Study guide
7.3 Areas, Volumes and Setting Out
SURCON Professional Examination — Surveyor Nigeria
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: The SURCON Professional Examination
1.1 The Surveyor's-Cadre Examination: Papers VI, VII and the Folio 1.2 Enrolment, Pupilage and the Certificate of Experience 1.3 Paper VII: The Professional Essay 1.4 Compiling the Survey Folio 1.5 The Oral Interview and Project Defence 1.6 Contemporary Professional Issues for the Essay and Interview
2 Chapter 2: The SURCON Act (Cap S18 LFN 2004)
2.1 The SURCON Act: Establishment, Membership and Functions 2.2 The Registrar and the Four-Part Register 2.3 Registration of Surveyors, Technologists and Technicians 2.4 Approved Qualifications, Supervision of Training and Appeals 2.5 Professional Discipline: the Disciplinary Committee and the Investigating Panel 2.6 Penalties, Offences and the Right to Practise
3 Chapter 3: Survey Co-ordination Act, Survey Laws and Regulations
3.1 The Survey Co-ordination Act 3.2 State Survey Laws: Plans, Deposit and Protection of Survey Marks 3.3 Survey Regulations: Field Survey Methods and the Standard of Survey 3.4 Survey Regulations: Demarcation and Beacon Construction 3.5 Survey Plans, Records and Information 3.6 Resurvey, Boundary Disputes and the Surveyor as Witness
4 Chapter 4: Land Law for Surveyors
4.1 The Land Use Act 1978: Vesting and Land Administration 4.2 Rights of Occupancy, Certificates of Occupancy and Deemed Grants 4.3 Alienation, Consent and the Nullity Rule 4.4 Revocation and Compensation under Sections 28 to 30 4.5 Land Registration Systems and LIS Integration 4.6 Minerals, Planning and Boundary Legislation
5 Chapter 5: Professional Practice, Ethics and Management
5.1 Professional Ethics and Client Relations 5.2 Charging for Survey Work, Records and the Surveyor's Signature 5.3 Establishing and Running a Survey Practice 5.4 Engagement, Liability, Quality Assurance and Safety
6 Chapter 6: Geodesy and Control
6.1 Minna Datum and Geodetic Reference Frames in Nigeria 6.2 Height Systems and Geoid Undulation 6.3 The Nigeria Transverse Mercator Projection and Grid Belts 6.4 GNSS Positioning, NIGNET and Control Networks 6.5 Geodetic Computations and Network Adjustments 6.6 Geodetic Astronomy and Azimuth Determination 6.7 Datum Transformation in Practice
7 Chapter 7: Computations, Land Surveying and LIS
7.1 Error Theory and Least Squares 7.2 Traverse Computation and Adjustment 7.3 Areas, Volumes and Setting Out 7.4 GIS Spatial Data Models and Topology 7.5 Land Information Systems and Spatial Databases 7.6 Web GIS, Cartography and Spatial Data Infrastructure
8 Chapter 8: Photogrammetry, Remote Sensing, Hydrography and Engineering
8.1 Fundamentals of Aerial Photogrammetry 8.2 UAV Photogrammetry and Structure from Motion 8.3 Satellite Remote Sensing and Image Interpretation 8.4 Image Processing, Classification and LiDAR 8.5 Sounding Systems and Hydrographic Equipment 8.6 Hydrographic Data Reductions and Tidal Datums 8.7 IHO S-44 Standards and Offshore Survey Practice 8.8 Engineering Route Surveying and Curve Geometry 8.9 Tunnelling, Mining Surveys and Deformation Monitoring
7.3 Areas, Volumes and Setting Out
Key Takeaways Explain This Topic AI
The coordinate cross-product formula gives the area of any straight-sided polygon directly from the corner coordinates, and is what regulation 5(E)(iv) requires.
The trapezoidal rule and Simpson's rule handle irregular boundaries from offsets; Simpson's rule requires an even number of equal intervals.
Earthwork volumes from cross-sections are computed by the end-area rule or, more accurately, by the prismoidal formula V = (L/6)(A1 + 4Am + A2).
Setting out reverses the survey: computed coordinates are converted to bearings and distances from a control station, and every set-out point must be independently checked.
