Study guide
11.5 As-Found / As-Left Documentation
NETA ETT Level II Certified Assistant Technician Exam
Track your progress as you read
Finished sections get a check mark.
1 Introduction & Exam Overview
1.1 About the NETA Level 2 Exam 1.2 The NETA Certification Hierarchy & Eligibility 1.3 Exam Administration, Scoring & Scheduling 1.4 Study Plan & How to Use This Guide
2 Chapter 1: Electrical Safety
2.1 NFPA 70E Approach Boundaries & Arc-Flash 2.2 PPE, Rubber Glove Classes & Hearing Protection 2.3 LOTO & the Electrically Safe Work Condition 2.4 Energized Work Permits & Live-Dead-Live 2.5 Temporary Protective Grounds & Induced Voltage 2.6 Hipot Testing Safety & Post-Hipot Grounding 2.7 Confined Space & General Electrical Safety 2.8 Risk Assessment, Job Briefings & the Hierarchy of Risk Controls 2.9 Codes & Standards: NFPA 70 Key Provisions and the ANSI/NETA Specifications
3 Chapter 2: Power Systems Theory
3.1 Three-Phase Power & Wye/Delta Relationships 3.2 Power Factor, Voltage Unbalance & Negative Sequence 3.3 Symmetrical Components & Fault-Current Paths 3.4 Grounding Systems & Impedance Grounding 3.5 Insulation Degradation & Dielectric Theory 3.6 Electrical Calculations, Units & Conversions
4 Chapter 3: Protection & Device Fundamentals
4.1 ANSI Device Numbers (27, 50, 51, 59, 86, 87) 4.2 IDMT/TCC Curves & Coordination 4.3 CT Theory: Ratio, Polarity, Burden, Accuracy & Knee Point 4.4 PT/VT Fundamentals & Insulation Coordination 4.5 Motor Circuits: FLA, PF Correction & Current Imbalance 4.6 One-Lines, Three-Lines, Schematics & Electrical Symbols 4.7 Short-Circuit & Coordination Studies
5 Chapter 4: Insulation Resistance Testing
5.1 Insulation Resistance: Test Voltages & IEEE 43 Minimums 5.2 Polarization Index (PI) & Dielectric Absorption Ratio (DAR) 5.3 Overpotential vs IR & Cable Hipot Basics 5.4 Guard Terminal, Doble Test Set & Thermography
6 Chapter 5: Withstand & Power-Factor Testing
6.1 DC Hipot: Step Voltage, Leakage Current & Pass Criteria 6.2 VLF Cable Testing & the DC/AC Voltage Conversion 6.3 Bushing Power Factor & Transformer PF Configurations 6.4 Oil Dielectric (ASTM) & DGA Sampling 6.5 Cable Fault Locating
7 Chapter 6: Transformer Testing
7.1 Transformer Turns Ratio (TTR) & Acceptance 7.2 Winding Resistance & Transformer Polarity 7.3 Transformer IR Configurations & Neutral-Ground Bond 7.4 SFRA, Sudden-Pressure Relay & Dry-Transformer ATS Tests
8 Chapter 7: CT, Relay & Motor Testing
8.1 CT Ratio, Polarity & Saturation Testing 8.2 Primary vs Secondary Injection & Relay Pickup 8.3 Three-Phase Relay Test Set, Phase-Angle Meter & Induction Disc 8.4 Motor Surge Test & Current Imbalance 8.5 Adjustable-Speed Drives, Reclosers, Sectionalizers & Fiber-Optic Cables
9 Chapter 8: Switchgear & Breaker Testing
9.1 Contact Resistance (Ductor) & Torque Verification 9.2 Vacuum Bottle Integrity & VCB Maintenance Tests 9.3 Post-Fault Breaker Maintenance & LV Trip-Unit Settings 9.4 Switchgear Bus IR, MCC Inspection & Bonding Jumpers 9.5 Switches, Circuit Switchers & Network Protectors 9.6 Metal-Enclosed Busways & Outdoor Bus Structures
10 Chapter 9: Grounding, Batteries & Protective Devices
10.1 Ground-Electrode Testing: Fall-of-Potential & Clamp-On 10.2 Battery Load Test (IEEE 450), VRLA Ohmic & Intervals 10.3 Fuses, GFCI & Zero-Sequence CT Grounding 10.4 Surge Arrester Acceptance & SPD Verification 10.5 Metering Devices & Regulating Apparatus 10.6 Capacitor Banks & Reactors: Inspection, Testing & Acceptance
11 Chapter 10: Systems & Commissioning
11.1 Automatic Transfer Switch Functional Testing 11.2 NFPA 110 Emergency System Load Tests 11.3 Switchgear Functional Testing & Feeder Trip Troubleshooting 11.4 Generator Paralleling & Emergency System Commissioning 11.5 As-Found / As-Left Documentation 11.6 Restoration & Handover Workflow
11.5 As-Found / As-Left Documentation
Key Takeaways Explain This Topic AI
As-found values document condition before any adjustment; as-left values document the final calibrated condition after the work is complete.
Both are required on every formal NETA acceptance and maintenance test report — one without the other is incomplete.
Together they form the trend baseline that lets the owner see drift, predict failure, and plan maintenance instead of reacting to it.
