Study guide

13.1 Standby & Alarm Load Basis (24 h + 5/15 min)

NICET Fire Alarm Systems Level II Exam

Track your progress as you read

Finished sections get a check mark.

1 Exam Overview & Open-Book Strategy

1.1 Exam Facts, Eligibility & Logistics 1.2 Open-Book References & On-Screen Navigation 1.3 Certification Path & Performance Measures

2 Installation: Work Planning

2.1 Work Plans from Field Conditions 2.2 Drawings, Specs & Code Interpretation 2.3 Jobsite Safety & Trade Coordination

3 Installation: Circuits, Pathways & Survivability

3.1 Pathway Classes A, B, C, D, E, N & X 3.2 Survivability Pathway Levels 0–3 3.3 NEC Article 760, NPLFA/PLFA & Raceways 3.4 SLC Topology, T-Taps & Supervision

4 Installation: Equipment

4.1 Initiating Devices (Level II Applications) 4.2 Notification Appliances & NAC Design 4.3 Control/Monitor Modules & FACU Hardware 4.4 Voice EVACS Speakers & Intelligibility Basics

5 Installation: Commissioning

5.1 Acceptance Testing & Commissioning Sequence 5.2 Record of Completion & As-Builts 5.3 Functional Verification of Interfaces

6 Installation: System Interfaces

6.1 Elevator Recall Phase I & II 6.2 Shunt Trip & Heat Detector Placement 6.3 HVAC Shutdown & Duct Smoke Detectors 6.4 Suppression Interconnections (Waterflow, Tamper, Releasing, Clean Agent, Hood)

7 Maintenance: Periodic Testing

7.1 ITM Framework (NFPA 72 Chapter 14) 7.2 Device Test Methods & Frequencies 7.3 Interface, Waterflow & Tamper Tests 7.4 EVACS, Elevator & Special Function Tests

8 Maintenance: Impairments & Troubleshooting

8.1 Impairment Programs & AHJ Notification 8.2 Troubleshooting SLC, NAC & Power Faults 8.3 Corrective Actions & Retest Requirements

9 Maintenance: Documentation

9.1 Required Records & Retention 9.2 Inspection & Test Reports 9.3 Record Drawing Updates After Changes

10 Submittals: Shop Drawing Packages

10.1 Shop Drawing Package Contents 10.2 Cut Sheets, Calculations & Sequence of Operation 10.3 AHJ Submittal Expectations

11 Submittals: Site Survey

11.1 Occupancy, Construction & Fire Protection Features 11.2 Layout Constraints & Field Verification 11.3 Pathway Routing & Survivability Field Checks

12 Submittals: Basic Technical Drawings

12.1 Symbols, Risers & Floor Plans 12.2 Zone Schedules & Legends 12.3 Drawing Notes for Voltage Drop & Conduit Fill

13 Submittals: Power Supply & Loading

13.1 Standby & Alarm Load Basis (24 h + 5/15 min) 13.2 Battery Sizing with 20% Aging Derating 13.3 Voltage Drop Calculations 13.4 Conduit Fill & Wire Sizing (NEC Chapter 9)

14 Layout Knowledge: Supervising Station

14.1 Supervising Station Types (Chapter 26) 14.2 Transmission Paths & 90-Second Alarm Window 14.3 Protected Premises vs Supervising Station Roles

15 Management & Supervision

15.1 Coordinate Work Activities 15.2 Reporting Progress & Problems 15.3 Ethics & NICET Code of Conduct 15.4 Safety Leadership & Multi-Trade Coordination

13.1 Standby & Alarm Load Basis (24 h + 5/15 min)

Key Takeaways Explain This Topic AI

Primary power is the dedicated AC branch; secondary power (usually batteries) must carry the system through required standby time plus full-alarm time if AC fails.

Most protected-premises fire alarm systems size secondary power for 24 hours of standby load followed by 5 minutes of alarm load; EVACS and many voice/releasing applications use 24 hours plus 15 minutes of alarm.

Standby current is the sum of every device and power supply that draws while the system is quiet; alarm current is the sum under worst-case full-alarm notification (and other alarm-mode loads).

