Study guide
9.6 Crane Assembly & Disassembly: Lattice Boom, Counterweights & the A/D Director
NCCER Rigger Basic / Advanced
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Overview, Qualifications & Safety Standards
1.1 NCCER Rigger Certification Structure, Exam Format & Testing Policies 1.2 OSHA 29 CFR 1926 Subpart CC & Qualified Rigger Requirements 1.3 ASME B30 Standards Framework for Rigging & Lifting 1.4 Job-Site Safety, Hazard Identification & Exclusion Zones
2 Chapter 2: Slings & Hitches
2.1 Types of Slings: Synthetic, Wire Rope, Alloy Chain & Metal Mesh 2.2 Basic Rigging Hitches: Vertical, Choker, Basket & Bridles 2.3 Choker Hitch Reductions & Choke Angle Factors 2.4 Basket Hitch Configurations, D/d Ratios & Efficiency
3 Chapter 3: Sling Angles & Tension Calculations
3.1 Principles of Sling Leg Angle & Horizontal Sling Angles 3.2 Sling Tension Formulas & Worked Calculation Examples 3.3 Critical Sling Angles & The 30-Degree Prohibition 3.4 Symmetrical vs. Non-Symmetrical Bridle Leg Tension & Center of Gravity Alignment
4 Chapter 4: Sling Inspection & Removal Criteria
4.1 Wire Rope Sling Inspection & ASME B30.9 Removal Criteria 4.2 Synthetic Web & Round Sling Inspection & Removal Criteria 4.3 Alloy Steel Chain Sling Inspection & Wear Limits 4.4 Metal Mesh & High-Performance Synthetic Slings Inspection
5 Chapter 5: Rigging Hardware & Below-the-Hook Lifting Devices
5.1 Shackles: Types, Application, Loading & ASME B30.26 Inspection 5.2 Eyebolts, Swivel Hoist Rings & Angular Loading Deratings 5.3 Hooks: Types, ASME B30.10 Inspection Criteria & Latch Requirements 5.4 Below-the-Hook Lifting Devices: Spreader Bars, Equalizer Beams & ASME B30.20
6 Chapter 6: Rigging Hardware Connections & Specialty Tools
6.1 Turnbuckles, Rigging Links & Master Rings 6.2 Wire Rope Clips: U-Bolt vs. Fist Grip & Installation Efficiency 6.3 Wedge Sockets & Wire Rope End Terminations 6.4 Snatch Blocks, Sheaves & Lead Line Calculations 6.5 Hoisting & Jacking Equipment: Chain Hoists, Lever Hoists, Winches & Gantries 6.6 Rigging Knots, Fiber Rope & Rope Work for Load Control
7 Chapter 7: Wire Rope Construction, Inspection & Reeving
7.1 Wire Rope Components, Core Types & Lay Classifications 7.2 Crane Hoist Wire Rope Inspection & Retirement Criteria 7.3 Reeving Patterns, Parts of Line & Mechanical Advantage 7.4 Hoist Drum Capacity, Fleet Angle & Minimum Wraps 7.5 Wire Rope Handling, Installation, Storage & Field Maintenance
8 Chapter 8: Load Weight Estimation & Center of Gravity
8.1 Material Densities & Basic Volume Formulas for Riggers 8.2 Load Weight Calculations for Symmetrical & Composite Shapes 8.3 Determining Center of Gravity (CG) for Regular & Irregular Loads 8.4 Center of Gravity Above vs. Below Pick Points & Load Stability
9 Chapter 9: Crane Operations, Safety Devices & Communication
9.1 Mobile Crane Types, Quadrants of Operation & Boom Geometry 9.2 Crane Safety Devices & Operational Aids (A2B, LMI, Level Indicators) 9.3 Standard ASME B30.5 Hand Signals & Radio Communication Protocols 9.4 Power Line Clearances, Weather Limits & Ground Bearing Conditions 9.5 Telescopic Boom Attachments: Swing-Away Extensions, Jibs, Erecting & Stowing 9.6 Crane Assembly & Disassembly: Lattice Boom, Counterweights & the A/D Director 9.7 Crane Safety Devices Out of Service, Emergency Procedures & Responding to Crane Incidents
10 Chapter 10: Advanced Rigging Operations & Lateral Movement
10.1 Lateral Load Movement: Incline Planes, Friction & Required Line Pull 10.2 Drifting Loads Between Two Hoists & Load Transfer Principles 10.3 Inverting, Rolling & Turning Heavy Loads 10.4 Advanced Cribbing, Blocking & Jacking Operations 10.5 Rigging Piping, Pipe Spools & Rebar Bundles