Grid distances must be converted back to ground distances before setting out, by dividing by the combined scale factor rather than multiplying.
Last updated: August 2026
- 7.3 Areas, Volumes and Setting Out
- 1. Area from coordinates
For a closed polygon with vertices ( E 1 , N 1 ) , ( E 2 , N 2 ) , … , ( E n , N n ) (E_1,N_1), (E_2,N_2), \dots, (E_n,N_n) ( E 1 , N 1 ) , ( E 2 , N 2 ) , … , ( E n , N n ) taken in order: A = 1 2 ∣ ∑ i = 1 n ( E i N i + 1 − E i + 1 N i ) ∣ A = \frac{1}{2}\left|\sum_{i=1}^{n}\left(E_iN_{i+1} - E_{i+1}N_i\right)\right| A = 2 1 i = 1 ∑ n ( E i N i + 1 − E i + 1 N i )
closing the polygon with ( E n + 1 , N n + 1 ) = ( E 1 , N 1 ) (E_{n+1}, N_{n+1}) = (E_1, N_1) ( E n + 1 , N n + 1 ) = ( E 1 , N 1 ) . This is what regulation 5(E)(iv) means by computing the area "arithmetically from the coordinates of the corners".
Worked example. A four-sided parcel:
- Point E (m) N (m)
- A 1000.00 1000.00
- B 1040.00 1010.00
- C 1050.00 1055.00
D 1005.00 1048.00 ∑ ( E i N i + 1 − E i + 1 N i ) = ( 1000.00 × 1010.00 − 1040.00 × 1000.00 ) + ( 1040.00 × 1055.00 − 1050.00 × 1010.00 ) + ( 1050.00 × 1048.00 − 1005.00 × 1055.00 ) + ( 1005.00 × 1000.00 − 1000.00 × 1048.00 ) \begin{aligned}
- \sum(E_iN_{i+1} - E_{i+1}N_i) =\;& (1000.00 \times 1010.00 - 1040.00 \times 1000.00) \\
- &+ (1040.00 \times 1055.00 - 1050.00 \times 1010.00) \\
- &+ (1050.00 \times 1048.00 - 1005.00 \times 1055.00) \\
- &+ (1005.00 \times 1000.00 - 1000.00 \times 1048.00)
\end{aligned} ∑ ( E i N i + 1 − E i + 1 N i ) = ( 1000.00 × 1010.00 − 1040.00 × 1000.00 ) + ( 1040.00 × 1055.00 − 1050.00 × 1010.00 ) + ( 1050.00 × 1048.00 − 1005.00 × 1055.00 ) + ( 1005.00 × 1000.00 − 1000.00 × 1048.00 ) = ( 1,010,000 − 1,040,000 ) + ( 1,097,200 − 1,060,500 ) + ( 1,100,400 − 1,060,275 ) + ( 1,005,000 − 1,048,000 ) = (1{,}010{,}000 - 1{,}040{,}000) + (1{,}097{,}200 - 1{,}060{,}500) + (1{,}100{,}400 - 1{,}060{,}275) + (1{,}005{,}000 - 1{,}048{,}000) = ( 1 , 010 , 000 − 1 , 040 , 000 ) + ( 1 , 097 , 200 − 1 , 060 , 500 ) + ( 1 , 100 , 400 − 1 , 060 , 275 ) + ( 1 , 005 , 000 − 1 , 048 , 000 ) = − 30,000 + 36,700 + 40,125 − 43,000 = 3,825 = -30{,}000 + 36{,}700 + 40{,}125 - 43{,}000 = 3{,}825 = − 30 , 000 + 36 , 700 + 40 , 125 − 43 , 000 = 3 , 825 A = 1 2 × 3,825 = 1,912.50 m 2 A = \tfrac{1}{2} \times 3{,}825 = 1{,}912.50\text{ m}^2 A = 2 1 × 3 , 825 = 1 , 912.50 m 2
The parcel is under two acres, so under regulation 31(j) the area is stated in square measure to the second decimal : 1,912.50 m². Note that the sign of the summation depends on whether the vertices are taken clockwise or anticlockwise; take the absolute value.
A useful check: recompute with the vertices in reverse order. The magnitude must be identical.
