Study guide

14.3 Five-Location Obstruction Examination, Evidence, and Required Follow-Up

NICET Inspection and Testing of Water-Based Systems Level II Exam

Track your progress as you read

Finished sections get a check mark.

1 Chapter 1: Personal Safety, PPE & Equipment

1.1 PPE Requirements & Maintenance 1.2 Tool Safety, Electrical Safety & Stored-Energy Hazards in Charged Piping 1.3 Environmental Hazards, Hazardous Materials & Worksite Illumination

2 Chapter 2: High-Hazard Safety: LOTO, Confined Space & Working at Heights

2.1 Lockout/Tagout (LOTO) Procedures 2.2 Permit-Required Confined Spaces & Atmospheric Testing 2.3 Ladder Safety, Scaffolding & Aerial Lifts

3 Chapter 3: Customer Coordination & Pre-Inspection Scope

3.1 Pre-Inspection Review, Scope of Work & Scheduling 3.2 Stakeholder Notifications: Owners, Designated Representatives & Facility Operations 3.3 Safety Impairment Procedures & Site-Specific Hazard Protocols

4 Chapter 4: Stakeholder Notification, Reporting & Impairment Procedures

4.1 Central Station Alarm Monitoring & AHJ Notifications Before/After Testing 4.2 NFPA 25 Chapter 15 Impairment Program: Coordinator, Tagging & Fire Watch Rules 4.3 ITM Documentation, Record Retention & Delivering Deficiency Reports

5 Chapter 5: Wet Sprinkler Systems ITM

5.1 Gauges, Control Valves & Visual Inspection Frequencies 5.2 Waterflow Alarm Devices: Vane-Type Paddle Switches & Mechanical Gongs 5.3 Main Drain Test Procedure & the 10% Pressure Drop Rule 5.4 Sprinkler Head Inspection, Clearance & Laboratory Testing Age Triggers

6 Chapter 6: Wet System Specialized Components: Antifreeze & Air Vents

6.1 Antifreeze Systems: Types, Listed Solutions, Backflow Isolation & Testing Procedures 6.2 Antifreeze Solution Measurement: Refractometer / Hydrometer & Freeze-Point Verification 6.3 Automatic Air Vents & Nitrogen Inerting in Wet Systems

7 Chapter 7: Dry Pipe Systems & Specialized Equipment

7.1 Dry Pipe Valve Principles, Differential Ratios & Priming Water Level 7.2 Quick-Opening Devices (QODs): Accelerators & Exhausters Inspection and Testing 7.3 Dedicated Air Compressors, Automatic Air Maintenance Devices (AMDs) & Regulators 7.4 Nitrogen Generation Systems & Gas Separation Membranes

8 Chapter 8: Dry System Testing & Operational Verification

8.1 Annual Partial Trip Test vs. Three-Year Full Flow Trip Test 8.2 Three-Year Air-Leakage Options and Annual Air-Pressure Supervisory Testing 8.3 Dry Pipe Auxiliary Drains (Drum Drips) & Condensate Management in Freezing Weather

9 Chapter 9: Standpipe Systems & Deficiency Classification

9.1 Standpipe Classes (I, II, III), System Types & Component Visual Inspections 9.2 Standpipe 5-Year Hydrostatic & Flow Testing Requirements (500 gpm / 250 gpm) 9.3 Hose Valves, Pressure Regulating Devices (PRDs/PRVs) & FDC Inspection and Testing

10 Chapter 10: Fire Pump Systems & Drivers

10.1 Fire Pump Types (Horizontal Split Case, Vertical Turbine, End Suction) & System Arrangements 10.2 Fire Pump Drivers: Electric Motors, Diesel Engines & Controller Components 10.3 Pressure-Maintenance Pumps: Purpose, Capacity, and Coordinated Settings

11 Chapter 11: Fire Pump Inspection, Testing & Maintenance

11.1 Weekly Diesel (30-Minute) & Weekly/Monthly Electric (10-Minute) No-Flow (Churn) Tests 11.2 Annual Fire Pump Flow Test: Churn (0%), 100% Rated Flow & 150% Peak Flow 11.3 Pump Performance Evaluation: Net/Gross Curves and the Complete Acceptance Criteria 11.4 Diesel Support-System Maintenance and Electric-Pump Alternate Power

12 Chapter 12: Private Fire Service Mains & Hydrants

12.1 Underground Piping ITM & 5-Year Underground Flow Testing 12.2 Fire Hydrant Inspection, Lubrication & Annual Drainage Operational Tests 12.3 NFPA 291 Water Flow Testing: Layout, Pitot Readings & Flow Math 12.4 Hydrant Classification, Color Coding & Available Flow Extrapolation at 20 psi Residual

13 Chapter 13: Water Storage Tanks

13.1 Tank Types (Suction, Elevated, Pressure) & Component Overview 13.2 Inspection Frequencies: Water Level, Temperature (Min 40°F), Exterior & Interior 13.3 Tank Heating Systems, Low-Water Alarms, Vents, Overflow & Anti-Vortex Plates

14 Chapter 14: Internal Pipe Assessment & Obstruction Triggers

14.1 NFPA 25 Five-Year Internal Piping Assessment Procedures & Non-Destructive Testing 14.2 The Sixteen NFPA 25 (2023) Obstruction-Investigation Triggers 14.3 Five-Location Obstruction Examination, Evidence, and Required Follow-Up

15 Chapter 15: Flushing Methods, Contaminants & Deficiency Classification

15.1 Obstruction Materials: Corrosion, MIC Indicators, Scale, Ice, and Foreign Debris 15.2 Hydraulic Flushing: Program Scope, Velocity Calculations, and Completion Evidence 15.3 Specialist Cleaning Methods: Suitability, Safety Controls, and Restoration 15.4 Classifying Findings: Impairments vs. Critical Deficiencies vs. Noncritical Deficiencies

14.3 Five-Location Obstruction Examination, Evidence, and Required Follow-Up

Key Takeaways Explain This Topic AI

The 2023 investigation requires five minimum locations, with specified remote cross-main, branch, and low-point-drain locations.

