Study guide
4.2 IDMT/TCC Curves & Coordination
NETA ETT Level II Certified Assistant Technician Exam
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 About the NETA Level 2 Exam 1.2 The NETA Certification Hierarchy & Eligibility 1.3 Exam Administration, Scoring & Scheduling 1.4 Study Plan & How to Use This Guide
2 Chapter 1: Electrical Safety
2.1 NFPA 70E Approach Boundaries & Arc-Flash 2.2 PPE, Rubber Glove Classes & Hearing Protection 2.3 LOTO & the Electrically Safe Work Condition 2.4 Energized Work Permits & Live-Dead-Live 2.5 Temporary Protective Grounds & Induced Voltage 2.6 Hipot Testing Safety & Post-Hipot Grounding 2.7 Confined Space & General Electrical Safety 2.8 Risk Assessment, Job Briefings & the Hierarchy of Risk Controls 2.9 Codes & Standards: NFPA 70 Key Provisions and the ANSI/NETA Specifications
3 Chapter 2: Power Systems Theory
3.1 Three-Phase Power & Wye/Delta Relationships 3.2 Power Factor, Voltage Unbalance & Negative Sequence 3.3 Symmetrical Components & Fault-Current Paths 3.4 Grounding Systems & Impedance Grounding 3.5 Insulation Degradation & Dielectric Theory 3.6 Electrical Calculations, Units & Conversions
4 Chapter 3: Protection & Device Fundamentals
4.1 ANSI Device Numbers (27, 50, 51, 59, 86, 87) 4.2 IDMT/TCC Curves & Coordination 4.3 CT Theory: Ratio, Polarity, Burden, Accuracy & Knee Point 4.4 PT/VT Fundamentals & Insulation Coordination 4.5 Motor Circuits: FLA, PF Correction & Current Imbalance 4.6 One-Lines, Three-Lines, Schematics & Electrical Symbols 4.7 Short-Circuit & Coordination Studies
5 Chapter 4: Insulation Resistance Testing
5.1 Insulation Resistance: Test Voltages & IEEE 43 Minimums 5.2 Polarization Index (PI) & Dielectric Absorption Ratio (DAR) 5.3 Overpotential vs IR & Cable Hipot Basics 5.4 Guard Terminal, Doble Test Set & Thermography
6 Chapter 5: Withstand & Power-Factor Testing
6.1 DC Hipot: Step Voltage, Leakage Current & Pass Criteria 6.2 VLF Cable Testing & the DC/AC Voltage Conversion 6.3 Bushing Power Factor & Transformer PF Configurations 6.4 Oil Dielectric (ASTM) & DGA Sampling 6.5 Cable Fault Locating
7 Chapter 6: Transformer Testing
7.1 Transformer Turns Ratio (TTR) & Acceptance 7.2 Winding Resistance & Transformer Polarity 7.3 Transformer IR Configurations & Neutral-Ground Bond 7.4 SFRA, Sudden-Pressure Relay & Dry-Transformer ATS Tests
8 Chapter 7: CT, Relay & Motor Testing
8.1 CT Ratio, Polarity & Saturation Testing 8.2 Primary vs Secondary Injection & Relay Pickup 8.3 Three-Phase Relay Test Set, Phase-Angle Meter & Induction Disc 8.4 Motor Surge Test & Current Imbalance 8.5 Adjustable-Speed Drives, Reclosers, Sectionalizers & Fiber-Optic Cables
9 Chapter 8: Switchgear & Breaker Testing
9.1 Contact Resistance (Ductor) & Torque Verification 9.2 Vacuum Bottle Integrity & VCB Maintenance Tests 9.3 Post-Fault Breaker Maintenance & LV Trip-Unit Settings 9.4 Switchgear Bus IR, MCC Inspection & Bonding Jumpers 9.5 Switches, Circuit Switchers & Network Protectors 9.6 Metal-Enclosed Busways & Outdoor Bus Structures
10 Chapter 9: Grounding, Batteries & Protective Devices
10.1 Ground-Electrode Testing: Fall-of-Potential & Clamp-On 10.2 Battery Load Test (IEEE 450), VRLA Ohmic & Intervals 10.3 Fuses, GFCI & Zero-Sequence CT Grounding 10.4 Surge Arrester Acceptance & SPD Verification 10.5 Metering Devices & Regulating Apparatus 10.6 Capacitor Banks & Reactors: Inspection, Testing & Acceptance
11 Chapter 10: Systems & Commissioning
11.1 Automatic Transfer Switch Functional Testing 11.2 NFPA 110 Emergency System Load Tests 11.3 Switchgear Functional Testing & Feeder Trip Troubleshooting 11.4 Generator Paralleling & Emergency System Commissioning 11.5 As-Found / As-Left Documentation 11.6 Restoration & Handover Workflow
4.2 IDMT/TCC Curves & Coordination
Key Takeaways Explain This Topic AI
An IDMT (Inverse Definite Minimum Time) curve has trip time inversely proportional to current but flattening to a minimum definite time at high multiples of pickup — the formula is t = TMS x k / ((I/Is)^alpha - 1).
IEC 60255-151 standard constants are Standard Inverse (k=0.14, alpha=0.02), Very Inverse (k=13.5, alpha=1.0), Extremely Inverse (k=80, alpha=2.0); IEEE C37.112 equivalents are Moderately, Very, and Extremely Inverse.