2. Irregular boundaries from offsets
Regulation 9 requires that where a boundary is irregular - a stream, for instance - the traverse line follows approximately its course and offsets are taken at suitable points . The strip between the traverse line and the boundary is then computed separately and added to or subtracted from the polygon area.
Trapezoidal rule
For n n n offsets y 1 … y n y_1 \dots y_n y 1 … y n at equal intervals d d d : A = d [ y 1 + y n 2 + y 2 + y 3 + ⋯ + y n − 1 ] A = d\left[\frac{y_1 + y_n}{2} + y_2 + y_3 + \cdots + y_{n-1}\right] A = d [ 2 y 1 + y n + y 2 + y 3 + ⋯ + y n − 1 ]
This is regulation 5(E)(iv)'s "series of trapezoids".
Simpson's rule
More accurate where the boundary curves smoothly, because it fits parabolic arcs rather than straight chords: A = d 3 [ y 1 + y n + 4 ( y 2 + y 4 + ⋯ ) + 2 ( y 3 + y 5 + ⋯ ) ] A = \frac{d}{3}\left[y_1 + y_n + 4(y_2 + y_4 + \cdots) + 2(y_3 + y_5 + \cdots)\right] A = 3 d [ y 1 + y n + 4 ( y 2 + y 4 + ⋯ ) + 2 ( y 3 + y 5 + ⋯ ) ]
Simpson's rule requires an odd number of offsets - that is, an even number of intervals. With an even number of offsets, apply Simpson to all but the last strip and the trapezoidal rule to the remainder.
Worked example. Offsets at 10 m intervals: 3.2, 4.8, 6.1, 5.4, 3.9 m (five offsets, four intervals).
Trapezoidal: 10 [ 3.2 + 3.9 2 + 4.8 + 6.1 + 5.4 ] = 10 [ 3.55 + 16.3 ] = 198.5 10\left[\frac{3.2+3.9}{2} + 4.8 + 6.1 + 5.4\right] = 10[3.55 + 16.3] = 198.5 10 [ 2 3.2 + 3.9 + 4.8 + 6.1 + 5.4 ] = 10 [ 3.55 + 16.3 ] = 198.5 m²
Simpson: 10 3 [ 3.2 + 3.9 + 4 ( 4.8 + 5.4 ) + 2 ( 6.1 ) ] = 10 3 [ 7.1 + 40.8 + 12.2 ] = 10 3 ( 60.1 ) = 200.3 \frac{10}{3}\left[3.2 + 3.9 + 4(4.8+5.4) + 2(6.1)\right] = \frac{10}{3}[7.1 + 40.8 + 12.2] = \frac{10}{3}(60.1) = 200.3 3 10 [ 3.2 + 3.9 + 4 ( 4.8 + 5.4 ) + 2 ( 6.1 ) ] = 3 10 [ 7.1 + 40.8 + 12.2 ] = 3 10 ( 60.1 ) = 200.3 m²
The difference of 1.8 m² on 200 m² is about 0.9 per cent - small in absolute terms but systematic, and the trapezoidal rule always under estimates a convex boundary.
- 3. Volumes from cross-sections
- End-area rule
For two cross-sectional areas A 1 A_1 A 1 and A 2 A_2 A 2 a distance L L L apart: V = L 2 ( A 1 + A 2 ) V = \frac{L}{2}(A_1 + A_2) V = 2 L ( A 1 + A 2 )
Simple, and it overestimates for a solid whose section varies non-linearly (the usual case in cut and fill).
Prismoidal formula V = L 6 ( A 1 + 4 A m + A 2 ) V = \frac{L}{6}\left(A_1 + 4A_m + A_2\right) V = 6 L ( A 1 + 4 A m + A 2 )
where A m A_m A m is the area of the section at the mid-point - computed from the mid-point dimensions, not as the mean of A 1 A_1 A 1 and A 2 A_2 A 2 . Computing A m A_m A m as the average of the end areas reduces the prismoidal formula algebraically back to the end-area rule and defeats the purpose. This is the single most common error in earthwork computation.
Worked example. A 1 = 24.0 A_1 = 24.0 A 1 = 24.0 m², A 2 = 40.0 A_2 = 40.0 A 2 = 40.0 m², mid-section computed from mid-point dimensions as A m = 31.5 A_m = 31.5 A m = 31.5 m², L = 30 L = 30 L = 30 m.
