15.2 Swell, Shrinkage & Load Factor Calculations
NCCER Heavy Equipment Operations Certification Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: NCCER Credentials, Trade Orientation, Safety & Equipment Classification
1.1 NCCER Heavy Equipment Operations Credentials, Curriculum & Assessments 1.2 Heavy Equipment Industry & Operator Responsibilities 1.3 OSHA & MSHA Regulatory Standards (29 CFR 1926 & 30 CFR) 1.4 Machine Safety Systems: ROPS, FOPS, Seatbelts & Interlocks 1.5 Classifying Heavy Equipment: Machine Families, Mining Machines, Drive Systems & Hydraulics
2 Chapter 2: Pre-Operation Inspection & Preventative Maintenance
2.1 Walk-Around Inspection Procedures & Daily Checklists 2.2 Fluid Levels, Hydraulic Inspection & Filter Maintenance 2.3 Undercarriage, Tires, Tracks & Ground Engaging Tools (GET) 2.4 Engine Systems, Startup & Warm-Up, and Hybrid and Electric Equipment Readiness
3 Chapter 3: Safe Operating Practices & Site Hazards
3.1 Mounting, Dismounting (Three-Point Contact) & Cab Safety 3.2 Electrical Power Line Clearances & Overhead Hazards 3.3 Blind Spots, Swing Radii, Spotters & Hand Signals
4 Chapter 4: Refueling, Parking, Shutdown & Equipment Transport
4.1 Engine Cooldown, Safe Parking & Lockout/Tagout Procedures 4.2 Fueling Safety, Fire Prevention & Environmental Controls 4.3 Heavy Equipment Transport, Rigging & Securement / Tie-Down
5 Chapter 5: Excavator Types, Components & Hydraulics
5.1 Excavator Classifications, Tracked vs. Wheeled Configurations 5.2 House, Boom, Stick, Bucket & Hydraulic Flow Systems 5.3 Quick-Couplers, Attachments & Operational Safety
6 Chapter 6: Excavator Operations, Trenching & Lifting
6.1 Excavator Positioning, Travel & Stable Working Platforms 6.2 Trenching Techniques, Bench Cutting & Production Digging 6.3 Lifting Operations, Rigging Capacities & Load Charts
7 Chapter 7: Backhoe Loader Components & Controls
7.1 Backhoe Loader Anatomy: Loader End vs. Backhoe End 7.2 Operator Station, Pilot vs. Wobble Stick Controls & Instruments 7.3 Stabilizer Deployment, Machine Levelling & Setup on Slopes
8 Chapter 8: Backhoe Loader Operational Techniques
8.1 Backhoe Digging, Spoiling, Truck Loading & Cycle Efficiency 8.2 Front-End Loader Operations with Backhoe Loaders 8.3 Backhoe Road Travel, Transport Safety & Boom Locking
9 Chapter 9: Bulldozer Types, Powertrains & Blade Configurations
9.1 Crawler Dozer Classifications, Undercarriages & Ground Pressure 9.2 Drivetrains: Torque Converters, Powershift & Hydrostatic Drives 9.3 Blade Types: Straight (S), Universal (U), Semi-Universal (SU) & Angle Blades
10 Chapter 10: Bulldozer Earthmoving Operations
10.1 Straight Dozing, Slot Dozing & Production Pushing 10.2 Push-Loading Scrapers & Multi-Machine Earthmoving 10.3 Stockpiling, Berm Construction & Material Spreading
11 Chapter 11: Dozer Slope Work, Ripping & Clearing
11.1 Sidehill Operations, Working Up and Down Steep Slopes 11.2 Ripper Attachments: Single Shank, Multi-Shank & Ripping Techniques 11.3 Site Clearing, Tree Felling & Stumping Precautions
12 Chapter 12: Wheel Loaders & Track Loaders
12.1 Wheel Loader Anatomy, Articulated Steering & Z-Bar Linkage 12.2 Loading Patterns: V-Pattern, I-Pattern & Truck Placement 12.3 Excavation, Stockpile Management & Carry Operations
13 Chapter 13: Motor Grader Anatomy & Blade Geometry
13.1 Motor Grader Components: Tandem Drive, Articulation & Front Wheel Lean 13.2 Moldboard Mechanics: Pitch, Angle, Lift & Side-Shift 13.3 Grader Safety, Operating Speeds & Reversing Precautions
14 Chapter 14: Motor Grader Operations & Finish Grading
