7.5 Manufactured Homes, RV Parks, Marinas & Temporary Installations (Articles 550, 551, 555, 590)

Nebraska Journeyman Electrician Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Nebraska State Electrical Act, Licensing & Exam Navigation

1.1 Nebraska Licensing Framework & State Electrical Act 1.2 Permitting, Inspections & Code Enforcement in Nebraska 1.3 Exam Format, NEC 2023 Structure & Open-Book Strategy

2 Chapter 2: General Electrical Knowledge — Definitions, Theory & Article 110

2.1 NEC Article 100 Definitions & Mandatory Code Rules 2.2 Electrical Theory, Ohm's Law & Power Calculations 2.3 General Installation Requirements & Equipment Working Spaces

3 Chapter 3: Branch Circuits, GFCI/AFCI, Load Calculations & Outside Feeders

3.1 Branch-Circuit Ratings & Required Outlets 3.2 GFCI & AFCI Protection Requirements 3.3 Feeder Sizing & General Demand Factors 3.4 Dwelling Unit Service & Feeder Load Calculations 3.5 Outside Branch Circuits, Feeders & Separate Buildings

4 Chapter 4: Services, Overcurrent Protection, Grounding & Bonding

4.1 Services & Service Equipment 4.2 Overcurrent Protection & Surge Protection (Articles 240 and 242) 4.3 Grounding vs. Bonding Principles 4.4 Grounding Electrode System & GEC Sizing 4.5 Equipment Grounding Conductors & Bonding Jumpers

5 Chapter 5: Wiring Methods, Conductors & Enclosure Calculations

5.1 Conductor Sizing, Ampacity & Derating 5.2 Raceways, Cable Assemblies & Underground Installations 5.3 Conduit Fill & Raceway Calculations 5.4 Box Fill & Enclosure Sizing

6 Chapter 6: Equipment for General Use

6.1 Receptacles, Switches & Luminaires 6.2 Cords, Panelboards, Appliances, Space Heating & Generators 6.3 Motor Branch Circuits, Overload & Short-Circuit Protection 6.4 Transformers & HVAC Equipment

7 Chapter 7: Special Occupancies

7.1 Hazardous (Classified) Locations 7.2 Commercial Garages, Motor Fuel Dispensing & Spray Areas (Articles 511, 514, 516) 7.3 Agricultural Buildings & Livestock Facilities 7.4 Healthcare Facilities & Places of Assembly 7.5 Manufactured Homes, RV Parks, Marinas & Temporary Installations (Articles 550, 551, 555, 590)

8 Chapter 8: Special Equipment — Pools, Solar PV, EV Charging & More

8.1 Swimming Pools, Spas & Hot Tubs (Article 680) 8.2 Solar Photovoltaic Systems & Energy Storage 8.3 EV Charging, Signs, Welders, Elevators & Fire Pumps (Articles 625, 600, 630, 620, 695)

9 Chapter 9: Special Conditions, Fire Alarm & Jobsite Safety

9.1 Emergency, Legally Required & Optional Standby Systems 9.2 Fire Alarm, Class 1, Class 2 & Class 3 Circuits (Articles 760, 722, 724, 725, 770) 9.3 Electrical Safety, OSHA & NFPA 70E Work Practices

7.5 Manufactured Homes, RV Parks, Marinas & Temporary Installations (Articles 550, 551, 555, 590)

Key Takeaways Explain This Topic AI

Mobile home service equipment must be adjacent to the home, in sight from it, and not more than 30 feet from its exterior wall, rated at least 100 A (NEC 550.32).

A mobile home feeder uses four insulated, color-coded conductors, and the neutral is isolated from the enclosure in the home's panelboard.

Under the 2023 NEC, 70 percent of RV sites need a 30-A receptacle, and 20 percent of existing and 40 percent of new sites need a 50-A receptacle (551.71).

Shore power receptacles at docks need individual GFPE of 30 mA or less, and dock feeders and branch circuits need GFPE of 100 mA or less (555.35).

On construction sites, receptacles may not share a branch circuit with temporary lighting, and 125-V, 15-, 20-, and 30-A temporary receptacles need GFCI protection (590.4, 590.6).

Last updated: October 2026

Manufactured Homes, RV Parks, Marinas & Temporary Installations (Articles 550, 551, 555, 590)

The rest of the Special Occupancies area covers four places where power is supplied to something that moves, floats, or will soon be removed:

  • mobile and manufactured homes (Article 550);
  • recreational vehicles and RV parks (Article 551);
  • marinas and docks (Article 555); and

temporary construction power (Article 590).

Each article has a short list of numbers the exam likes to ask about.

1. Mobile and Manufactured Homes (Article 550)

A mobile home is a factory-built dwelling on a permanent chassis. A manufactured home is built to the federal HUD code and may sit on a permanent foundation. Both terms are defined in Article 100.

Service equipment (550.32):

Item Rule

Location for a mobile home Adjacent to the home, not mounted in or on it, and in sight from and not more than 30 feet from its exterior wall

Manufactured home Service equipment may be installed in or on the home when the 550.32(B) conditions are met, such as a permanent foundation and installation per the manufacturer's instructions

  • Rating At least 100 A at 120/240 V for the mobile home service equipment
  • Outlet for the home An outlet (receptacle or feeder connection) rated to match the supply

Feeder and cord (550.10, 550.33):

A home may be supplied by a listed power-supply cord , rated 50 A maximum. A 40-A cord is allowed only when the home is factory-equipped with gas or oil heat and cooking. Cord length is 21 to 36½ feet .