End-area: V = 30 2 ( 24.0 + 40.0 ) = 15 × 64.0 = 960.0 V = \frac{30}{2}(24.0 + 40.0) = 15 \times 64.0 = 960.0 V = 2 30 ( 24.0 + 40.0 ) = 15 × 64.0 = 960.0 m³
Prismoidal: V = 30 6 ( 24.0 + 4 × 31.5 + 40.0 ) = 5 ( 24.0 + 126.0 + 40.0 ) = 5 × 190.0 = 950.0 V = \frac{30}{6}(24.0 + 4 \times 31.5 + 40.0) = 5(24.0 + 126.0 + 40.0) = 5 \times 190.0 = 950.0 V = 6 30 ( 24.0 + 4 × 31.5 + 40.0 ) = 5 ( 24.0 + 126.0 + 40.0 ) = 5 × 190.0 = 950.0 m³
The prismoidal correction of 10.0 m³ is about 1 per cent - which on a road project of many thousands of cubic metres is a commercially significant sum.
4. Sub-division of areas
A recurring practical problem: divide a parcel so that a specified area falls on one side of a line.
Line through a fixed point. Compute the area cut off by a trial line through the point, then rotate the line and interpolate. Because area varies smoothly with the rotation angle, two trials usually bracket the answer and a third converges it.
Line of given direction. Where the dividing line must be parallel to an existing boundary - a common planning requirement - the area cut off is a simple function of the perpendicular offset, and the offset can be solved directly for a triangle or trapezium and iterated for a general polygon.
In both cases, compute the coordinates of the new corner points and set them out and demarcate them . Regulation 15 requires demarcation prior to or simultaneously with the measurements determining position, and regulation 17 requires proof by actual measurements recorded in the field book where a beacon is placed in accordance with computed data.
5. Setting out
Setting out is the survey run backwards: instead of measuring what is there, you place what is designed.
The computation
From a control station S S S at ( E S , N S ) (E_S, N_S) ( E S , N S ) to a design point P P P at ( E P , N P ) (E_P, N_P) ( E P , N P ) : Δ E = E P − E S , Δ N = N P − N S \Delta E = E_P - E_S, \qquad \Delta N = N_P - N_S Δ E = E P − E S , Δ N = N P − N S Distance D = Δ E 2 + Δ N 2 \text{Distance } D = \sqrt{\Delta E^2 + \Delta N^2} Distance D = Δ E 2 + Δ N 2 Bearing θ = arctan ( Δ E Δ N ) (resolved into the correct quadrant by the signs of Δ E , Δ N ) \text{Bearing } \theta = \arctan\!\left(\frac{\Delta E}{\Delta N}\right) \quad\text{(resolved into the correct quadrant by the signs of } \Delta E, \Delta N) Bearing θ = arctan ( Δ N Δ E ) (resolved into the correct quadrant by the signs of Δ E , Δ N )
The quadrant is where errors happen. arctan \arctan arctan returns a value in a half-plane; the signs of Δ E \Delta E Δ E and Δ N \Delta N Δ N determine which of the four quadrants the bearing lies in, and a sign error puts the point 180 degrees out.
The scale-factor trap
Design coordinates are grid coordinates. The distance you set out on the ground is a ground distance. The reduction runs the other way: D g r o u n d = D g r i d k c o m b i n e d D_{ground} = \frac{D_{grid}}{k_{combined}} D g ro u n d = k co mbin e d D g r i d
Divide , do not multiply. With k c o m b i n e d ≈ 0.99979 k_{combined} \approx 0.99979 k co mbin e d ≈ 0.99979 (the worked case in section 6.3), a 2,000 m grid distance corresponds to 2,000.42 m on the ground. Applying the factor in the wrong direction produces an error of twice the correction - 84 cm on 2 km in that example.
Checks
No set-out point is finished until it has been checked independently :
- set out from a second control station and compare;
- check the distance between adjacent set-out points against the design distance; or
observe a check bearing to a third known station before and after the work.
A set-out point placed from one station by one observation, with no check, is exactly the kind of unverified value that regulation 17 refuses to accept in a survey - and it is the origin of most construction set-out disputes.