Study guide

3.1 Slings, Rigging Hardware, and Inspection Criteria

NCCER Industrial Maintenance Mechanic Exam

Track your progress as you read

Finished sections get a check mark.

1 The NCCER Industrial Maintenance Mechanic Assessment

1.1 The IMM Journey-Level Credential and Assessment Specification 1.2 The Nine Content Domains: Item Counts and a Study Plan

2 Industrial Maintenance Mechanic Fundamentals

2.1 Safety Programs, PPE, and Hazard Communication 2.2 Hazardous Energy Control: Lockout/Tagout and Confined Space Entry 2.3 Tools of the Trade: Hand and Power Tools 2.4 Oxyfuel Cutting: Equipment, Safe Setup, and Cutting Practice 2.5 Ferrous Metal Piping Practices: Cutting, Threading, and Joining

3 Rigging and Mobile Equipment

3.1 Slings, Rigging Hardware, and Inspection Criteria 3.2 Load Weight, Center of Gravity, Sling Angle, and Hand Signals 3.3 Mobile and Support Equipment: Forklifts, Aerial Lifts, and Mobile Cranes

4 Craft Mathematics, Layout, and Precision Measurement

4.1 Craft-Related Mathematics: Fractions, Units, Area, and Volume 4.2 Advanced Trade Math: Right Triangles, Trigonometry, and Pipe Offsets 4.3 Basic Layout: Squaring, Leveling, and Transferring Elevations 4.4 Precision Measuring Tools: Micrometers, Verniers, and Dial Indicators 4.5 Gauges, Tolerances and Fits, and Torque Measurement

5 Construction Drawings and Blueprint Reading

5.1 Reading Construction Drawings: Views, Lines, Scales, and the Title Block 5.2 Orthographic, Isometric, Arrangement, and Foundation Drawings 5.3 Advanced Blueprint Reading: P&IDs, Instrument Tags, and Welding Symbols

6 Valves, Packing, and Mechanical Seals

6.1 Valve Types and Service Selection 6.2 Valve Construction, Markings, Pressure Classes, and Actuators 6.3 Removing and Installing Valves: Flange Bolting and Torque Sequence 6.4 Valve Maintenance: Packing, Stuffing Boxes, Gaskets, and O-Rings 6.5 Hydrostatic and Pneumatic Testing of Piping and Equipment 6.6 Mechanical Seals: Components, Types, and Installation

7 Bearings, Lubrication, and Couplings

7.1 Bearing Types, Designations, and Selection 7.2 Bearing Lubrication, Handling, and Failure Analysis 7.3 Removing and Installing Bearings: Fits, Heating, and Mounting 7.4 Couplings: Types, Selection, and Installation

8 Pumps, Baseplates, and Mechanical Drives

8.1 Pumps and Drivers: Centrifugal and Positive Displacement 8.2 Setting Baseplates and Soleplates: Leveling, Anchoring, and Grouting 8.3 Prealignment: Soft Foot, Runout, Pipe Strain, and Shims 8.4 Installing Belt and Chain Drives

9 Shaft Alignment: Conventional, Reverse, and Laser

9.1 Conventional Rim-and-Face Dial Indicator Alignment 9.2 Reverse Dial Indicator Alignment 9.3 Laser Shaft Alignment Systems

10 Maintenance Troubleshooting: Method, Pumps, and Gearboxes

10.1 Systematic Troubleshooting and Root Cause Analysis 10.2 Troubleshooting and Repairing Pumps 10.3 Troubleshooting and Repairing Gearboxes

11 Steam Systems, Boilers, and Process Vessels

11.1 Low-Pressure Steam Systems, Traps, and Condensate Return 11.2 High-Pressure Steam Generation and Boiler Auxiliaries 11.3 Distillation Towers, Vessels, and Internals

12 Compressors and Pneumatic Systems

12.1 Air Compressor Types, Operation, and Maintenance 12.2 Compressed Air Treatment, Storage, and Distribution 12.3 FRL Units, Pneumatic Valves, Actuators, and Speed Control

3.1 Slings, Rigging Hardware, and Inspection Criteria

Key Takeaways Explain This Topic AI

OSHA 29 CFR 1910.184 requires each sling and all fastenings and attachments to be inspected for damage or defects by a competent person each day before use.

A wire rope sling must be removed from service when there are ten randomly distributed broken wires in one rope lay or five broken wires in one strand in one rope lay.