Every measured value must carry the instrument ID and calibration date — an out-of-calibration instrument invalidates the test.
A NETA test report is a legal record of the equipment's condition on that date; write it for the reader five years from now who has only the report.
Last updated: August 2026
Definitions
As-found values are the test results captured before any maintenance, adjustment, or repair is performed. As-left values are the results captured after the work is complete and the equipment is returned to service condition. The distinction is not bookkeeping: as-found documents the relay's condition before the technician made any adjustment, which is the only evidence of how the equipment had actually been performing in service; as-left confirms the final calibrated state that the system will now rely on. Both are required on formal NETA acceptance and maintenance reports.
Why Both Matter
As-found proves what was wrong. If a relay was picking up at 4.8 A when the setting called for 5.0 A, the as-found record is the evidence — it supports a misoperation analysis, justifies the corrective action, and protects the technician and the owner from later disputes about whether the equipment was actually out of spec before the work began. As-left proves what was corrected; the same relay now picks up at 5.0 A within tolerance. Without as-left, you cannot demonstrate that the equipment left the shop in spec.
Together they form the trend baseline. Year over year, the as-found/as-left pair lets the owner see drift, predict failure, and plan maintenance instead of reacting to it. If the as-found pickup drifts from 4.99 A to 4.95 A to 4.90 A over three maintenance cycles, the trend tells the owner the relay is heading out of tolerance and should be replaced before it misoperates — even though each individual as-found was still within ±5 percent.
Required Content of a NETA Test Record
A defensible as-found/as-left entry includes:
Equipment identification — asset tag, serial number, location, one-line reference.
Test performed — the name of the test (e.g., "instantaneous pickup", "insulation resistance 1 minute") and the standard section it maps to.
Instrument ID and calibration date — every measured value is traceable to a calibrated instrument; an instrument out of calibration invalidates the test.
Test setup — connections, applied voltage or current, range, whether primary or secondary injection.
Environmental conditions — temperature and humidity where they affect the result. Insulation resistance is temperature-corrected to 40 °C; humidity affects IR on large rotating machinery.
Measured values — the actual numbers, all three phases where applicable.
Acceptance criteria — the tolerance band or pass/fail threshold (e.g., "pick up within ±5 percent of setting").
Pass/fail verdict — explicit, not implied.
Technician signature and date — accountability.
NETA Test Report Format Essentials
NETA acceptance and maintenance test reports follow a consistent structure:
Project and owner identification.
Equipment under test, with serial numbers.
A table of test points with columns for as-found, as-left, and acceptance criteria.
Instrument IDs and calibration dates for every instrument used.
Environmental conditions (temperature, humidity) where they affect results.
A deficiencies and recommendations section.
Technician and reviewer signatures.
The one-line or three-line diagram is referenced, not redrawn. Deviations from the standard test plan are noted and justified. The report is the legal record of the equipment's condition on that date — write it for the reader five years from now who has only the report, not for yourself.
Traceability
Every value traces to a calibrated instrument; every instrument traces to a calibration standard; every setting traces to the coordination study or the manufacturer's instruction book; every deviation traces to an authorized engineering decision. A test report that says "IR = 1200 megohms" without an instrument ID is not traceable and is not a NETA-compliant record. As-found and as-left values must each carry their own instrument ID — using the same instrument for both is fine, but the record must show which instrument produced each value on each date. If an instrument is found out of calibration after a test, every value it produced during the out-of-cal period is suspect and must be flagged or reverified.
Worked Example — Trending a Drifting Overcurrent Relay
A feeder 51 relay is calibrated annually. The setting is 5.0 A pickup, ±5 percent acceptance band (4.75 to 5.25 A). Over four years the as-found pickup reads: Year 1 — 4.98 A; Year 2 — 4.95 A; Year 3 — 4.90 A; Year 4 — 4.82 A. Every as-found is still within the ±5 percent band, so a report that records only pass/fail would show "pass" four times and the drift would be invisible. The as-found/as-left pair, recorded to the digit, makes the trend visible: the relay is drifting toward the low end of the band at about 0.05 A per year and will cross 4.75 A sometime in Year 5 or 6. The owner can plan a relay replacement at the next scheduled outage instead of discovering a misoperation in service. This is the trending value that justifies recording the actual numbers, not just a checkmark.
Why As-Found/As-Left Is a NETA Hard Requirement
NETA acceptance and maintenance specifications require both as-found and as-left values on the test report because each answers a different question. As-found answers "what was the equipment doing before I touched it?" — the question that matters for misoperation analysis, warranty disputes, and owner liability. As-left answers "what is the equipment doing now that I have finished?" — the question that matters for return-to-service, future trending, and the next technician's baseline. A report with only as-left cannot prove the technician actually corrected anything; a report with only as-found cannot prove the equipment was returned to spec. Both are required, both must be traceable, and both must be recorded with the same rigor.
Common Documentation Errors
Recording a pass/fail verdict without the actual measured value — destroys the trend.
Recording as-left values without the matching as-found — cannot prove a correction was made.
Omitting the instrument ID on one of the two values — breaks traceability for that measurement.
Failing to temperature-correct IR before recording — produces a value that is not comparable year over year.
Backdating or batch-filling the record at the end of the day instead of in real time — invites missed steps and is not a defensible legal record.