in embankment fill." An operator who understands these labels knows which material is acceptable, which must be hauled to waste, and how each will behave under the machine.
These engineering systems are different from OSHA's Type A, B, and C soil classes in Subpart P (Chapter 18). OSHA's system decides how an excavation must be protected. The USCS and AASHTO systems describe what the soil is made of and how well it will perform as fill or subgrade.
Grain Sizes and Sieves
Soil particles are sorted by passing a sample through a stack of standard sieves:
- Particle group Size limits
- Boulders Larger than 12 inches
- Cobbles 3 to 12 inches
- Gravel Passes the 3-inch sieve, retained on the No. 4 sieve (4.75 mm)
- Sand Passes the No. 4, retained on the No. 200 sieve (0.075 mm)
- Fines (silt and clay) Pass the No. 200 sieve
Silt and clay particles are too small to separate by sieve, so they are told apart by how they behave with water.
Atterberg Limits
Liquid limit (LL): the water content at which a soil changes from a plastic state to a liquid state.
Plastic limit (PL): the water content at which soil just crumbles when rolled into a 1/8-inch thread.
Plasticity index (PI): the range of water content over which the soil is plastic. P I = L L − P L PI = LL - PL P I = LL − P L
A soil with LL = 45 and PL = 20 has PI = 25, which means a sticky clay that swells when wet and shrinks and cracks when dry. Silts have little or no plasticity.
The Unified Soil Classification System (ASTM D2487)
USCS group symbols use two letters. The first names the main soil type: G gravel, S sand, M silt, C clay, O organic, and PT peat. The second describes gradation or plasticity: W well graded, P poorly graded, L low plasticity, and H high plasticity.
- Major division Rule Group symbols
- Coarse-grained soils More than 50% retained on the No. 200 sieve —
- Gravels More than half of the coarse fraction retained on the No. 4 GW, GP, GM, GC
- Sands Half or more of the coarse fraction passes the No. 4 SW, SP, SM, SC
- Fine-grained soils, LL less than 50 50% or more passes the No. 200 ML, CL, OL
- Fine-grained soils, LL 50 or more 50% or more passes the No. 200 MH, CH, OH
- Highly organic soils Mostly organic matter, dark, fibrous PT
Clean coarse soils with less than 5 percent fines get a gradation letter (GW, SP). Coarse soils with more than 12 percent fines get a fines letter (GM, SC). Soils between 5 and 12 percent fines receive dual symbols such as SP-SM.
To separate clays from silts, engineers plot LL and PI on the plasticity chart. Soils above the A-line , where P I = 0.73 ( L L − 20 ) PI = 0.73\,(LL - 20) P I = 0.73 ( LL − 20 ) , are clays; soils below it are silts or organic soils.
The AASHTO System (AASHTO M 145)
Highway agencies usually classify soil with AASHTO groups, which rate soils as road subgrade:
- Group Fines passing No. 200 Typical material General subgrade rating
- A-1 (A-1-a, A-1-b) 35% or less Well-graded gravel and sand Excellent to good
- A-3 35% or less Fine sand with few fines Excellent to good
- A-2 (A-2-4 to A-2-7) 35% or less Silty or clayey gravel and sand Excellent to good
- A-4 More than 35% Silty soil, LL 40 or less, PI 10 or less Fair to poor
- A-5 More than 35% Elastic silt, LL 41 or more, PI 10 or less Fair to poor
- A-6 More than 35% Clayey soil, LL 40 or less, PI 11 or more Fair to poor
- A-7 (A-7-5, A-7-6) More than 35% Plastic clay, LL 41 or more, PI 11 or more Fair to poor
A group index in parentheses, such as A-6 (12), refines the rating; the higher the number, the poorer the subgrade.
- How Soil Type Affects Equipment
- Traction
Usable pull equals the coefficient of traction times the weight on the drivers. The Caterpillar Performance Handbook lists:
- Surface Rubber tires Tracks
- Clay loam, dry 0.55 0.90
- Clay loam, wet 0.45 0.70
- Rutted clay loam 0.40 0.70
- Dry sand 0.20 0.30
- Wet sand 0.40 0.50
- Quarry pit 0.65 0.55
- Loose gravel road 0.36 0.50
- Packed snow 0.20 0.27
- Rolling Resistance
Rolling resistance is the force needed to keep wheels rolling on a surface, expressed as a percentage of gross machine weight. Caterpillar's table for bias-ply tires ranges from 1.5 percent on a very hard, smooth road to 4 percent on a rutted dirt road with about 1 inch of tire penetration, 8 percent with 4 inches of penetration, 10 percent in loose sand or gravel, and 20 percent on a very soft, muddy road with about 12 inches of penetration. A 100,000-pound loaded truck on an 8 percent road needs about 8,000 pounds of rimpull just to keep rolling, four times the 2,000 pounds needed on a maintained 2 percent road.
Practical Behavior by Soil Group
Clean gravels and sands (GW, GP, SW, SP; A-1, A-3): drain quickly and compact well with vibration. Dry loose sand gives tires poor traction.
Silts (ML, MH; A-4, A-5): dusty when dry and can turn soft or "quick" when wet and vibrated. Their compaction is very sensitive to moisture.
Clays (CL, CH; A-6, A-7): strong and hard when dry but sticky when wet. Wet clay builds up in buckets and on tracks and causes ruts. Padfoot rollers compact them best.
Organic soils and peat (OL, OH, PT): compressible and unsuitable for structural fill. They are usually removed and replaced.