2.2 Hazardous Energy Control: Lockout/Tagout and Confined Space Entry

NCCER Industrial Maintenance Mechanic Exam

Track your progress as you read

Finished sections get a check mark.

1 The NCCER Industrial Maintenance Mechanic Assessment

1.1 The IMM Journey-Level Credential and Assessment Specification 1.2 The Nine Content Domains: Item Counts and a Study Plan

2 Industrial Maintenance Mechanic Fundamentals

2.1 Safety Programs, PPE, and Hazard Communication 2.2 Hazardous Energy Control: Lockout/Tagout and Confined Space Entry 2.3 Tools of the Trade: Hand and Power Tools 2.4 Oxyfuel Cutting: Equipment, Safe Setup, and Cutting Practice 2.5 Ferrous Metal Piping Practices: Cutting, Threading, and Joining

3 Rigging and Mobile Equipment

3.1 Slings, Rigging Hardware, and Inspection Criteria 3.2 Load Weight, Center of Gravity, Sling Angle, and Hand Signals 3.3 Mobile and Support Equipment: Forklifts, Aerial Lifts, and Mobile Cranes

4 Craft Mathematics, Layout, and Precision Measurement

4.1 Craft-Related Mathematics: Fractions, Units, Area, and Volume 4.2 Advanced Trade Math: Right Triangles, Trigonometry, and Pipe Offsets 4.3 Basic Layout: Squaring, Leveling, and Transferring Elevations 4.4 Precision Measuring Tools: Micrometers, Verniers, and Dial Indicators 4.5 Gauges, Tolerances and Fits, and Torque Measurement

5 Construction Drawings and Blueprint Reading

5.1 Reading Construction Drawings: Views, Lines, Scales, and the Title Block 5.2 Orthographic, Isometric, Arrangement, and Foundation Drawings 5.3 Advanced Blueprint Reading: P&IDs, Instrument Tags, and Welding Symbols

6 Valves, Packing, and Mechanical Seals

6.1 Valve Types and Service Selection 6.2 Valve Construction, Markings, Pressure Classes, and Actuators 6.3 Removing and Installing Valves: Flange Bolting and Torque Sequence 6.4 Valve Maintenance: Packing, Stuffing Boxes, Gaskets, and O-Rings 6.5 Hydrostatic and Pneumatic Testing of Piping and Equipment 6.6 Mechanical Seals: Components, Types, and Installation

7 Bearings, Lubrication, and Couplings

7.1 Bearing Types, Designations, and Selection 7.2 Bearing Lubrication, Handling, and Failure Analysis 7.3 Removing and Installing Bearings: Fits, Heating, and Mounting 7.4 Couplings: Types, Selection, and Installation

8 Pumps, Baseplates, and Mechanical Drives

8.1 Pumps and Drivers: Centrifugal and Positive Displacement 8.2 Setting Baseplates and Soleplates: Leveling, Anchoring, and Grouting 8.3 Prealignment: Soft Foot, Runout, Pipe Strain, and Shims 8.4 Installing Belt and Chain Drives

9 Shaft Alignment: Conventional, Reverse, and Laser

9.1 Conventional Rim-and-Face Dial Indicator Alignment 9.2 Reverse Dial Indicator Alignment 9.3 Laser Shaft Alignment Systems

10 Maintenance Troubleshooting: Method, Pumps, and Gearboxes

10.1 Systematic Troubleshooting and Root Cause Analysis 10.2 Troubleshooting and Repairing Pumps 10.3 Troubleshooting and Repairing Gearboxes

11 Steam Systems, Boilers, and Process Vessels

11.1 Low-Pressure Steam Systems, Traps, and Condensate Return 11.2 High-Pressure Steam Generation and Boiler Auxiliaries 11.3 Distillation Towers, Vessels, and Internals

12 Compressors and Pneumatic Systems

12.1 Air Compressor Types, Operation, and Maintenance 12.2 Compressed Air Treatment, Storage, and Distribution 12.3 FRL Units, Pneumatic Valves, Actuators, and Speed Control

2.2 Hazardous Energy Control: Lockout/Tagout and Confined Space Entry

Key Takeaways Explain This Topic AI

OSHA 29 CFR 1910.147(d) prescribes six steps: preparation for shutdown, machine shutdown, machine isolation, lockout/tagout device application, stored energy release or restraint, and verification of isolation.

Pushbuttons, emergency stops, selector switches, and controller interlocks are control circuit devices and may never serve as the energy isolating device for lockout.

Every authorized employee servicing the equipment must apply their own personal lock; group lockout uses master locks whose keys are secured in a lockbox that each worker locks.

Electrical zero-energy verification uses the live-dead-live method on a known energized source before and after testing the target conductors.

OSHA 29 CFR 1910.146 requires a permit for confined spaces that contain a hazardous atmosphere, engulfment potential, converging walls, or any other recognized serious hazard.