A TCC (time-current characteristic) curve plots current on the X-axis (log scale) and trip time on the Y-axis (log scale); coordination studies overlay device curves to confirm selectivity.
Selective coordination requires the downstream device curve to lie below the upstream device curve with a coordination time interval (CTI) of about 0.3 to 0.5 seconds at the worst-case fault current.
Class RK1 fuses are more current-limiting (lower peak let-through energy) than Class RK5; RK1 is preferred for arc-flash and component-withstand protection.
Last updated: August 2026
The IDMT Curve Equation
Quick Answer: For an IEC 60255-151 inverse definite minimum time curve, trip time t = TMS x k / ((I / Is)^alpha - 1) , where TMS is the time multiplier setting, Is is the pickup current, and k and alpha are curve-type constants.
An IDMT characteristic means trip time decreases as current increases, but flattens out at a minimum (definite) time once the current is many times pickup. That is the "inverse" and the "definite minimum" in the name. The three IEC curve families every NETA Level 2 candidate should memorize:
- Curve type k alpha Behavior
- Standard Inverse (SI) 0.14 0.02 Gentle slope; long times at low multiples, slow to flatten
- Very Inverse (VI) 13.5 1.0 Steeper; good for grading with fuses and long feeders
- Extremely Inverse (EI) 80 2.0 Very steep; closely matches fuse and transformer damage curves
- Long Time Inverse (LTI) 120 1.0 Earth-fault grading over long cable runs
IEEE C37.112-1996 defines equivalent Moderately, Very, and Extremely Inverse curves using a slightly different equation form (with A, B, and p parameters). Most modern numeric relays let you select either the IEC or the IEEE family.
Worked IDMT Calculations
Standard Inverse, pickup 100 A, TMS 0.2, fault 500 A (M = 5):
t = 0.2 x 0.14 / (5^0.02 - 1) = 0.028 / (1.0328 - 1) = 0.028 / 0.0328 = 0.854 s
Extremely Inverse, pickup 100 A, TMS 0.3, fault 1000 A (M = 10):
t = 0.3 x 80 / (10^2 - 1) = 24 / 99 = 0.242 s
These match the published IEC 60255-151 tables. If your injection test gives a time more than about 10 percent off the calculated value, suspect a wrong TMS, a CT ratio mismatch, or a saturated CT.
Reading a TCC Curve
A time-current characteristic (TCC) curve is plotted on log-log paper: current on the X-axis (log scale), trip time on the Y-axis (log scale) . A coordination study overlays every device curve in the chain so you can see, at a glance, which device trips first for any given fault current.
Reading a TCC:
Find the fault current on the X-axis (e.g., the maximum available fault at the downstream bus).
Move up to each device curve.
Read the trip time on the Y-axis for each device.
The downstream device must clear before the upstream device by at least the coordination time interval (CTI).
The CTI accounts for breaker interrupting time (3 to 5 cycles), relay overtravel, and a safety margin. The industry standard is 0.3 to 0.5 seconds ; 0.3 s is the tightest normally accepted, 0.4 s is common, 0.5 s is conservative.
Pickup vs. Time-Dial (TMS) Settings
The pickup (Is) shifts the curve left or right — raising pickup moves the curve right, so the relay operates at higher current. The time multiplier (TMS, or time dial TD on electromechanical relays) shifts the curve up or down without changing its shape. To grade two relays on the same curve family, keep the curve shape identical and increase the upstream TMS so its curve sits above the downstream curve by at least one CTI at the worst-case fault.
Pickup is normally set 1.05 to 1.3 times maximum load current so the relay does not trip on normal overload. The lower end (1.05) is for cables and transformers; the upper end (1.25 to 1.3) is typical for feeders with motor inrush.
RK1 vs. RK5 Fuse Links
Class R (rejection) fuses are rated 250 V or 600 V and come in two current-limiting subclasses:
RK5 — less current-limiting, time-delay. Cheaper, used where some let-through is tolerable.
RK1 — more current-limiting, lower peak let-through energy (lower I2t). Preferred for arc-flash reduction and protecting components with low short-time withstand.
On a TCC, the RK1 curve sits below and to the left of the RK5 curve at high currents — it clears faster and lets less energy through. When a specification calls for arc-flash mitigation or a lower incident energy at a panel, RK1 is usually required.
Worked Coordination Example
A 225 A main breaker with a 51 relay (pickup 270 A, TMS 0.5, Standard Inverse) feeds a 100 A feeder breaker with a 50/51 relay (pickup 120 A, TMS 0.3, Standard Inverse). A bolted fault of 4000 A occurs on the feeder.
- Feeder 51: M = 4000 / 120 = 33.3
- t_feeder = 0.3 x 0.14 / (33.3^0.02 - 1) = 0.042 / 0.0726 = 0.579 s
- Main 51: M = 4000 / 270 = 14.8
- t_main = 0.5 x 0.14 / (14.8^0.02 - 1) = 0.07 / 0.0554 = 1.264 s
CTI = 1.264 - 0.579 = 0.685 s — well above the 0.3 s minimum, so coordination is selective. The feeder trips first and isolates only the faulted segment; the main stays closed and serves the rest of the switchboard. If the curves overlapped at 4000 A, a fault on the feeder would trip the main and black out every feeder — a coordination failure your TCC review should catch before commissioning.