Otherwise, the home is supplied by a permanently installed feeder of four continuous, insulated, color-coded conductors : two ungrounded, one grounded (neutral), and one EGC .

Grounding inside the home (550.16). The home's panelboard is treated like a subpanel. The neutral bar is insulated from the enclosure , and the EGC bonds the frame and enclosure. The home is not the service equipment unless the 550.32(B) conditions allow it.

Park load calculations (550.31). Park electrical wiring systems are calculated at the larger of 16,000 VA per lot or the calculated load of the largest typical home the lot will accept. The demand factors of Table 550.31 decrease as the number of lots increases.

2. Recreational Vehicles and RV Parks (Article 551)

Receptacles at each site (551.71):

  • Requirement 2023 NEC
  • Every RV site with electrical supply At least one 20-A, 125-V receptacle
  • 30-A sites At least 70% of sites also have a 30-A, 125-V receptacle
  • 50-A sites At least 20% of existing and 40% of new sites have a 50-A, 125/250-V receptacle
  • GFCI 125-V, single-phase, 15- and 20-A receptacles need GFCI protection

Other RV park rules:

Calculated load (551.73): Feeders and services are calculated on minimum volt-amperes per site, which differ for 50-A sites, 20- and 30-A sites, 20-A-only sites, and tent sites. Table 551.73(A) gives minimum demand factors.

Branch circuits: Each 50-A receptacle must be on its own branch circuit (551.72).

Grounding: EGC continuity may not depend on device removal, and there is no neutral-to-ground bonding on the load side.

Overhead clearances (551.79): In areas subject to RV movement, overhead conductors need at least 18 ft vertically and 3 ft horizontally. Elsewhere, 225.18 and 225.19 apply.

3. Marinas, Boatyards & Docking Facilities (Article 555)

Electric shock drowning is a real hazard: current leaking into fresh water can paralyze a swimmer. Nebraska's lakes and reservoirs make Article 555 relevant even though the state is landlocked.

Rule Requirement

Ground-fault protection, feeders and branch circuits on docks (555.35(A), 2023) GFPE set to open at not more than 100 mA , coordinated with downstream devices

Shore power receptacles (555.35(B)) Individual GFPE not exceeding 30 mA for each shore power receptacle's branch circuit

Other 125-V, 15- and 20-A receptacles on docks GFCI protection

Shore power receptacle rating (555.33) At least 30 A . 30-A and 50-A shore power receptacles must be locking and grounding type, in listed marina power outlets or enclosures

Electrical datum plane For floating piers, 30 in above the water and at least 12 in above the deck. Electrical connections on floating piers must be located at or above it

Equipotential plane (555.14, new in 2023) Required at outdoor service equipment or disconnects controlling equipment in or on the water, when the voltage is over 250 V to ground and the equipment is within 10 ft of the water. Extends 36 in in all directions from where a person can stand to operate the equipment

4. Temporary Installations (Article 590)

Time limits (590.3):

During construction: Temporary power and lighting are allowed for the period of construction, remodeling, maintenance, repair, or demolition.

90 days: Holiday decorative lighting and similar uses are limited to 90 days.

Emergencies and tests: Temporary wiring is allowed for emergencies, tests, experiments, and development work.

Removal: Temporary wiring must be removed immediately when the project or purpose is complete.

Wiring rules (590.4):

Feeders and branch circuits: They originate in an approved distribution center. Cable assemblies or multiconductor cords of hard-usage or extra-hard-usage types (Table 400.4) are allowed.

Receptacles: All must be the grounding type . On construction sites, receptacles may not share a branch circuit with temporary lighting .

Lamp protection: General-illumination lamps need a guard or a suitable luminaire. Metal-shell sockets must be grounded.

Splices: On construction sites, a box is not required for splices in nonmetallic multiconductor cord or cable assemblies if EGC continuity is maintained, or for metal-sheathed cables terminated in listed fittings.

Support: Cables and cords must be supported to protect them from damage. Branch-circuit and feeder cables may not lie on the floor or ground, and vegetation may not support overhead spans. Extension cords are exempt from the support rule.

Disconnects: Suitable disconnects are required for every ungrounded conductor of each temporary circuit, with multiwire circuits disconnected simultaneously.

GFCI protection (590.6):

125-V, single-phase, 15-, 20-, and 30-A receptacle outlets that are not part of the permanent wiring and are used by personnel need listed GFCI protection.

The 125-V and 125/250-V, 15-, 20-, and 30-A receptacles on portable generators of 15 kW or less used for temporary power also need listed GFCI protection (590.6(A)(3)).

Other receptacles used for temporary power by personnel need GFCI protection, special-purpose GFCI (SPGFCI) protection where the voltage or phase requires it, or another method permitted by 590.6(B).

OSHA 1926.404(b) imposes a parallel federal requirement on construction employers (section 9.3).

5. Common Exam Traps

Mobile home service location: The service goes beside the home, within 30 feet , not on it, unless the home is a manufactured home meeting 550.32(B).

Mobile home feeder: It has four wires. The neutral is isolated in the home's panel.

Temporary lighting: Construction-site receptacles may not share a circuit with temporary lighting.

Holiday lighting: The limit is 90 days .

Dock ground fault: Feeders and branch circuits use 100 mA GFPE. Shore power receptacles use 30 mA .