15.4 Drywall & Finishes: Gypsum Board, GA-214 Levels, Ceilings, Tile & Paint
Nevada General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Nevada State Contractors Board & Licensing Law
1.1 Nevada Contractor Exams: CMS and Class B Trade Exam Format, Outline & References 1.2 NSCB Regulatory Framework, NRS 624 Scope & Contractor Definitions 1.3 License Classifications (A, B, C, AB) & Qualifying Party Requirements 1.4 License Maintenance, Biennial Renewal, Inactive Status & Business Changes
2 Chapter 2: Financial Limits, Bonding & Residential Recovery Fund
2.1 Monetary License Limits, Financial Statements & Limit Increases 2.2 Contractor Surety Bonds (NRS 624.270) & Cash Deposit Rules 2.3 Residential Recovery Fund (NRS 624.400–624.560): Eligibility, Assessments & Payouts
3 Chapter 3: Unlawful Conduct, Citations & Disciplinary Procedures
3.1 Unlawful Advertising, Unlicensed Contracting Penalties & Criminal Sanctions 3.2 Administrative Citations, Fines, Disciplinary Hearings & License Revocation
4 Chapter 4: Construction Contracts & Nevada Residential Disclosures
4.1 Essential Contract Elements, Agreement Types & Standard Construction Clauses 4.2 Nevada Residential Contract Requirements & Disclosures (NRS 624.520, 624.600 & 624.970) 4.3 Subcontractor Agreements, Flow-Down Provisions & Independent Contractor Status
5 Chapter 5: Change Orders, Prompt Payment & Dispute Resolution
5.1 Change Orders, Written Authorization Rules & Constructive Changes 5.2 Nevada Prompt Payment Law (NRS 624.606–624.630), Pay-If-Paid & Retention 5.3 Nevada Construction Defect Law (NRS Chapter 40) & Dispute Resolution
6 Chapter 6: Nevada Mechanics' Lien Law
6.1 Statutory Lien Rights, Property Subject to Lien & Excluded Work 6.2 Notice of Right to Lien (31-Day Coverage), Notice of Nonresponsibility & 15-Day Notice of Intent to Lien 6.3 Recording the Notice of Lien (90-Day Rule), Priority, Statutory Waivers & 6-Month Foreclosure Suits
7 Chapter 7: Estimating, Bidding Strategy & Public Works
7.1 Quantity Takeoff, Direct Costs, Material & Labor Estimating 7.2 Overhead Allocation, Profit Margins & Markup Calculations 7.3 Competitive Bidding Strategy, Public Works Bidding (NRS 338) & Bid Bonds
8 Chapter 8: Project Management, CPM Scheduling & Quality Control
8.1 Project Planning, Work Breakdown Structures & Critical Path Method (CPM) Scheduling 8.2 Jobsite Logistics, Submittals, Daily Logs & Progress Tracking 8.3 Quality Control, Building Inspections, Warranties & Project Closeout
9 Chapter 9: Nevada Safety, NVOSHA & Mandatory Safety Cards
9.1 Nevada OSHA (NVOSHA) Framework, Inspections, Citations & Recordkeeping 9.2 Nevada Mandatory 10-Hour & 30-Hour Construction Safety Cards (NRS 618.983) 9.3 Personal Protective Equipment, Hazard Communication & Environmental Health Hazards
10 Chapter 10: Construction Site Safety, Excavation & Nevada One Call
10.1 Fall Protection, Scaffolding & Ladder Safety (29 CFR 1926 Subparts L, M, X) 10.2 Excavation, Trenching, Soil Classification & Shoring (29 CFR 1926 Subpart P) 10.3 Nevada One Call / USA North 811 & Underground Utility Damage Prevention
11 Chapter 11: Risk Management, Insurance & Construction Bonds
11.1 Commercial General Liability (CGL) & Builder's Risk Insurance 11.2 Nevada Workers' Compensation (NRS 616A–616D Industrial Insurance) 11.3 Construction Surety Bonds: Bid, Performance, Payment & Maintenance Bonds
12 Chapter 12: Construction Accounting, Financial Analysis, Taxes & Labor Law
12.1 Construction Accounting Methods: Cash, Accrual & Percentage of Completion 12.2 Financial Statements, Balance Sheet Ratios & Cash Flow Management 12.3 Federal & Nevada State Taxes: FICA, FUTA, MBT, Commerce Tax & Sales/Use Tax 12.4 Nevada & Federal Labor Laws: Minimum Wage, Overtime, Final Pay & Paid Leave
13 Chapter 13: Building Codes, Plan Reading & Sitework