Extend the examination based on evidence; minimum locations do not prove every unexamined segment clear.

Test tubercules/slime for MIC indications using the qualified laboratory method, without improvised chemical or odor tests.

Sufficient obstructive material requires a complete flushing program by qualified personnel, followed by verified restoration.

Last updated: October 2026

Define the investigation scope from the actual edition

An obstruction investigation follows evidence or conditions requiring examination beyond a routine assessment. NFPA 25 (2023), 14.3.2.2, identifies five minimum examination locations . The older four-category list of valve, riser, cross main, and branch line is not the current examination-reference list. Keep the investigation separate from the more flexible internal-assessment method under 14.2.

The five locations are the system or water-control valve where provided; the most remote end of the remote cross main; a branch line near the most remote line at its cross-main connection; that branch-line area at its remote end; and branch piping directly connected to the most remote low-point drain. Use the actual drawings and field arrangement to identify these locations. A convenient opening beside the riser is not automatically equivalent to a remote location.

  • Minimum location Evidence sought
  • System/water-control valve where provided Introduced material, deposits, and component condition
  • Remote end of remote cross main Material transported through or retained in the distribution main
  • Near-remote branch at cross-main connection Condition where water enters smaller distribution piping
  • Near-remote branch at its end Deposits or debris at the terminal portion
  • Branch connected to remote low-point drain Material accumulating near a drainage low point

These are minimum points, not a guarantee that five clean photographs establish every unexamined segment is clear. Extend the examination as needed to determine the extent and severity indicated by the findings. The exact access method and any permissible alternative nondestructive examination must be capable of addressing the condition and documented limitations.

Prepare for opening and evidence collection

Review the triggering event, previous findings, supply history, system drawings, and the operating configuration. Identify the protection affected by isolation and coordinate the impairment with the responsible owner/coordinator. Prepare safe drainage, access, replacement components, appropriate tools, and a restoration plan before dismantling. Confirm stored pressure is relieved through the approved method. Do not remove a cap simply because a distant gauge reads zero.

Control foreign-material entry during the investigation. Keep clean components and tools protected, use suitable temporary closures, and account for loose parts. Photograph each location before disturbing deposits where feasible. Record material distribution and appearance, approximate size, looseness, and whether it can migrate toward smaller openings. A ruler or other safe scale reference helps interpretation; a photograph without system/location identification is weak evidence.

Interpret deposits without inventing acceptance limits

NFPA 25 does not provide a universal deposit-thickness or percentage-area allowance that clears every pipe. The same fragment that is minor in a large main can obstruct a sprinkler orifice. Evaluate the amount, mobility, size, location, and connected openings. Do not scrape a deposit away and then report the original condition as clear merely because the final photograph looks clean.

Tubercules or slime found during investigation must be tested for indications of MIC. Arrange qualified analysis and follow the receiving laboratory's instructions for sampling, containers, preservation, and transport. There is no single mandatory twenty-four-hour/chilled/air-free protocol applying to every possible analysis. Do not add acid, bleach, or other chemicals to an unknown deposit to identify it by smell. Odor and color alone are not a definitive microbiological diagnosis.

When the finding requires complete flushing

Under 14.3.3, if the investigation indicates sufficient material to obstruct pipe or sprinklers, qualified personnel must conduct a complete flushing program. Merely expanding the investigation is not the complete required response. Establish the affected scope and suitable corrective method, manage protection, and coordinate the actual flushing or other necessary repairs. A brief main-drain run does not prove that every affected branch has been cleaned.

If the condition remains uncorrected or can continue to cause obstruction despite prior flushing, 14.3.2.1 requires the applicable five-year examination. Correcting the current blockage without controlling its source can allow recurrence. Review intake protection, supply repairs, corrosion conditions, drainage, and any design-required nitrogen supply. Preserve the ongoing examination and maintenance requirements in the owner's records.

Verify repair and restoration

Reassemble opened locations with appropriate components and instructions, complete required post-work tests, and check leaks and valve positions. Restore normal water/gas supply, QOD and other accessories, alarms, and monitoring as applicable. Remove impairment controls only after restoration has actually been confirmed. Record any remaining uncertainty as an open limitation requiring resolution rather than declaring a blanket pass.

The final report should connect trigger, locations, method, observations, laboratory findings, affected extent, correction, retest, and restored status. Identify who received notice and what follow-up remains. That chain of evidence makes the investigation useful for both immediate protection and future comparison.

Source checked October 19, 2026: NFPA 25 (2023), 14.3.2 through 14.3.4 and corresponding Annex A explanations.