14.1 Ditching, Backsloping & Windrowing Techniques 14.2 Roadway Crown, Cross-Slope & Superelevation Creation 14.3 Fine Grading Tolerances, Blue Tops & Final Trimming
15 Chapter 15: Earthmoving Principles, Excavation Math, Soils & Planning
15.1 Soil Mechanics: Bank, Loose & Compacted Cubic Yards 15.2 Swell, Shrinkage & Load Factor Calculations 15.3 Slope Ratios, Percent Grade & Elevation Calculations 15.4 Soil Classification Systems (USCS & AASHTO) and Soil Effects on Equipment 15.5 Earthmoving Planning & Soil Stabilization Methods
16 Chapter 16: Civil Drawings, Staking, Layout, Pipe Laying & Machine Control
16.1 Reading Civil Engineering Site Plans, Contours & Profiles 16.2 Construction Stakes: Stationing, Offset, Cut & Fill Stakes 16.3 Laser Levels, GNSS/GPS Machine Control & 3D Telematics 16.4 Foundation Layout & Pipe Laying
17 Chapter 17: Soil Compaction Equipment & Methods
17.1 Principles of Soil Compaction & Optimum Moisture Content (Proctor Test) 17.2 Roller Types: Smooth Drum, Padfoot / Sheepsfoot, Pneumatic & Tamping 17.3 Lift Thickness, Pass Overlap & In-Place Density Testing
18 Chapter 18: OSHA 1926 Subpart P: Soil Classification & Cave-In Protection
18.1 OSHA Soil Mechanics: Type A, Type B & Type C Classification 18.2 Cave-In Protection Systems: Sloping, Benching, Shoring & Shielding 18.3 Duties of the OSHA Competent Person & Daily Trench Inspections
19 Chapter 19: Excavation Site Hazards & Underground Utilities
19.1 Utility Locating (811 Call Before You Dig) & Potholing Procedures 19.2 Safe Access, Egress (Ladders/Ramps) & Hazardous Atmospheres 19.3 Surface Water Diversion, Dewatering & Backfilling Requirements
20 Chapter 20: Specialized Equipment: Compact Loaders, Forklifts, Haulers & Tractors
20.1 Skid-Steer Loaders & Compact Track Loaders (CTLs): Controls & Stability 20.2 Rough-Terrain Forklifts & Telehandlers: Stability Triangle & Load Charts 20.3 Scrapers, Off-Road Articulated Dump Trucks & Utility Tractors 20.4 Dump Trucks: On-Road and Off-Road Operation 20.5 Utility Tractors: ROPS, Overturn Prevention, Ballast & Implement Hookup 20.6 Conventional (Sit-Down Counterbalanced) Forklifts
15.2 Swell, Shrinkage & Load Factor Calculations
Key Takeaways Explain This Topic AI
Swell percentage quantifies the volumetric expansion occurring when consolidated bank soil is excavated, calculated as ((Bank Density / Loose Density) - 1) × 100.
The Load Factor (LF) is the mathematical reciprocal of the swell multiplier (LF = Loose Density / Bank Density), directly converting loose truck payloads into bank volume (BCY = LCY × LF).
Shrinkage percentage measures the volume reduction when bank earth is placed and rolled into engineered fill, requiring earthwork planners to excavate more bank material than the final compacted fill volume (BCY = CCY / (1 - Shrinkage)).
Haul truck fleet dispatching requires evaluating both volumetric body capacity (struck vs. heaped LCY) and legal gravimetric payload ratings to determine whether haul units are volume-limited or weight-limited.
Last updated: October 2026
- Swell, Shrinkage & Load Factor Calculations
- Mathematical Mechanics of Soil Swell and Swell Percentage
When heavy equipment excavates native earth from its consolidated in-situ cut, the material expands in volume. In earthmoving engineering, this phenomenon is quantified as the Swell Percentage (often denoted as % Swell \% \text{Swell} % Swell ). Swell represents the percentage increase in volume that occurs when soil transitions from its undisturbed bank state (BCY) to its disturbed loose state (LCY).
