7.3 Outside Air, Exhaust Balancing, and Building Pressurization
NEBB Testing, Adjusting and Balancing Certified Technician CT
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Role, Documents, and Readiness
1.1 NEBB TAB CT Role, CP Guidance, Standards, and Data Integrity 1.2 Interpreting Plans, Schedules, and Control Sequences 1.3 Field Verification, Pre-TAB Readiness, and Deficiencies
2 Chapter 2: TAB Math and Heat Transfer
2.1 TAB Mathematics, Units, Ratios, and Formula Discipline 2.2 Air-Side Sensible, Latent, and Total Heat Transfer 2.3 Hydronic Heat Transfer, Glycol Corrections, and Coil Cross-Checks
3 Chapter 3: Psychrometrics
3.1 Psychrometric Properties and Reading the Chart 3.2 Psychrometric Processes, Air Mixing, and Coil Diagnostics
4 Chapter 4: TAB Instrumentation and Measurement Quality
4.1 Pressure Instruments, Manometers, Zeroing, and Tubing 4.2 Airflow Instruments: Hoods, Anemometers, and Pitot Tubes 4.3 Hydronic Pressure and Temperature Instruments 4.4 Electrical and Rotational Instruments
5 Chapter 5: Air Systems and Airflow Fundamentals
5.1 Air-System Configurations and System Relationships 5.2 Airflow Continuity, Standard Air, Density, and Velocity 5.3 Duct Geometry and Worked Airflow Calculations
6 Chapter 6: Duct Traverses
6.1 Traverse Locations, Disturbances, and Point Layout 6.2 Traverse Velocity Conversion and Airflow Calculation
7 Chapter 7: Terminal Measurements and Air Balancing
7.1 Terminal Devices, Effective Area, and Capture-Hood Checks 7.2 Proportional Air Balancing and Final Verification 7.3 Outside Air, Exhaust Balancing, and Building Pressurization
8 Chapter 8: Fans, Motors, and Drives
8.1 Fan Types, Performance Curves, and Rotation 8.2 Fan Affinity Laws, Pressure, and Power 8.3 Motors, Single- and Three-Phase Measurements, and Loading 8.4 Belts, Sheaves, Alignment, and Variable Frequency Drives
9 Chapter 9: HVAC Controls and VAV Systems
9.1 HVAC Control Fundamentals, Signals, and Test States 9.2 VAV Terminal Types, Airflow Sensors, and Calibration 9.3 VAV System Balancing, Diversity, and Static-Pressure Control
10 Chapter 10: Hydronic System Fundamentals
10.1 Hydronic Pressure, Head, Open and Closed Systems, and Resistance 10.2 Expansion Tanks, Point of No Pressure Change, and Fill Pressure
11 Chapter 11: Pumps and Hydronic Balancing
11.1 Centrifugal Pumps, Pump Curves, and Pump Affinity Laws 11.2 Balancing Valves, Circuit Setters, Strainers, and Hydronic Procedures
12 Chapter 12: Reporting, Safety, and Problem Solving
12.1 Project Acceptance Criteria, Data Traceability, and Certified Reports 12.2 Field Safety, Electrical Boundaries, Pressure, and Access 12.3 Integrated TAB Problem Solving and Measurement Cross-Checks
7.3 Outside Air, Exhaust Balancing, and Building Pressurization
Key Takeaways Explain This Topic AI
A mixed-air temperature ratio is an estimate that requires representative, stable temperatures, adequate separation, complete mixing, and a disclosed uncertainty screen.
Test the outdoor-air and economizer operating points required by the approved design and sequence; neither a universal minimum mode nor a 100% command applies to every system.
Building and room pressure direction and magnitude come from the design and applicable occupancy requirements; example targets are not universal acceptance criteria.
Specialized spaces use the pressure direction, magnitude, door state, and test condition defined by their governing project requirements.
Use continuity only across an explicitly defined boundary, with every intake, exhaust, relief, transfer, and leakage path considered.
Last updated: August 2026
- Outside Air, Exhaust, and Building Pressure
- Start with boundaries and modes
Outdoor-air verification is a mass-balance problem tied to a particular operating mode. Identify the air-handling-unit mixing boundary and the building-envelope boundary. At steady conditions, and with all relevant streams included, supply air is the combination of return and outdoor air. At the building boundary, supply, return, exhaust, relief, infiltration, and exfiltration must reconcile. Leakage or an unmeasured relief path makes a simple subtraction incomplete.