Convert milliamps to amps (÷ 1000) before multiplying by hours; battery capacity is in amp-hours (Ah), not raw milliamps.

Submittal battery worksheets list a device-by-device (or circuit) inventory with manufacturer current draws—guessing loads or omitting NAC alarm current fails Level II documentation and the exam.

Last updated: August 2026

13.1 Standby & Alarm Load Basis (24 h + 5/15 min)

Quick Answer: Size secondary power from two currents and two times: standby current × 24 hours , plus alarm current × alarm duration . Alarm duration is 5 minutes for most protected-premises systems and 15 minutes for emergency voice/alarm communications systems (EVACS) and many voice/releasing applications. Convert mA to A before multiplying. Domain 2.3.4 (power supply and loading calculations) tests this inventory math—not vague “put in a big battery.”

Chapter 10 put battery calculations on the shop-drawing package list. Chapter 12 locked drawing notes for voltage drop and fill. This chapter is the numeric engine : load basis (13.1), aging derating and bank selection (13.2), voltage drop (13.3), and conduit fill (13.4). On NICET Fire Alarm Systems Level II, wrong duration (5 vs 15 minutes) and botched unit conversion are classic traps.

Primary vs Secondary Power

Supply Role Typical form

Primary (main) Normal operating power Dedicated AC branch circuit to the control unit / power supplies; overcurrent device identified as fire-alarm circuit

Secondary (standby) Keeps the system alive when primary fails Storage batteries (often sealed lead-acid), sometimes engine-driven generators where permitted

When AC is present, the charger maintains the batteries and the system runs from primary. When AC fails, the system must transfer to secondary without losing required functions , and the secondary supply must be sized for the required standby period plus the required alarm period that follows.

Level II submittal work documents what the secondary must support , not only that “batteries are provided.” AHJs and plan reviewers expect a worksheet tied to the device schedule and cut sheets.

What “Standby Load” Means

Standby current (also called quiescent or supervisory current) is the continuous current drawn while the system is normal: monitoring initiating devices, supervising pathways, powering the control unit logic, remote annunciators, network cards, and any other loads that stay on before an alarm.

Build a standby current inventory :

Control unit base (main board, display, network, dialer/communicator as applicable).

Every initiating device and module on the SLC (or conventional zone loads).

Remote power supplies and booster panels in standby (including their own electronics).

Annunciators, printers, and other continuous accessories on battery-backed power.

Any continuously energized auxiliary loads the secondary is required to support.

Use manufacturer data at the system voltage (for example 24 VDC). Do not invent milliamp values. If a device draws different currents in different modes, use the standby-mode figure for the standby column.

Exam discipline: Notification appliances usually draw near-zero or negligible current in standby if they are silent and unlit. Their big draw belongs in the alarm column when the NAC energizes them.

What “Alarm Load” Means

Alarm current is the current under the design alarm condition used for secondary-power sizing—typically all notification appliances required to operate on battery-backed power, plus control-unit alarm-mode current, plus initiating/module currents that still apply, plus any other loads that run in alarm (door holders released may drop off; amplifiers and speakers on EVACS surge).

Build an alarm current inventory :

Control unit in alarm (often higher than standby).

Initiating devices/modules still powered.

Full notification load on each battery-backed NAC or amplifier channel (sum appliance currents from cut sheets at the candela/setting used).

Voice amplifiers, digital message repeaters, and speaker circuits for EVACS.

Releasing, fan-control, or other alarm-mode outputs if the secondary must power them for the alarm period.

If a remote NAC power supply has its own batteries, size that supply’s secondary separately from the FACU battery—but the load basis method is the same : standby + alarm with the correct duration.

Required Durations (Know Cold)

  • System type (typical Level II framing) Standby time Alarm time after standby
  • Standard protected-premises fire alarm (non-voice) 24 hours 5 minutes
  • EVACS / emergency voice and many voice-alarm applications 24 hours 15 minutes

Many releasing / special systems (confirm adopted NFPA 72 edition and listing) Often 24 hours Often 15 minutes (do not default to 5 without checking)

These numbers are the load-basis times used in secondary-supply calculations for exam and submittal work. Always confirm the adopted NFPA 72 edition and any special system chapter requirements for the occupancy—Level II is open-book, but you must know where the 5-minute vs 15-minute split lives and that voice systems are not the 5-minute default .

