3.4 Data Collectors, Field Software Jobs, and File Management
NSPS Certified Survey Technician Level I Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Survey Types & Historical Development
1.1 CST Certification & Survey Licensing Distinction 1.2 Boundary, Cadastral, and Land Surveys 1.3 Topographic, Hydrographic, and Route Surveys 1.4 Construction, As-Built, and Industrial Alignment Surveys 1.5 Historical Surveying Units, Instruments, and Practices
2 Chapter 2: Tripods, Instruments & Field Setup
2.1 Tripod Setup, Centering, Plumbing, and Optical Plummets 2.2 Instrument Leveling, Bubble Vials, and Electronic Tilt Sensors 2.3 Equipment Care, Cleaning, Storage, and Transport Safety
3 Chapter 3: Taping, Leveling & Distance Measurement
3.1 Steel Taping, Tension, Temperature, and Slope Corrections 3.2 Differential Leveling Equipment, Rods, Targets, and Rod Reading 3.3 Total Station Operations, Prism Constants, and EDM Basics 3.4 Data Collectors, Field Software Jobs, and File Management
4 Chapter 4: Field Operations, Notes & Communication
4.1 Field Note Bookkeeping, Standard Layout, and Hand-Drawn Sketches 4.2 Field Radio Procedures, Hand Signals, and Crew Communications 4.3 Line Clearing, Brush Removal, and Obstacle Clearance Safety 4.4 Setting Field Monuments, Rebar, Caps, Stakes, and Tacks
5 Chapter 5: Survey Control Networks & Monuments
5.1 Horizontal & Vertical Control Principles and Monument Types 5.2 Benchmarks, Datums (NAVD88, NAD83), and Field Verification Checks
6 Chapter 6: Basic Surveying Mathematics & Unit Conversions
6.1 Linear & Angular Unit Conversions (Feet, Chains, Links, Acres, DMS, Radians) 6.2 Right Triangle Trigonometry and Geometry in Surveying 6.3 Approved Calculator Operations & Memory Management (Casio fx-115/991, HP 35s, TI-36X)
7 Chapter 7: Leveling & Distance Computations
7.1 Differential Leveling Computations (HI, Backsight, Foresight, Page Checks) 7.2 Slope Distance Reductions and Horizontal/Vertical Components 7.3 Elevation, Grade Percent, and Stationing Calculations
8 Chapter 8: Coordinate Geometry & Area Calculations
8.1 Bearings, Azimuths, and Angular Conversions 8.2 Rectangular Coordinates (Northings/Eastings) and Departure/Latitude Basics 8.3 Area Calculations (Triangles, Trapezoids, Rectangles, and Simple Polygons)
9 Chapter 9: Plan Reading, Scale & Topography
9.1 Map Types, Plan Sheets, Title Blocks, and Revision Blocks 9.2 Scale Conversions, Graphical Scales, and Dimension Verification 9.3 Contour Lines, Spot Elevations, Interpolation, and Profiles
10 Chapter 10: CAD & Drafting Conventions
10.1 CAD Layers, Line Types, Symbols, and Legend Standards 10.2 Drafting Standards, Text Styles, and Title Block Preparation 10.3 Coordinate Systems, Grid vs. Ground, and Plan Orientation
11 Chapter 11: Field Safety, Hazards & First Aid
11.1 Personal Protective Equipment (PPE) & Construction Site Safety 11.2 Traffic Control, Flaggers, and Roadway Work Zone Safety (MUTCD) 11.3 Environmental Hazards: Heat Stress, Cold Exposure, Poisonous Plants, and Animals 11.4 Electrical Hazards, Overhead Power Lines, and Excavation Safety 11.5 Basic First Aid, CPR Principles, and Emergency Response Protocols
3.4 Data Collectors, Field Software Jobs, and File Management
Key Takeaways Explain This Topic AI
Raw data files (.RAW or .RW5) store unedited raw angle, distance, HI, and HT observations forming an indelible audit trail.
ASCII coordinate files (.CSV or .TXT) follow the standard PNEZD format: Point Number, Northing, Easting, Elevation, Description.
Line work control codes (e.g. ST, PC, PT, END) embedded in feature descriptors automate 2D/3D CAD line drawing.
Resection routines solve instrument coordinates (N, E, Z) by observing angles and distances to two or more known control points.
Daily data backups must be performed to cloud or external drives; raw data files should never be deleted or overwritten.
Last updated: July 2026
- 3.4 Data Collectors, Field Software Jobs, and File Management
- 1. Handheld Data Collectors and Field Operating Systems
Handheld data collectors (field controllers) are ruggedized mobile computers running specialized survey field software (such as Trimble Access, Leica Captivate, Carlson SurvCE/SurvPC, or Topcon MAGNET Field).
