Study guide
4.4 Setting Field Monuments, Rebar, Caps, Stakes, and Tacks
NSPS Certified Survey Technician Level I Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Survey Types & Historical Development
1.1 CST Certification & Survey Licensing Distinction 1.2 Boundary, Cadastral, and Land Surveys 1.3 Topographic, Hydrographic, and Route Surveys 1.4 Construction, As-Built, and Industrial Alignment Surveys 1.5 Historical Surveying Units, Instruments, and Practices
2 Chapter 2: Tripods, Instruments & Field Setup
2.1 Tripod Setup, Centering, Plumbing, and Optical Plummets 2.2 Instrument Leveling, Bubble Vials, and Electronic Tilt Sensors 2.3 Equipment Care, Cleaning, Storage, and Transport Safety
3 Chapter 3: Taping, Leveling & Distance Measurement
3.1 Steel Taping, Tension, Temperature, and Slope Corrections 3.2 Differential Leveling Equipment, Rods, Targets, and Rod Reading 3.3 Total Station Operations, Prism Constants, and EDM Basics 3.4 Data Collectors, Field Software Jobs, and File Management
4 Chapter 4: Field Operations, Notes & Communication
4.1 Field Note Bookkeeping, Standard Layout, and Hand-Drawn Sketches 4.2 Field Radio Procedures, Hand Signals, and Crew Communications 4.3 Line Clearing, Brush Removal, and Obstacle Clearance Safety 4.4 Setting Field Monuments, Rebar, Caps, Stakes, and Tacks
5 Chapter 5: Survey Control Networks & Monuments
5.1 Horizontal & Vertical Control Principles and Monument Types 5.2 Benchmarks, Datums (NAVD88, NAD83), and Field Verification Checks
6 Chapter 6: Basic Surveying Mathematics & Unit Conversions
6.1 Linear & Angular Unit Conversions (Feet, Chains, Links, Acres, DMS, Radians) 6.2 Right Triangle Trigonometry and Geometry in Surveying 6.3 Approved Calculator Operations & Memory Management (Casio fx-115/991, HP 35s, TI-36X)
7 Chapter 7: Leveling & Distance Computations
7.1 Differential Leveling Computations (HI, Backsight, Foresight, Page Checks) 7.2 Slope Distance Reductions and Horizontal/Vertical Components 7.3 Elevation, Grade Percent, and Stationing Calculations
8 Chapter 8: Coordinate Geometry & Area Calculations
8.1 Bearings, Azimuths, and Angular Conversions 8.2 Rectangular Coordinates (Northings/Eastings) and Departure/Latitude Basics 8.3 Area Calculations (Triangles, Trapezoids, Rectangles, and Simple Polygons)
9 Chapter 9: Plan Reading, Scale & Topography
9.1 Map Types, Plan Sheets, Title Blocks, and Revision Blocks 9.2 Scale Conversions, Graphical Scales, and Dimension Verification 9.3 Contour Lines, Spot Elevations, Interpolation, and Profiles
10 Chapter 10: CAD & Drafting Conventions
10.1 CAD Layers, Line Types, Symbols, and Legend Standards 10.2 Drafting Standards, Text Styles, and Title Block Preparation 10.3 Coordinate Systems, Grid vs. Ground, and Plan Orientation
11 Chapter 11: Field Safety, Hazards & First Aid
11.1 Personal Protective Equipment (PPE) & Construction Site Safety 11.2 Traffic Control, Flaggers, and Roadway Work Zone Safety (MUTCD) 11.3 Environmental Hazards: Heat Stress, Cold Exposure, Poisonous Plants, and Animals 11.4 Electrical Hazards, Overhead Power Lines, and Excavation Safety 11.5 Basic First Aid, CPR Principles, and Emergency Response Protocols
4.4 Setting Field Monuments, Rebar, Caps, Stakes, and Tacks
Key Takeaways Explain This Topic AI
Boundary monuments must possess physical permanence and legal identification; standard boundary markers consist of steel rebar (minimum 1/2" or 5/8" diameter) topped with stamped plastic or metal caps.
Wood hubs and tacks establish precise 3D point control: the tack defines horizontal position, while the top surface of the wood hub establishes vertical elevation.
Guard stakes (lath) protect hubs/monuments and display essential metadata: stationing, offset distances, cut/fill values, benchmark elevations, and point numbers.
Monuments installed in northern climates must be driven below local frost depth or set securely to resist frost heave displacement.
Driving stakes cleanly requires proper tool selection (3-4 lb hand sledge, slide driver), plumb alignment, and solid seating in undisturbed subsoil.
Last updated: July 2026
4.4 Setting Field Monuments, Rebar, Caps, Stakes, and Tacks
Field Rule: A survey calculation is only as accurate as the physical marker set in the ground. If a hub is driven loosely in soft topsoil or a boundary rebar is left uncapped, the survey fails both physical and legal standards.
The ultimate physical outcome of most field operations is setting physical markers in the ground. Boundary monuments define legal land ownership corners, control monuments establish permanent spatial reference frameworks, and construction stakes guide earthwork contractors, utility installers, and building builders. Setting markers requires understanding material permanence, state administrative capping laws, stake lettering standards, and soil mechanics.