Swell percentage can be calculated either from physical volumetric measurements or from laboratory unit weight (density) testing:
Volumetric Swell Formula : % Swell = ( Loose Volume (LCY) − Bank Volume (BCY) Bank Volume (BCY) ) × 100 \% \text{Swell} = \left(\frac{\text{Loose Volume (LCY)} - \text{Bank Volume (BCY)}}{\text{Bank Volume (BCY)}}\right) \times 100 % Swell = ( Bank Volume (BCY) Loose Volume (LCY) − Bank Volume (BCY) ) × 100
Density-Based Swell Formula :
Because total solid mass remains constant while volume expands, density decreases proportionally. Swell is calculated from unit weights as: % Swell = ( Bank Density Loose Density − 1 ) × 100 \% \text{Swell} = \left(\frac{\text{Bank Density}}{\text{Loose Density}} - 1\right) \times 100 % Swell = ( Loose Density Bank Density − 1 ) × 100
Once the swell percentage is established, calculating the loose volume produced by an in-place excavation cut is straightforward: Loose Volume (LCY) = Bank Volume (BCY) × ( 1 + % Swell 100 ) \text{Loose Volume (LCY)} = \text{Bank Volume (BCY)} \times \left(1 + \frac{\% \text{Swell}}{100}\right) Loose Volume (LCY) = Bank Volume (BCY) × ( 1 + 100 % Swell )
For example, if an excavator removes 10,000 BCY of dense plastic clay exhibiting a 35% swell factor, the loose volume requiring hauling is: LCY = 10,000 BCY × ( 1 + 0.35 ) = 13,500 LCY \text{LCY} = 10{,}000\text{ BCY} \times (1 + 0.35) = 13{,}500\text{ LCY} LCY = 10 , 000 BCY × ( 1 + 0.35 ) = 13 , 500 LCY
Different soil classifications exhibit vastly different swell characteristics. Uniform cohesionless sands swell only 10% to 15% because rounded sand grains quickly re-settle into loose packing. Highly plastic cohesive clays swell 30% to 45% because sticky clay platelets adhere irregularly, trapping large air pockets. Solid rock blasted from an intact ledge swells between 50% and 75% because jagged, irregular rock fragments cannot pack tightly without mechanical crushing.
The Load Factor: Converting Loose Volume to Bank Measure
While estimators plan cut quantities in Bank Cubic Yards, operators on the grade measure production by counting haul truck loads or weighing haul units on axle scales. Because haul trucks carry loose material, contractors require a direct mathematical coefficient to convert loose measurements back into bank volume for billing and progress tracking. This multiplier is the Load Factor (LF) .
The Load Factor is defined as the ratio of loose density to bank density, which is also the exact mathematical reciprocal of the swell multiplier: L F = Loose Density Bank Density = 1 1 + % Swell / 100 LF = \frac{\text{Loose Density}}{\text{Bank Density}} = \frac{1}{1 + \% \text{Swell}/100} L F = Bank Density Loose Density = 1 + % Swell /100 1
By multiplying loose volume (LCY) by the Load Factor, the equivalent bank volume (BCY) is immediately determined: BCY = LCY × L F \text{BCY} = \text{LCY} \times LF BCY = LCY × L F
Consider an earthmoving operation where a fleet of articulated dump trucks hauls 450 loads of common earth in a shift. Each truck carries a heaped payload of 20 LCY, yielding a total hauled volume of 450 × 20 = 9,000 LCY 450 \times 20 = 9{,}000\text{ LCY} 450 × 20 = 9 , 000 LCY . Geotechnical testing shows the common earth has a bank density of 2,800 lb/BCY and a loose density of 2,240 lb/LCY.
To determine how many Bank Cubic Yards were excavated from the cut:
Calculate the Load Factor: L F = 2,240 lb/LCY 2,800 lb/BCY = 0.80 LF = \frac{2{,}240\text{ lb/LCY}}{2{,}800\text{ lb/BCY}} = 0.80 L F = 2 , 800 lb/BCY 2 , 240 lb/LCY = 0.80
Convert loose volume to bank volume: BCY = 9,000 LCY × 0.80 = 7,200 BCY \text{BCY} = 9{,}000\text{ LCY} \times 0.80 = 7{,}200\text{ BCY} BCY = 9 , 000 LCY × 0.80 = 7 , 200 BCY
The Load Factor is always a decimal less than 1.0 (except in rare expansive mineral conditions), reflecting the fact that one loose cubic yard contains less solid mineral mass than one undisturbed bank cubic yard.
