Study guide
4.1 ANSI Device Numbers (27, 50, 51, 59, 86, 87)
NETA ETT Level II Certified Assistant Technician Exam
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 About the NETA Level 2 Exam 1.2 The NETA Certification Hierarchy & Eligibility 1.3 Exam Administration, Scoring & Scheduling 1.4 Study Plan & How to Use This Guide
2 Chapter 1: Electrical Safety
2.1 NFPA 70E Approach Boundaries & Arc-Flash 2.2 PPE, Rubber Glove Classes & Hearing Protection 2.3 LOTO & the Electrically Safe Work Condition 2.4 Energized Work Permits & Live-Dead-Live 2.5 Temporary Protective Grounds & Induced Voltage 2.6 Hipot Testing Safety & Post-Hipot Grounding 2.7 Confined Space & General Electrical Safety 2.8 Risk Assessment, Job Briefings & the Hierarchy of Risk Controls 2.9 Codes & Standards: NFPA 70 Key Provisions and the ANSI/NETA Specifications
3 Chapter 2: Power Systems Theory
3.1 Three-Phase Power & Wye/Delta Relationships 3.2 Power Factor, Voltage Unbalance & Negative Sequence 3.3 Symmetrical Components & Fault-Current Paths 3.4 Grounding Systems & Impedance Grounding 3.5 Insulation Degradation & Dielectric Theory 3.6 Electrical Calculations, Units & Conversions
4 Chapter 3: Protection & Device Fundamentals
4.1 ANSI Device Numbers (27, 50, 51, 59, 86, 87) 4.2 IDMT/TCC Curves & Coordination 4.3 CT Theory: Ratio, Polarity, Burden, Accuracy & Knee Point 4.4 PT/VT Fundamentals & Insulation Coordination 4.5 Motor Circuits: FLA, PF Correction & Current Imbalance 4.6 One-Lines, Three-Lines, Schematics & Electrical Symbols 4.7 Short-Circuit & Coordination Studies
5 Chapter 4: Insulation Resistance Testing
5.1 Insulation Resistance: Test Voltages & IEEE 43 Minimums 5.2 Polarization Index (PI) & Dielectric Absorption Ratio (DAR) 5.3 Overpotential vs IR & Cable Hipot Basics 5.4 Guard Terminal, Doble Test Set & Thermography
6 Chapter 5: Withstand & Power-Factor Testing
6.1 DC Hipot: Step Voltage, Leakage Current & Pass Criteria 6.2 VLF Cable Testing & the DC/AC Voltage Conversion 6.3 Bushing Power Factor & Transformer PF Configurations 6.4 Oil Dielectric (ASTM) & DGA Sampling 6.5 Cable Fault Locating
7 Chapter 6: Transformer Testing
7.1 Transformer Turns Ratio (TTR) & Acceptance 7.2 Winding Resistance & Transformer Polarity 7.3 Transformer IR Configurations & Neutral-Ground Bond 7.4 SFRA, Sudden-Pressure Relay & Dry-Transformer ATS Tests
8 Chapter 7: CT, Relay & Motor Testing
8.1 CT Ratio, Polarity & Saturation Testing 8.2 Primary vs Secondary Injection & Relay Pickup 8.3 Three-Phase Relay Test Set, Phase-Angle Meter & Induction Disc 8.4 Motor Surge Test & Current Imbalance 8.5 Adjustable-Speed Drives, Reclosers, Sectionalizers & Fiber-Optic Cables
9 Chapter 8: Switchgear & Breaker Testing
9.1 Contact Resistance (Ductor) & Torque Verification 9.2 Vacuum Bottle Integrity & VCB Maintenance Tests 9.3 Post-Fault Breaker Maintenance & LV Trip-Unit Settings 9.4 Switchgear Bus IR, MCC Inspection & Bonding Jumpers 9.5 Switches, Circuit Switchers & Network Protectors 9.6 Metal-Enclosed Busways & Outdoor Bus Structures
10 Chapter 9: Grounding, Batteries & Protective Devices
10.1 Ground-Electrode Testing: Fall-of-Potential & Clamp-On 10.2 Battery Load Test (IEEE 450), VRLA Ohmic & Intervals 10.3 Fuses, GFCI & Zero-Sequence CT Grounding 10.4 Surge Arrester Acceptance & SPD Verification 10.5 Metering Devices & Regulating Apparatus 10.6 Capacitor Banks & Reactors: Inspection, Testing & Acceptance
11 Chapter 10: Systems & Commissioning
11.1 Automatic Transfer Switch Functional Testing 11.2 NFPA 110 Emergency System Load Tests 11.3 Switchgear Functional Testing & Feeder Trip Troubleshooting 11.4 Generator Paralleling & Emergency System Commissioning 11.5 As-Found / As-Left Documentation 11.6 Restoration & Handover Workflow
4.1 ANSI Device Numbers (27, 50, 51, 59, 86, 87)
Key Takeaways Explain This Topic AI
ANSI/IEEE C37.2-2022 assigns each protective function a number; 27 = undervoltage, 50 = instantaneous overcurrent, 51 = AC time overcurrent, 59 = overvoltage, 86 = lockout, 87 = differential.