11 Chapter 11: Complex Lift Planning & Multi-Crane Lifts
11.1 Lift Plan Components, Roles & Responsibilities 11.2 Critical Lift Criteria & Engineering Analysis 11.3 Multi-Crane Tandem Lifts: Load Distribution & Synchronization 11.4 Crane Load Chart Deductions: Net vs. Gross Capacity Calculations 11.5 Reading Mobile Crane Load Charts: Configurations, Range Diagrams & Chart Selection
12 Chapter 12: Personnel Hoisting & Site Rigging Management
12.1 OSHA 29 CFR 1926.1431 Personnel Hoisting Regulations & Derating 12.2 Suspended Personnel Platforms: Design, Proof Testing & Trial Lift 12.3 Tagline Safety, Load Control & Line-of-Fire / Pinch-Point Hazards 12.4 Rigging Storage, Maintenance, Documentation & Periodic Inspection Logs
9.6 Crane Assembly & Disassembly: Lattice Boom, Counterweights & the A/D Director
Key Takeaways Explain This Topic AI
Crane assembling and disassembly is an explicit Crane Knowledge topic on the NCCER Advanced Rigger written assessment and is taught in module 21306, Lattice Boom Assembly and Disassembly.
OSHA 29 CFR 1926.1404 requires assembly/disassembly to be directed by an A/D director who both understands the procedures and meets the criteria for a competent person and a qualified person (or works with one).
The A/D director must address a defined list of hazards including ground bearing conditions, blocking material and placement, verified assist-crane loads, boom and jib pick points, center of gravity, stability upon pin removal, snagging, counterweight movement, boom hoist brake failure, and loss of backward stability.
Rigging for assembly/disassembly must be performed by a qualified rigger under 1926.1404(r)(1) — this is one of only two places OSHA names the qualified rigger by title.
Lattice sections are non-symmetrical: the center of gravity is rarely at the geometric middle, so pick points, blocking placement, and pin-removal sequence all follow the manufacturer procedure, not judgment.
Last updated: August 2026
9.6 Crane Assembly & Disassembly: Lattice Boom, Counterweights & the A/D Director
The Advanced Rigger written assessment lists "crane assembling and disassembly" under Crane Knowledge, and NCCER module 21306, Lattice Boom Assembly and Disassembly , teaches it. Assembly/disassembly (A/D) is also one of exactly two places in OSHA Subpart CC where a qualified rigger is named by title — which is why it belongs in a rigger study guide rather than only an operator one.
A/D deserves that attention. The crane is at its least stable while it is being built or taken apart: sections are supported by blocking rather than by the machine, counterweights are being moved, and pins are being pulled from members that are still carrying load.
The A/D Director
Under 29 CFR 1926.1404, assembly and disassembly must be directed by a person who meets the criteria for both a competent person and a qualified person, or by a competent person who is assisted by a qualified person . That person is the A/D director , and the standard gives them concrete duties:
Understand the applicable assembly/disassembly procedures before the work starts.
Review the procedures immediately prior to beginning work, unless they have already applied them to the same type and configuration of equipment.
Ensure crew members understand their tasks, the hazards, and the hazardous positions or locations they must avoid.
Verify that any crew member who moves out of the operator's view has a means of signaling or an agreed protocol before re-entering a hazardous area.