Last updated: September 2026

The standard and who it covers

29 CFR 1910.147, The Control of Hazardous Energy , applies whenever servicing or maintenance is performed and unexpected energization, startup, or the release of stored energy could injure someone. It defines three employee roles:

Authorized employee — locks or tags out equipment in order to service it. Only authorized employees apply personal locks and verify the zero-energy state.

Affected employee — operates the equipment being serviced, or works in the area where the servicing occurs. They must be notified before lockout begins and after it is removed.

Other employee — anyone whose work may take them into an area where energy control procedures are used.

Energy isolating device versus control circuit device

This distinction produces assessment items every cycle. An energy isolating device is a mechanical device that physically prevents the transmission or release of energy.

Classification Examples Acceptable as the lockout point?

Energy isolating device Manually operated disconnect switch, circuit breaker, line block valve (gate, ball, butterfly), blind flange or paddle blind, safety block or chock Yes

Control circuit device Start/stop pushbutton, emergency stop button, HMI touchscreen control, selector switch, controller interlock, light curtain No

A control circuit device operates through pilot voltage or software. A welded contactor, a shorted conductor, or a logic fault can bypass it, so OSHA does not accept it as the isolation point.

The six steps of 1910.147(d), in order

OSHA's application of control paragraph lists the sequence. Learn it exactly:

Preparation for shutdown — identify the type and magnitude of every energy source, the hazards, and the means of control. Gather locks, tags, hasps, blinds, and blocks.

Machine or equipment shutdown — shut down using the normal operating procedure, in an orderly way that does not create a new hazard.

Machine or equipment isolation — operate every energy isolating device so the equipment is physically separated from its energy sources.

Lockout or tagout device application — each authorized employee affixes their own lock and durable tag to each isolating device.

Stored energy release or restraint — relieve, disconnect, restrain, or otherwise render safe all residual or stored energy.

Verification of isolation — confirm the zero-energy state before work begins.

Notification of affected employees is required by 1910.147(c)(9) before controls are applied and after they are removed, but it is not one of the six numbered application steps. Training materials that insert "notify" as step 2 are describing good practice, not the regulatory sequence.

Stored energy: what has to be bled, blocked, or drained

Energy form Typical maintenance hazard Control action

Electrical Charged capacitor banks in drives and power factor correction Discharge with an approved grounding device; wait for the manufacturer's dwell time

Hydraulic Accumulators holding pressure after the pump stops Open the manual accumulator dump valve; confirm gauges read zero

Pneumatic Plant air trapped downstream of a closed valve Vent through the bleed port; verify the regulator gauge falls to zero

Gravity Raised press rams, counterweights, elevated booms Lower to the lowest position, or insert certified safety pins or blocks

Spring Compressed springs in brakes, clutches, and relief valves Relieve or mechanically restrain per the equipment procedure

Rotational Flywheels, fan impellers, centrifuge bowls coasting after power loss Allow full coastdown; apply a mechanical brake or pin

Thermal Hot steam headers, heat transfer oil, cryogenic lines Allow to cool or warm, drain, and isolate

Process fluid Toxic, corrosive, or flammable material trapped in piping Double block and bleed, or install a blind flange

Verification: the try-step and live-dead-live

Verification is step 6, and it has two forms.

For mechanical verification , clear all personnel from the machine's zone of motion, attempt a normal start using the operating controls, confirm nothing moves, and then return the operating controls to the off or neutral position so the machine will not jump when it is eventually re-energized.

For electrical verification , use the live-dead-live method:

Test the meter on a known energized source to prove the meter and leads work.

Test the target conductors phase to phase and phase to ground, confirming zero voltage.

Re-test the meter on the known energized source to prove it did not fail during the measurement.

Group lockout and shift turnover

When a turnaround involves several crafts and dozens of isolation points, 1910.147(f)(3) allows group lockout. A primary authorized employee applies master locks to every isolating device, places the keys in a group lockbox , and locks the box. Every craft worker on the job then adds a personal lock to the lockbox hasp. The box cannot open — and the equipment cannot be re-energized — while any personal lock remains. At shift change, the outgoing worker removes their lock only as the incoming worker applies theirs, so protection is never interrupted.

Permit-required confined space entry

Maintenance mechanics routinely enter vessels, tanks, sumps, and boiler drums. 29 CFR 1910.146 classifies a confined space as permit-required if it contains or has the potential to contain a hazardous atmosphere, contains material that could engulf the entrant, has walls that converge or a floor that slopes to a smaller cross-section, or contains any other recognized serious safety or health hazard.

Atmospheric testing follows a fixed order: oxygen first, then flammable gases and vapors, then toxic gases and vapors. Oxygen is tested first because combustible gas meters and many toxic sensors give unreliable readings in an oxygen-deficient atmosphere. Acceptable oxygen content is 19.5% to 23.5% . Entry requires an attendant stationed outside the space for the duration of the entry, continuous or periodic monitoring per the permit, and a rescue plan that does not rely on the attendant entering.

Loading diagram... LOTO application sequence under 1910.147(d)