13.1 Building Codes (IBC/IRC), Permits & Inspection Sequence 13.2 Architectural & Structural Plan Reading, Scale & Symbol Conventions 13.3 Sitework, Grading, Soil Mechanics & Foundation Layout
14 Chapter 14: Concrete, Masonry & Metals
14.1 Concrete Materials, Field Testing, Formwork & Reinforcing Steel 14.2 Concrete Placement, Finishing, Joints, Curing & Post-Tensioning 14.3 Masonry: CMU, Mortar, Grout, Veneer & Wall Bracing 14.4 Structural Steel, Bolting, Welding, Joists, Light-Gauge Framing & Subpart R
15 Chapter 15: Carpentry, Thermal & Moisture Protection, Openings & Finishes
15.1 Wood Framing & Carpentry: Lumber, Engineered Wood, Anchorage & Shear Walls 15.2 Thermal & Moisture Protection: WRBs, Stucco, Insulation, Vapor Control & Roofing 15.3 Doors, Windows & Hardware: Fire Doors, Accessibility, Glazing & Flashing 15.4 Drywall & Finishes: Gypsum Board, GA-214 Levels, Ceilings, Tile & Paint
15.4 Drywall & Finishes: Gypsum Board, GA-214 Levels, Ceilings, Tile & Paint
Key Takeaways Explain This Topic AI
Type X gypsum board is 5/8 inch thick; fire ratings belong to the tested assembly, such as a UL design, not to the board alone.
GA-214 recommends a Level 5 skim-coat finish under gloss, semi-gloss, or enamel paint and in critical lighting; Level 4 suits flat paint.
Water-resistant greenboard may not be used where it is directly exposed to water; showers need cement, fiber-cement, or glass-mat backers.
ANSI A108.5 requires at least 80% mortar coverage for tile in dry interior areas and 95% in wet areas and exteriors.
The EPA RRP rule requires certified firms when work disturbs more than 6 sq ft of paint per room inside, or 20 sq ft outside, on pre-1978 housing.
Last updated: September 2026
- Gypsum Board Products & Finishes
- 1. Gypsum Board (Drywall) Types
Regular Gypsum Board (ASTM C1396): Standard 1 / 2 -inch 1/2\text{-inch} 1/2 -inch thickness for non-rated residential and light commercial interior partitions.
Type X Gypsum Board ( 5 / 8 inch 5/8\ \text{inch} 5/8 inch thick): Formulated with special core additives, including non-combustible glass fibers that maintain core cohesion when subjected to fire. One layer on each side of wood or steel studs is the basis of many 1-hour rated partitions, and two layers each side reach 2 hours. The rating belongs to the tested assembly (for example, a UL design number), not to the board alone.
Type C Gypsum Board: Enhanced version of Type X containing expanded vermiculite, used for fire-rated horizontal floor-ceiling assemblies.
Moisture-Resistant Gypsum Board ("Greenboard"): Water-repellent paper and core for areas with occasional moisture. The code does not allow water-resistant gypsum backing board where it will be directly exposed to water. Tile in tub and shower areas goes over cement, fiber-cement, or glass-mat gypsum backers (for example, ASTM C1325 cement board) installed to the manufacturer's instructions.
Abuse- and Mold-Resistant Boards: Abuse-resistant and impact-resistant panels serve corridors and schools. Glass-mat (paperless) boards resist mold and serve as exterior sheathing.
- 2. GA-214 Recommended Levels of Gypsum Board Finish
- The Gypsum Association (GA-214) establishes six standardized finish levels: GA-214 DRYWALL FINISH LEVELS
- LEVEL TREATMENT DESCRIPTION RECOMMENDED SERVICE ENVIRONMENT
- ─────────────────────────────────────────────────────────────────────────────
LEVEL 0 No taping, finishing, or coating. Temporary construction; dust barriers.
- ─────────────────────────────────────────────────────────────────────────────
- LEVEL 1 Tape embedded in compound; tool Concealed spaces, plenums, elevator
marks and ridges acceptable. shafts, attics (provides "fire-taping").
- ─────────────────────────────────────────────────────────────────────────────
- LEVEL 2 Tape embedded and wiped; fastener Water-resistant backer under tile;
heads get one coat. garages, storage where looks are secondary.