The employer must use either the manufacturer procedures or employer procedures that meet the standard's requirements — improvised sequences are not an option.
The Hazards OSHA Requires the Director to Address
29 CFR 1926.1404(h) names them explicitly. Learn this list; it is the skeleton of any A/D exam question.
1926.1404(h) Hazard What it means on the ground
(h)(1) Site and ground bearing conditions The ground must support the equipment during A/D, not just during the lift (cross-reference 1926.1402)
(h)(2) Blocking material Size, amount, condition, and stacking method sufficient to sustain the loads and maintain stability
(h)(3) Proper location of blocking Placed to protect structural integrity and prevent dangerous movement and collapse
(h)(4) Verifying assist crane loads Loads imposed on the assist crane at each phase must be verified before work begins
(h)(5) Boom and jib pick points Rigging attachment points must prevent structural damage and allow safe handling
(h)(6) Center of gravity CG must be identified where the stability method depends on it; where information is insufficient, use measures that prevent unintended dangerous movement
(h)(7) Stability upon pin removal Sections, suspension systems (gantry A-frames, jib struts), and components must be rigged or supported to stay stable when the pins come out
(h)(8) Snagging Suspension ropes and pendants must not catch on connection pins, cotter pins, keepers, or locking pins
(h)(9) Struck by counterweights Unintended movement from inadequately supported counterweights and from hoisting counterweights
(h)(10) Boom hoist brake failure The brake must be tested before each time reliance is placed on it to hold the boom during A/D
(h)(11)+ Loss of backward stability Backward stability before swinging the upperworks, travelling, and during A/D
Lattice Boom Handling: Why the Middle Is Not the Middle
A lattice section looks symmetrical and almost never is. Chord sizes taper along the boom, splice plates and lugs sit on one end, and inserts differ from butt and tip sections. That has three consequences:
Pick points are designated, not chosen. The manufacturer specifies where to rig a section. Rigging at the geometric center of a section whose CG is offset will make it swing the instant it leaves the blocking.
Blocking supports the chords, not the lacing. Lattice lacing members are slender compression/tension web members. Blocking placed under lacing crushes the section. Blocking goes under the chords, at the locations the procedure specifies, on material sized for the load.
Pin removal order is fixed. Pins are pulled in a sequence that keeps the section supported at every step. A section that becomes a cantilever mid-sequence will bind the last pin so hard it cannot be driven — and when it finally releases, it releases violently.
Pin-driving discipline: never align a pin bore with fingers, never stand in the swing path of a suspended section, and never assume a pin is free because it is loose in the bore — a boom section under residual load can pinch a pin that has already been backed out.
Counterweights
Counterweight handling causes a disproportionate share of A/D fatalities. The controls are simple and non-negotiable:
Install and remove counterweights strictly in the manufacturer sequence and quantity . Partial or mismatched counterweight configurations produce a crane that matches no load chart at all.
Support slabs so they cannot tip or slide when the lifting force is released — a leaning slab on a trailer deck is a crush hazard the moment the rigging goes slack.
Keep the crew out of the swing path of the counterweight and out of the pinch between the counterweight and the carrier or superstructure.
Backward stability is a live hazard during A/D: an upperworks carrying full counterweight with no boom, or with the boom at a high angle, can tip rearward . That is why the standard treats loss of backward stability as its own listed hazard.
The Rigger's Specific Duties
Under 1926.1404(r) , when rigging is used for assembly/disassembly:
(r)(1) the rigging work must be done by a qualified rigger ;
(r)(2) synthetic slings must be protected from abrasive, sharp, or acute edges and from configurations that reduce rated capacity, such as distortion or localized compression;
(r)(3) the synthetic sling manufacturer's instructions must be followed.
Combined with 1926.1425(c) — qualified rigger required whenever employees are in the fall zone hooking, unhooking, or guiding a load — these are the two places where OSHA converts "qualified rigger" from a general expectation into a specific legal requirement.