Verify occupied mode, fan speed, VAV diversity, economizer command, relief or return-fan operation, doors, and major exhaust systems. Record weather and exterior-reference location because wind and stack effect can dominate a small envelope-pressure reading.
Direct outdoor-air methods
A traverse in a dedicated outdoor-air duct is preferred when a suitable plane and measurable velocity are available. Use the selected traverse procedure, actual net area, density treatment, and a calibrated instrument. A face-velocity sweep at a louver or damper requires a valid manufacturer effective-area factor and a repeatable measurement plane; gross louver dimensions alone generally do not establish flow.
Another useful check is a complete airflow balance. Under stated steady assumptions and with no omitted relief or leakage stream, outdoor airflow at a mixing unit equals supply minus return. Treat this as a diagnostic cross-check, not an automatic substitute for a direct measurement.
Temperature-ratio method
When outdoor and return airstreams mix without intervening sensible heat, the outdoor-air fraction can be estimated from dry-bulb temperatures:
OA fraction = (Tma - Tra) / (Toa - Tra)
The temperatures must represent the mean outdoor, return, and mixed streams. Use a multipoint grid where stratification exists. Coils, humidifiers, fan heat, solar-heated intake surfaces, leakage, and poor mixing can invalidate the energy balance.
The denominator controls uncertainty. As Toa approaches Tra, ordinary sensor error and spatial variation produce a large percentage error. Some field procedures use a screening difference such as 20°F, but the technician must follow the governing method and perform an uncertainty check rather than claiming a universal NEBB minimum. Enthalpy or tracer methods may be more suitable when latent conditions matter, provided the project procedure supports them.
Example: total supply is 20,000 CFM, Toa is 95°F, Tra is 75°F, and a representative Tma is 79°F. The fraction is (79 - 75) / (95 - 75) = 0.20, so the estimate is 4,000 CFM. The result is defensible only after the stated assumptions and mixing quality are verified.
Economizer and minimum ventilation
Follow the approved sequence for minimum-ventilation, economizer, and relief modes. Command only authorized overrides, verify physical damper response and linkage, measure flow, and adjust only the permitted setpoint or mechanism. A command percentage is not an airflow percentage. Recheck outdoor flow after changes in fan speed or duct static because damper pressure drop changes.
There is no universal TAB acceptance band that permits every outdoor-air result from design to 10% high. Apply the project criterion. If a minimum ventilation requirement is involved, report the measured result and limitation without altering data to create a pass.
Building differential pressure
The target and test conditions come from the design, sequence, space use, and governing requirements. An office, isolation room, hazardous compounding room, operating room, stair enclosure, and laboratory can require different pressure relationships and verification methods. Do not apply +0.02 to +0.05 in. w.g. as a universal office target or use pressure alone to predict door-opening force.
Measure across the specified boundary with a suitable low-range differential instrument. Route and shield the outdoor reference as the method requires. Test with the defined doors open or closed and the required exhaust systems operating. Sample multiple facades or conditions when wind is influential. For room relationships, verify airflow direction at the doorway or transfer path using the specified method in addition to pressure where required.
Reconcile the system
Suppose supply is 50,000 CFM, return is 41,000 CFM, and exhaust is 6,500 CFM. If conditions are steady and there are no other intake, relief, transfer, or leakage streams within the chosen boundary, supply minus return implies 9,000 CFM outdoor air, leaving 2,500 CFM for outward envelope flow. In an actual building, use independently measured streams and document uncertainty before assigning the entire residual to exfiltration.
Unexpected pressure calls for a system check: verify fan and exhaust status, damper command versus position, relief path, door and elevator conditions, filter loading, wind, stack effect, and measurement reference. Preserve both the measured value and the conditions under which it occurred.
A valid outdoor-air result records:
- the selected measurement boundary and all included airstreams;
- occupied, economizer, exhaust, return, and relief modes;
- weather, door state, and exterior pressure reference; and
method limitations such as stratification, leakage, or small temperature difference.