Synthetic web slings are removed for acid or caustic burns, melting or charring, holes, tears, cuts, snags, broken or worn stitching, and distorted fittings.

A shackle must never be side-loaded, and its pin must never be replaced with an ordinary bolt.

Alloy steel chain slings and all other slings must be marked with the manufacturer's identification and rated capacity, and unmarked slings are removed from service.

Last updated: September 2026

The domain in one sentence

Domain 2, Rigging and Mobile Equipment , contributes 9 of 115 items and draws on core module 00106 Basic Rigging , 32111 Material Handling and Hand Rigging , and 32112 Mobile and Support Equipment . Nine items is small, but rigging is heavily standardized, so it is the cheapest domain on the exam to convert into points.

Sling types and where each belongs

Sling type Strengths Limitations Governing detail

Alloy steel chain Heat tolerant, abrasion resistant, repairable Heavy; can damage finished surfaces Rated capacity tag required; removal for cracks, gouges, stretch, or twisted links

Wire rope High strength, good abrasion resistance, visible failure warning Kinks are permanent; birdcaging is fatal Removal for broken-wire counts, kinking, crushing, birdcaging, or heat damage

Synthetic web Light, wide bearing surface, protects finishes Cut and chemical sensitive; degrades in sunlight Removal for burns, melting, charring, holes, cuts, snags, broken stitching

Round sling Conforms to the load, very light Cover damage hides core damage Removal if the core yarn is exposed

Metal mesh Excellent for hot or sharp loads Heavy, limited flexibility Removal for broken welds, broken mesh, distortion

Inspection: the rule that generates the items

29 CFR 1910.184(d) requires that each day before being used, the sling and all fastenings and attachments be inspected for damage or defects by a competent person designated by the employer, and that damaged or defective slings be immediately removed from service . Additional periodic inspections are required where service conditions warrant, and a record of the most recent thorough inspection is required for alloy steel chain slings.

The removal criteria worth memorizing exactly:

Wire rope slings — remove for ten randomly distributed broken wires in one rope lay , or five broken wires in one strand in one rope lay . Also remove for kinking, crushing, birdcaging, heat damage, severe corrosion, or end-attachment damage.

Synthetic web slings — remove for acid or caustic burns, melting or charring of any part of the sling, snags, punctures, tears or cuts, broken or worn stitches, and distortion of fittings.

Alloy steel chain slings — remove for cracked, bent, gouged, stretched, or twisted links, and whenever the manufacturer's allowable wear is exceeded.

Every sling must carry the manufacturer's identification and its rated capacity . A sling with an unreadable tag has no rated capacity and comes out of service.

A "rope lay" is the distance along the rope in which one strand makes a complete revolution around the core. Counting broken wires over a longer distance understates the damage.

Rigging hardware

Shackles. Anchor (bow) shackles handle multi-leg loads and side-pull better than chain (D) shackles, which are meant for straight in-line pull. Three rules cover most assessment items:

Never side-load a shackle beyond its rating; capacity falls sharply as the pull angle moves off the shackle's axis.

Never replace a shackle pin with a bolt. A bolt is not rated, is not the correct diameter, and will bend.

Seat a screw-pin shackle fully, then back it off a quarter turn only if the manufacturer instructs; on long-term or vibrating lifts, use a bolt-type shackle with a nut and cotter pin .

Hooks. Every hook used for personnel-adjacent lifting should have a functioning safety latch . Under ASME B30.10 practice, a hook is removed when the throat opening has increased by more than 15% of the original dimension or the hook is twisted more than 10 degrees from the plane of the unbent hook, and for any crack, gouge, or wear exceeding 10% of the original section.

Eyebolts. A plain (non-shouldered) eyebolt is rated for vertical, in-line pull only . A shouldered eyebolt can take an angular pull, but its capacity drops dramatically as the angle increases, and the shoulder must be seated flush against the load. Never rig two legs to a single eyebolt in a way that pulls it sideways.

Turnbuckles, wire rope clips, thimbles. Wire rope clips are installed with the saddle on the live (load) side and the U-bolt on the dead end — "never saddle a dead horse." Thimbles preserve the eye radius and prevent crushing.

Protecting the sling and the load

Sharp corners cut synthetic slings and crush wire rope. Use softeners, corner protectors, or wear pads at every edge. Keep slings off the floor when not in use, store them out of sunlight, and never shorten a sling by knotting it, bolting it, or wrapping it around the hook.