- ─────────────────────────────────────────────────────────────────────────────
- LEVEL 3 Tape + one additional coat over Medium or heavy textures applied
joints; fasteners two coats. before final painting.
- ─────────────────────────────────────────────────────────────────────────────
- LEVEL 4 Tape + two separate coats over flat Flat paints, light textures, and
joints, one over angles; fasteners wallcoverings.
three coats; sanded smooth.
- ─────────────────────────────────────────────────────────────────────────────
- LEVEL 5 Level 4 PLUS a thin skim coat (or Recommended under gloss, semi-gloss,
- equivalent material) over the enamel, or untextured flat paint where
ENTIRE surface. critical lighting exists.
─────────────────────────────────────────────────────────────────────────────
Exam Key Rule: Gloss or enamel paint over a Level 4 finish often shows joint banding (photographing) : the different texture and porosity of paper and compound become visible in raking light. GA-214 recommends a Level 5 finish (skim coat) for gloss, semi-gloss, and enamel paints and for critical lighting. The finish level is a specification choice, not a building-code requirement, so it must be written into the contract documents.
3. Installation Rules (Gypsum Construction Handbook / GA-216)
Ceilings first: Hang ceiling board before walls so the wall board supports the ceiling edges. Run board perpendicular to framing where possible and stagger end joints.
Fastening: Screws are typically spaced about 12 inches on ceilings and 16 inches on walls when framing is 16 inches on center (closer at 24-inch framing and in rated assemblies). Drive heads just below the surface without breaking the face paper. Fire-rated assemblies must follow the tested design's fastener type and spacing exactly.
Joints at openings: Avoid joints that line up with door and window jambs. Joints there crack, so place them over the header.
Control joints: Long runs of wall or ceiling need control joints at the spacing in the manufacturer's literature (commonly about 30 feet for walls). Put them at door frames and wherever the substrate changes.
Rated assemblies: Fire-taping (at least Level 1) is required in concealed spaces of rated assemblies. Every penetration needs a listed firestop system that matches the wall rating and the item penetrating it.
Moisture: Keep board dry and off the floor. Do not hang drywall until the building is dried in. Mold-damaged board is removed, not painted over.
- Ceilings, Flooring, Tile & Paint
- 1. Suspended Acoustical Ceilings
Hangers: ASTM C636 calls for 12-gauge hanger wires spaced no more than 4 feet on center, plus extra wires at light fixtures and other concentrated loads.
Seismic: In higher seismic design categories, ASTM E580 adds wider perimeter closure angles, lateral bracing wires, and compression posts on larger ceilings. Light fixtures need independent support wires. Much of Nevada is assigned SDC D, so check the structural notes.
2. Resilient Flooring over Concrete
Moisture testing: Test new slabs before installing vinyl, VCT, wood, or other moisture-sensitive floors. Use in-situ relative humidity probes (ASTM F2170) or calcium chloride tests (ASTM F1869), and compare the results with the flooring manufacturer's limit. Slab moisture is a leading cause of flooring failures.
Surface preparation: Smooth and level the slab and remove curing compounds that would block adhesion. Patch with cementitious underlayment.
3. Ceramic Tile (ANSI A108/A118 and the TCNA Handbook)
Mortar coverage: At least 80% contact in dry interior areas and 95% in wet areas and exteriors (ANSI A108.5). Back-butter large tiles to reach this coverage.
Substrate flatness: Tile with any edge of 15 inches or longer needs a flatter substrate. ANSI A108.02 allows no more than 1/8 inch of variation in 10 feet for these tiles.
Movement joints: Install them at perimeters, at changes of plane, and over structural joints, following TCNA detail EJ171. Never grout over a slab control joint.
Wet areas: Use a waterproof membrane or backer system, and slope shower pans to the drain.
4. Painting & Coatings
Surface preparation drives the life of most coatings. Concrete and masonry must be cured and dry. Steel needs the surface preparation the coating requires. Drywall needs the specified finish level and a primer.
Film thickness: Specifications state the dry film thickness in mils. Inspectors check wet film with a wet-film gauge as the paint goes on.
Lead paint (EPA RRP rule, 40 CFR 745): Renovations that disturb painted surfaces in pre-1978 housing or child-occupied facilities need an EPA-certified firm and certified renovator when they disturb more than 6 square feet inside per room or more than 20 square feet outside. Lead-safe work practices and the Renovate Right pamphlet are required.