1. Permanent and Semi-Permanent Monument Types
Survey monuments are categorized by their intended longevity and legal function:
Monument Type Physical Dimensions Primary Application Legal & Technical Requirements
Steel Rebar & Cap #4 (1/2") or #5 (5/8") rebar, 18" to 30" length Standard boundary corner marker Must be topped with a durable plastic or metal cap stamped with the Professional Land Surveyor's (PLS) license number.
Iron Pipe 3/4" to 1" inside diameter galvanized pipe, 18" to 36" length Historical & rural boundary corners Open top or capped; offers excellent magnetic detection depth in dense soils.
Concrete Monument Precast or cast-in-place concrete post (6"x6" x 36") with brass cap Primary control network, municipal boundaries, highway rights-of-way Set flush or slightly below ground; high permanence; highly resistant to disturbance.
Wood Hub & Tack 2"x2" square wood stake, 6" to 18" length with central metal tack Construction layout control point, total station setup point Wood hub establishes vertical elevation grade; central tack defines precise 2D horizontal coordinates.
Masonry Nail (Mag/PK Nail) Hardened steel nail driven into asphalt or concrete pavement Temporary control point, offset layout point in paved roads High magnetic signature for quick retrieval; driven flush with pavement surface.
2. Regulatory Capping Requirements
Under state land surveying administrative codes, setting an uncapped iron rod or pipe as a boundary corner is a regulatory violation. Capping regulations enforce three standards:
Identification: Caps must be permanently stamped with the Licensed Professional Land Surveyor's (PLS) license number or firm registration ID.
Durability: Caps must be constructed of weather-resistant plastic, aluminum, or brass press-fitted onto the steel rebar top.
Notice to Public: A stamped cap provides immediate public notice of who performed the survey, enabling title examiners, property owners, and adjacent surveyors to contact the surveyor of record.
3. Wood Hubs, Tacks, and Guard Stakes (Lath) Layout Standards
In construction layout and traverse control, survey crews utilize a two-part marking system: the Wood Hub (the physical point) and the Guard Stake (the informational signpost). [GUARD STAKE / LATH] [WOOD HUB & TACK]
- +-------------------+ +-----------------+
- | STA 12+50.00 | | |
- | OFF 15.00' RT | | ( TACK ) |
- | CUT 2.45' | | . | <-- 2D POINT
- | PT #104 | | [WOOD HUB] | <-- ELEVATION
- +-------------------+ +-----------------+
- | |
- | (Driven at angle) | (Driven flush)
- v v
- ======================================================================== GROUND
- Wood Hub and Tack Setup
Wood Hub: A 2x2-inch square wooden stake driven firmly into the ground until its top face is flush or 1 inch above ground level.
Surveyor's Tack: A small metal tack driven into the top face of the hub. The center of the tack head defines the exact horizontal coordinate ( N , E N, E N , E ). The top wood surface immediately adjacent to the tack serves as the exact vertical elevation reference.
Guard Stake (Lath) Lettering Standards
A flat wooden lath (1x2 inches, 36 to 48 inches long) is driven at a slight angle beside the hub to protect it from construction equipment and display critical metadata using waterproof felt markers:
Front Face (Facing the Roadway or Hub):
Stationing: E.g., STA 12+50.00 (distance along alignment baseline).
Offset Distance & Direction: E.g., OFF 15.00' RT (stake is 15 feet right of centerline).
Point Number: E.g., PT #104 .
Back Face (Facing Away):
Cut or Fill Designation: E.g., C-2.45' (Cut 2.45 feet down to grade) or F-1.12' (Fill 1.12 feet up to grade).
Grade Elevation: E.g., GRD ELEV = 542.18' .
Benchmark Info: E.g., BM ELEV = 104.52' NAVD88 .
4. Stake Driving Mechanics and Soil Conditions
Driving stakes cleanly requires proper tools and physical techniques:
Tool Selection: Use a 3 to 4 lb single-hand engineering sledgehammer for wood hubs and short rebar. Use an 8 lb double-face sledgehammer or slide-hammer stake driver for long boundary rebar and tall lath.
Plumb Orientation: Hold the stake perfectly plumb (vertical) before delivering initial light setting strikes. Striking an un-plumb stake causes it to bend, split, or wander horizontally.
Solid Seating: Stakes must be driven into firm, undisturbed subsoil. If topsoil is loose or muddy, clear surface organic layers before driving the hub.
5. Frost Depth Considerations and Monument Stability
In northern regions subject to freezing winter temperatures, soil water freezes and expands, generating upward displacement forces known as frost heave :
Mechanism of Frost Heave: Freezing moisture attaches to shallow monument walls, lifting the monument upward and tilting it out of plumb during seasonal freeze-thaw cycles.
Prevention Protocols: Permanent boundary and control monuments must be driven or set below local frost depth (often 36 to 48 inches deep in northern states). Concrete monuments should feature smooth, tapered, or bell-bottom bases below the frost line so freezing soil slips along the upper shaft without gripping the monument.