Soil Shrinkage and Compaction Factor Calculations
When excavated soil is transported to an embankment, spread in thin horizontal lifts, and compacted by vibratory smooth-drum or padfoot rollers, mechanical energy expels air voids. The soil particles are forced into a tight, dense configuration, resulting in a volume that is generally smaller than the original undisturbed bank cut. This volumetric contraction is known as Shrinkage .
Shrinkage Percentage ( % Shrinkage \% \text{Shrinkage} % Shrinkage ) quantifies the percentage reduction from the original in-situ bank volume to the final compacted fill volume:
Volumetric Shrinkage Formula : % Shrinkage = ( Bank Volume (BCY) − Compacted Volume (CCY) Bank Volume (BCY) ) × 100 \% \text{Shrinkage} = \left(\frac{\text{Bank Volume (BCY)} - \text{Compacted Volume (CCY)}}{\text{Bank Volume (BCY)}}\right) \times 100 % Shrinkage = ( Bank Volume (BCY) Bank Volume (BCY) − Compacted Volume (CCY) ) × 100
Density-Based Shrinkage Formula : % Shrinkage = ( 1 − Bank Density Compacted Density ) × 100 \% \text{Shrinkage} = \left(1 - \frac{\text{Bank Density}}{\text{Compacted Density}}\right) \times 100 % Shrinkage = ( 1 − Compacted Density Bank Density ) × 100
The decimal equivalent of shrinkage is the Shrinkage Factor ( S F = % Shrinkage / 100 SF = \% \text{Shrinkage} / 100 SF = % Shrinkage /100 ). The reciprocal relationship connecting bank and compacted volumes is expressed through the Compaction Factor ( C F CF CF ): Compaction Factor = 1 − S F = Compacted Density (Bank) Compacted Density (Fill) = CCY BCY \text{Compaction Factor} = 1 - SF = \frac{\text{Compacted Density (Bank)}}{\text{Compacted Density (Fill)}} = \frac{\text{CCY}}{\text{BCY}} Compaction Factor = 1 − SF = Compacted Density (Fill) Compacted Density (Bank) = BCY CCY CCY = BCY × ( 1 − S F ) \text{CCY} = \text{BCY} \times (1 - SF) CCY = BCY × ( 1 − SF )
Determining Required Borrow Pit Excavation
A critical calculation in site grading and highway construction involves determining how many Bank Cubic Yards must be excavated from an off-site borrow pit to construct an engineered embankment of specified CCY dimensions. Because the soil shrinks during compaction, excavating only the embankment volume would result in a severe material shortfall.
To calculate the required borrow cut volume, divide the required compacted fill volume by the quantity ( 1 − S F ) (1 - SF) ( 1 − SF ) : Required BCY = Required CCY 1 − S F = Required CCY Compaction Factor \text{Required BCY} = \frac{\text{Required CCY}}{1 - SF} = \frac{\text{Required CCY}}{\text{Compaction Factor}} Required BCY = 1 − SF Required CCY = Compaction Factor Required CCY
For example, if a highway overpass embankment requires 50,000 CCY of compacted clay fill, and geotechnical testing indicates a 15% shrinkage factor ( S F = 0.15 SF = 0.15 SF = 0.15 ): Required BCY = 50,000 CCY 1 − 0.15 = 50,000 0.85 = 58,824 BCY \text{Required BCY} = \frac{50{,}000\text{ CCY}}{1 - 0.15} = \frac{50{,}000}{0.85} = 58{,}824\text{ BCY} Required BCY = 1 − 0.15 50 , 000 CCY = 0.85 50 , 000 = 58 , 824 BCY The contractor must excavate 58,824 BCY from the borrow source to produce 50,000 CCY of completed, compacted embankment.