Trap: Using 5 minutes for a voice-evac system understates alarm amp-hours and produces an undersized battery. Using 15 minutes for a plain horn/strobe protected-premises system oversizes (safer but wrong if the question asks for the required basis).

Unit Conversion: mA → A → Ah

Battery capacity is in amp-hours (Ah) .

Sum currents in mA if that is how the cut sheets read.

Convert: I (A) = I (mA) ÷ 1000 .

Multiply by time in hours :

  • Standby Ah = I_standby (A) × 24
  • Alarm Ah = I_alarm (A) × ( 5/60 ) for 5 minutes, or × ( 15/60 = 0.25 ) for 15 minutes

5 minutes = 5/60 = 1/12 hour ≈ 0.0833 h.

15 minutes = 0.25 h.

Never multiply milliamp totals by 24 and call the result “Ah” without dividing by 1000. That error is off by a factor of one thousand.

Preliminary load Ah (before aging derating in 13.2):

Calculated Ah = Standby Ah + Alarm Ah

Section 13.2 multiplies that total by 1.20 (20% aging). Do not skip straight to catalog battery size without both steps unless the question already baked them in.

Worked Example — Device Table (Protected Premises, 5 min Alarm)

A small addressable protected-premises system (no EVACS) is powered from a 24 V control unit with onboard NAC capacity. Manufacturer currents (illustrative for method):

  • Load item Qty Standby each (mA) Alarm each (mA) Standby total (mA) Alarm total (mA)
  • FACU (main) 1 180 250 180 250
  • Addressable smoke 40 0.5 0.5 20 20
  • Manual stations 8 0.5 0.5 4 4
  • Monitor modules 6 0.5 0.5 3 3
  • Control modules 4 0.5 0.5 2 2
  • Horn/strobe (NAC) 18 0 110 0 1980
  • Strobe only (NAC) 12 0 55 0 660
  • Column totals 209 mA 2919 mA

Convert:

  • I_standby = 209 mA ÷ 1000 = 0.209 A
  • I_alarm = 2919 mA ÷ 1000 = 2.919 A
  • Standby Ah = 0.209 A × 24 h = 5.016 Ah
  • Alarm Ah (5 min) = 2.919 A × (5/60) h = 2.919 × 0.08333 ≈ 0.243 Ah
  • Calculated load Ah = 5.016 + 0.243 = 5.259 Ah
  • (Section 13.2 will apply × 1.20 → about 6.31 Ah required before selecting the next standard battery size.)
  • Same Loads as EVACS (15 min Alarm) — Compare

If the same currents applied to a voice system requiring 15 minutes of alarm:

  • Alarm Ah = 2.919 × 0.25 = 0.730 Ah
  • Calculated load Ah = 5.016 + 0.730 = 5.746 Ah
  • (After 20% in 13.2 ≈ 6.90 Ah .)

The standby term dominates on many systems; the alarm duration still moves the final size and is a favorite exam differentiator.

Inventory Quality Checks

Before you submit or answer:

Every NAC appliance on battery-backed power appears in the alarm column at the candela/setting used on the drawings.

Remote supplies are either included or calculated as separate secondary systems—never double-counted and never forgotten.

Communicators, cellular, network cards are on the correct column (usually continuous standby + any alarm-mode surge if documented).

EOL resistors and supervision are not a substitute for appliance alarm current.

Currents match cut sheets cited in the package (Chapter 10.2), not memory from a different project.

Level II Role

You assemble the load basis from schedules, risers, and product data; you verify someone else’s spreadsheet against the same sources; and you flag when the drawing set shows EVACS speakers but the battery sheet used 5 minutes. You do not invent sealed-engineer authority—you make the math and basis traceable .

Bridge to 13.2

5.259 Ah (this example, 5 min) is not yet the battery you order. Next: apply the 20% aging factor , consider temperature and manufacturer minimums, and select series/parallel bank configuration for system voltage.