Hardware Architecture
Field data collectors are designed for extreme site conditions, featuring IP67 or IP68 ingress protection against dust and water immersion. They incorporate full tactile QWERTY/numeric keypads, sunlight-readable touchscreens, long-life lithium-ion battery systems, and integrated wireless communications (Bluetooth, Wi-Fi, cellular data, and long-range robotic radio modems).
The data collector establishes bi-directional communication with total stations and GNSS receivers, logging real-time observations, performing geometric field calculations, and managing project databases.
2. Core Field Software Routines
Survey field software organizes tasks into standardized operational routines:
Topographic Survey Routine
Used to record 3D coordinates and descriptions of existing site features (natural ground, utilities, pavement, structures). Features can be stored individually by pressing a trigger key or logged continuously using auto-store parameters (storing points automatically by time interval or distance traveled).
Construction Stakeout Routine
Provides graphical guidance to navigate a rodperson to a target design coordinate ( N , E , Z N, E, Z N , E , Z ) or design alignment line (station and offset). The data collector screen displays real-time navigation directions (e.g. Go North 4.25 ft, Go East 1.10 ft, Fill 0.85 ft ).
Resection Routine
Allows a survey crew to set up the total station at an arbitrary, un-monumented location (an unknown station) with clear sight lines. By measuring horizontal angles, vertical angles, and slope distances to two or more known control points , the field software computes the instrument station's coordinates ( N , E , Z N, E, Z N , E , Z ) using least-squares or trigonometric intersection.
Traverse Routine
Used to establish boundary and control networks. The software guides the operator through systematic sets of direct and reverse telescope observations (Face 1 and Face 2 / Sight Right and Sight Left) to eliminate instrument mechanical axis errors. It tracks angular closure error and computes field traverse closing precision (e.g. 1:20,000).
3. Feature Coding and Line Work Conventions
To convert field measurements into structured CAD drawings efficiently, survey crews assign standardized feature codes (point descriptors) to every point collected.
Point Descriptors
Alphanumeric codes describing ground features:
- IPF = Iron Pin Found
- MON = Monument
- EP = Edge of Pavement
- CL = Centerline
- MH = Manhole
- UTIL = Overhead Utility Pole
- Line Work Control Codes
Action codes appended to descriptors that instruct office CAD software to draw polylines, 3D breaklines, and smooth curves automatically upon import:
ST or BEG : Start a new line feature (e.g., EP ST ).
END : End the active line feature.
PC : Point of Curvature (start of a horizontal arc).
PT : Point of Tangency (end of a horizontal arc).
CLS : Close polyline back to starting point (e.g., for a building footprint).
4. Raw Data Files vs. ASCII Coordinate Formats
Survey project data is categorized into two distinct file types: raw observation files and processed coordinate export files.
Raw Data Files ( .RAW , .RW5 , .JOB )
The raw data file is an unedited, chronological ledger of all physical measurements recorded during field operations. It records every occupied station setup, backsight reference angle, measured slope distance, zenith angle, instrument height ( H I HI H I ), target height ( H T HT H T ), and prism offset.
Audit Trail Integrity: The raw file forms an unalterable legal record. If a target height was incorrectly entered as 5.50 ft instead of 5.00 ft in the field, the raw file can be edited in the office to recalculate all downstream point elevations correctly without re-running the field survey.
ASCII Coordinate Export Files ( .TXT , .CSV )
ASCII coordinate files contain calculated flat 3D point lists exported for CAD drafting or client deliverables. The most universally recognized format is PNEZD (Comma-Delimited): Point Number, Northing, Easting, Elevation, Description \text{Point Number, Northing, Easting, Elevation, Description} Point Number, Northing, Easting, Elevation, Description 101,1005234.125,543110.850,452.15,IPF
- 102,1005280.450,543195.210,454.80,EP ST
- 103,1005315.600,543250.100,456.25,EP PC
- 5. Daily Backup Protocols and Data Security
Data loss in the field due to hardware failure, dropped controllers, battery corruption, or accidental job deletion can cost thousands of dollars in lost crew hours.
File Type Primary Extension Contains Editable in Office? Critical Purpose
Raw Data File .RW5 , .RAW , .JOB Angles, distances, HI, HT, setup points YES (audit/recalc) Legal proof of field measurements
ASCII Coordinate File .CSV , .TXT , .DAT Calculated N, E, Z coordinates & codes YES Direct import into CAD & GIS software
Project Job File .JOB , .JOBXML , .DB Proprietary software database & maps NO (use software) Real-time graphics & field software state
Important
Data Security Golden Rules:
Back up data files at the end of EVERY working day to a secure cloud server or external USB thumb drive.
Never delete raw data files ( .RW5 / .RAW ) from the data collector until verified intact on office backup servers.
Always maintain separate project jobs in the field controller for distinct field dates or tasks to prevent accidental coordinate overwrites.