Technical Comparison: Typical Swell and Shrinkage Percentages by Soil Type
Earthwork engineers and machine operators utilize standard reference ranges to estimate volumetric changes when specific geotechnical laboratory Proctor tests are pending:
Soil Classification Swell Range (%) Typical Swell (%) Typical Load Factor (LF) Shrinkage Range (%) Typical Shrinkage (%) Net Compaction Factor (CCY/BCY)
- Clean Sand & Gravel 10% to 18% 15% 0.870 8% to 15% 12% 0.880
- Common Earth (Loam & Silt) 20% to 30% 25% 0.800 12% to 20% 16% 0.840
- Dense Plastic Clay 28% to 42% 35% 0.741 18% to 26% 22% 0.780
- Decomposed Rock / Soft Shale 35% to 50% 40% 0.714 0% to 8% 5% 0.950
Blasted Hard Rock (Granite / Basalt) 50% to 75% 60% 0.625 Net Swell (-15% to -30%) -20% (Net Swell) 1.200 (Net Gain)
Haul Fleet Logistics: Volume-Limited vs. Weight-Limited Truck Payload Calculations
A central operational responsibility in earthmoving logistics is pass matching and truck fleet payload balancing. Every haul truck—whether a highway dump truck, an articulated dump truck (ADT), or a rigid-frame quarry hauler—operates under two distinct engineering limits:
Volumetric Capacity : Defined by the physical dimensions of the truck body. Truck bodies carry two volumetric ratings established by SAE/ISO standards:
Struck Capacity : The water-level volume of the truck body when struck completely flat along the top edge of the sideboards.
Heaped Capacity : The maximum volume of material the body can hold when crowned above the sideboards at a standardized 2:1 slope angle (2 units horizontal to 1 unit vertical).
Gravimetric (Weight) Capacity : The maximum allowable net payload weight, determined by the truck's Gross Vehicle Weight Rating (GVWR), structural frame integrity, suspension limits, tire load ratings, and public highway bridge laws.
Determining the Limiting Haul Factor
To prevent dangerous vehicle overloading or inefficient partial hauling, the fleet supervisor must calculate whether the fleet is volume-limited ("volumed out") or weight-limited ("weighed out"): Potential Payload Weight = Heaped Body Capacity (LCY) × Material Loose Density (lb/LCY) \text{Potential Payload Weight} = \text{Heaped Body Capacity (LCY)} \times \text{Material Loose Density (lb/LCY)} Potential Payload Weight = Heaped Body Capacity (LCY) × Material Loose Density (lb/LCY)
If Potential Payload Weight > Truck Rated Weight Capacity \text{Potential Payload Weight} > \text{Truck Rated Weight Capacity} Potential Payload Weight > Truck Rated Weight Capacity , the machine is weight-limited . The truck cannot be filled to its heaped volumetric capacity without exceeding structural or legal weight ratings. Operators must load only to the weight limit.
If Potential Payload Weight ≤ Truck Rated Weight Capacity \text{Potential Payload Weight} \le \text{Truck Rated Weight Capacity} Potential Payload Weight ≤ Truck Rated Weight Capacity , the machine is volume-limited . The truck can be safely loaded to full heaped capacity without exceeding gross weight limits.
Total Haul Cycles Formula
Once usable capacity per truck is established, the total number of truck loads required to complete a project is calculated: Required Truck Loads = Total Project Loose Volume (LCY) Usable Capacity per Load (LCY) \text{Required Truck Loads} = \frac{\text{Total Project Loose Volume (LCY)}}{\text{Usable Capacity per Load (LCY)}} Required Truck Loads = Usable Capacity per Load (LCY) Total Project Loose Volume (LCY) Always round fractional loads up to the next whole number.
- Worked Engineering Examples: Step-by-Step Earthwork Calculations
- Example 1: Calculating Swell and Load Factor from Field Densities
A cut section in a highway project contains native glacial till. Nuclear gauge testing determines that the in-situ bank density is 3,120 lb/BCY. When excavated into a loose stockpile, the material exhibits a loose density of 2,400 lb/LCY.