50 trips with no intentional time delay once current exceeds pickup; 51 trips on an inverse-time characteristic, so the same overcurrent device can do both jobs in a 50/51 unit.
Suffixes refine the function: N = neutral (50N/51N measured by residual or neutral CT), G = ground (51G on a separate ground CT), P = phase; 87T, 87G, 87B split differential into transformer, generator, and bus zones.
Pickup testing differs by device: a 50 element is checked at one current point (operate / no-operate), while a 51 element must be swept at several multiples of pickup to confirm the time curve.
86 is a lockout (master trip) relay — once it operates it stays operated and blocks reclose until an operator manually or electrically resets it.
Last updated: August 2026
Why Device Numbers Matter on a NETA Job
Quick Answer: Every relay, lockout, and meter on a one-line is labeled with an ANSI/IEEE C37.2 number. Knowing the number tells you what the device does, what test to perform, and what the trip target is before you ever touch the test set.
ANSI/IEEE C37.2-2022 (the active standard; no 2026 revision exists) assigns 95 function numbers plus 22 acronyms. A NETA Level 2 technician meets the same handful on almost every acceptance and maintenance job, so memorize the core set first.
The Core Device Numbers You Must Know
- Number Function Where a Level 2 tech encounters it
- 27 Undervoltage relay Undervoltage load shed, motor bus transfer, generator protection
- 50 Instantaneous overcurrent relay Feeder and motor short-circuit protection; the fast element of a 50/51
- 51 AC time overcurrent relay Feeder/motor overload and backup short-circuit protection; inverse-time curve
- 59 Overvoltage relay Bus overvoltage, capacitor can protection, generator V/Hz backup
- 67 Directional overcurrent relay Networked feeders, tie breakers, generator motoring protection
- 79 Reclosing relay Distribution feeder autoreclose (4-shot cycles common)
- 86 Lockout relay Master lockout after a fault; blocks reclose until reset
- 87 Differential relay Transformer (87T), generator (87G), bus (87B), motor (87M) zone protection
- Suffix Letters That Change the Meaning
A bare number tells you the function; the suffix tells you the application.
N — Neutral. 50N and 51N operate on residual or neutral current (3I0). They are sensitive to ground faults a phase element may miss.
G — Ground. 51G uses a dedicated ground CT (often a window/zero-sequence CT) rather than the residual connection. The distinction matters during a 50G/51G commissioning test because the shield and ground conductors must be routed back through the window or the scheme will misoperate on through-current.
P — Phase. 50P/51P are the phase overcurrent elements; modern numeric relays label each phase explicitly (50P-A, 50P-B, 50P-C).
T / G / B / M on 87. 87T = transformer differential, 87G = generator differential, 87B = bus differential, 87M = motor differential. Each zone has its own restraint characteristic and CT requirement.
S — Stalled / start. 66/48S-style suffixes appear on motor relays; 46 is phase-balance (negative-sequence) protection.
Why 50 Versus 51 Matters for Pickup Testing
A 50 element is an instantaneous trip. Once current crosses the pickup setting, the relay issues a trip in roughly 1.5 to 4 cycles — there is no intentional delay. Field pickup testing is therefore a single-point operate/no-operate check: inject 0.9 x pickup and confirm no trip, inject 1.1 x pickup and confirm a fast trip, and read the actual drop-out.
A 51 element is time-overcurrent. It follows an inverse-time curve (see Section 4.2), so pickup is verified at several multiples of setting current — typically 2x, 3x, 5x, and 10x — and the measured operate times are compared to the manufacturer curve and the coordination study. A common Level 2 mistake is to test a 51 at one current only; you have missed whether the time dial is correct.
A combined 50/51 relay houses both elements. The instantaneous element is usually set above the maximum through-fault (so it never operates for an external fault), while the time element covers overload and downstream backup. When you inject a current above the 50 pickup, expect an instantaneous trip; below the 50 pickup but above the 51 pickup, expect a timed trip. Reading the wrong target is a frequent cause of misdiagnosed relay tests.
86 Lockout — the Master Trip Relay
The 86 relay is not a protective relay in the sensing sense; it is a lockout/master trip auxiliary. When any protective element (50, 51, 87, etc.) operates, it energizes the 86 coil, which then seals itself in through a contact and trips all required breakers. Because it locks in, the breaker cannot be reclosed until an operator pushes the reset button (or sends a remote reset command). The 86 is why a faulted transformer stays isolated after a trip — without it, autoreclose schemes (79) could re-energize damaged equipment.
Worked Scenario: 50/51 on a 480 V Feeder
A 480 V feeder carries 600 A load and is protected by a 50/51 relay with a 1200:5 CT. Settings: 51 pickup = 1.25 x FLA (750 A primary, 3.125 A secondary), 51 time dial = 0.3 (standard inverse), 50 pickup = 9000 A primary (37.5 A secondary, set above the 7500 A maximum through-fault). During a close-in bolted fault at 25,000 A:
The 50 element operates first, tripping the feeder in ~2.5 cycles.
The 51 element also starts timing but the breaker is already open, so its target may not pick up.
The 86 lockout seals in and blocks autoreclose.
If you mis-set the 50 pickup to 6000 A (below the 7500 A through-fault), the relay will trip for a downstream fault — a coordination failure your injection test will catch if you sweep both elements.