Calculate Swell Percentage: % Swell = ( 3,120 lb/BCY 2,400 lb/LCY − 1 ) × 100 = ( 1.30 − 1 ) × 100 = 30.0 % \% \text{Swell} = \left(\frac{3{,}120\text{ lb/BCY}}{2{,}400\text{ lb/LCY}} - 1\right) \times 100 = (1.30 - 1) \times 100 = 30.0\% % Swell = ( 2 , 400 lb/LCY 3 , 120 lb/BCY − 1 ) × 100 = ( 1.30 − 1 ) × 100 = 30.0%
Calculate Load Factor: L F = 2,400 lb/LCY 3,120 lb/BCY = 0.769 LF = \frac{2{,}400\text{ lb/LCY}}{3{,}120\text{ lb/BCY}} = 0.769 L F = 3 , 120 lb/BCY 2 , 400 lb/LCY = 0.769
Example 2: Determining Borrow Pit Excavation for a Highway Embankment
A civil contractor must construct a highway bridge approach embankment requiring 72,000 Compacted Cubic Yards (CCY) of compacted cohesive fill. Geotechnical tests indicate a shrinkage factor of 18% ( S F = 0.18 SF = 0.18 SF = 0.18 ) from the designated borrow pit.
Calculate Required Borrow Bank Volume (BCY): Required BCY = Required CCY 1 − S F = 72,000 CCY 1 − 0.18 = 72,000 0.82 = 87,805 BCY \text{Required BCY} = \frac{\text{Required CCY}}{1 - SF} = \frac{72{,}000\text{ CCY}}{1 - 0.18} = \frac{72{,}000}{0.82} = 87{,}805\text{ BCY} Required BCY = 1 − SF Required CCY = 1 − 0.18 72 , 000 CCY = 0.82 72 , 000 = 87 , 805 BCY
Calculate Material to Haul (Assuming 28% Swell in Borrow Cut): Loose Volume (LCY) = 87,805 BCY × 1.28 = 112,390 LCY \text{Loose Volume (LCY)} = 87{,}805\text{ BCY} \times 1.28 = 112{,}390\text{ LCY} Loose Volume (LCY) = 87 , 805 BCY × 1.28 = 112 , 390 LCY
Example 3: Truck Fleet Cycle Sizing for a Major Cut-to-Waste Project
An excavation cut requires removing 24,000 BCY of dense clay (bank density: 3,000 lb/BCY; swell: 25%; loose density: 2,400 lb/LCY). The contractor deploys articulated dump trucks with a heaped capacity of 20 LCY and a maximum manufacturer payload rating of 46,000 lb (23 tons).
Check Weight Limitation: Heaped Load Weight = 20 LCY × 2,400 lb/LCY = 48,000 lb \text{Heaped Load Weight} = 20\text{ LCY} \times 2{,}400\text{ lb/LCY} = 48{,}000\text{ lb} Heaped Load Weight = 20 LCY × 2 , 400 lb/LCY = 48 , 000 lb Because 48,000 lb exceeds the 46,000 lb rated payload, the truck is weight-limited !
Determine Maximum Usable Volume per Truck: Usable Volume = 46,000 lb 2,400 lb/LCY = 19.17 LCY per load \text{Usable Volume} = \frac{46{,}000\text{ lb}}{2{,}400\text{ lb/LCY}} = 19.17\text{ LCY per load} Usable Volume = 2 , 400 lb/LCY 46 , 000 lb = 19.17 LCY per load
Calculate Total Loose Volume to Move: Total LCY = 24,000 BCY × 1.25 = 30,000 LCY \text{Total LCY} = 24{,}000\text{ BCY} \times 1.25 = 30{,}000\text{ LCY} Total LCY = 24 , 000 BCY × 1.25 = 30 , 000 LCY
Calculate Required Truck Loads: Loads = 30,000 LCY × 2,400 lb/LCY 46,000 lb/load = 1,565.2 → 1,566 truck loads \text{Loads} = \frac{30{,}000\text{ LCY} \times 2{,}400\text{ lb/LCY}}{46{,}000\text{ lb/load}} = 1{,}565.2 \to 1{,}566\text{ truck loads} Loads = 46 , 000 lb/load 30 , 000 LCY × 2 , 400 lb/LCY = 1 , 565.2 → 1 , 566 truck loads (Dividing by the rounded 19.17 LCY per load gives 1,564.9, which would wrongly round to 1,565; carry full precision so the final round-up is not missed.)