Study guide
5.2 Nevada Prompt Payment Law (NRS 624.606–624.630), Pay-If-Paid & Retention
Nevada General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Nevada State Contractors Board & Licensing Law
1.1 Nevada Contractor Exams: CMS and Class B Trade Exam Format, Outline & References 1.2 NSCB Regulatory Framework, NRS 624 Scope & Contractor Definitions 1.3 License Classifications (A, B, C, AB) & Qualifying Party Requirements 1.4 License Maintenance, Biennial Renewal, Inactive Status & Business Changes
2 Chapter 2: Financial Limits, Bonding & Residential Recovery Fund
2.1 Monetary License Limits, Financial Statements & Limit Increases 2.2 Contractor Surety Bonds (NRS 624.270) & Cash Deposit Rules 2.3 Residential Recovery Fund (NRS 624.400–624.560): Eligibility, Assessments & Payouts
3 Chapter 3: Unlawful Conduct, Citations & Disciplinary Procedures
3.1 Unlawful Advertising, Unlicensed Contracting Penalties & Criminal Sanctions 3.2 Administrative Citations, Fines, Disciplinary Hearings & License Revocation
4 Chapter 4: Construction Contracts & Nevada Residential Disclosures
4.1 Essential Contract Elements, Agreement Types & Standard Construction Clauses 4.2 Nevada Residential Contract Requirements & Disclosures (NRS 624.520, 624.600 & 624.970) 4.3 Subcontractor Agreements, Flow-Down Provisions & Independent Contractor Status
5 Chapter 5: Change Orders, Prompt Payment & Dispute Resolution
5.1 Change Orders, Written Authorization Rules & Constructive Changes 5.2 Nevada Prompt Payment Law (NRS 624.606–624.630), Pay-If-Paid & Retention 5.3 Nevada Construction Defect Law (NRS Chapter 40) & Dispute Resolution
6 Chapter 6: Nevada Mechanics' Lien Law
6.1 Statutory Lien Rights, Property Subject to Lien & Excluded Work 6.2 Notice of Right to Lien (31-Day Coverage), Notice of Nonresponsibility & 15-Day Notice of Intent to Lien 6.3 Recording the Notice of Lien (90-Day Rule), Priority, Statutory Waivers & 6-Month Foreclosure Suits
7 Chapter 7: Estimating, Bidding Strategy & Public Works
7.1 Quantity Takeoff, Direct Costs, Material & Labor Estimating 7.2 Overhead Allocation, Profit Margins & Markup Calculations 7.3 Competitive Bidding Strategy, Public Works Bidding (NRS 338) & Bid Bonds
8 Chapter 8: Project Management, CPM Scheduling & Quality Control
8.1 Project Planning, Work Breakdown Structures & Critical Path Method (CPM) Scheduling 8.2 Jobsite Logistics, Submittals, Daily Logs & Progress Tracking 8.3 Quality Control, Building Inspections, Warranties & Project Closeout
9 Chapter 9: Nevada Safety, NVOSHA & Mandatory Safety Cards
9.1 Nevada OSHA (NVOSHA) Framework, Inspections, Citations & Recordkeeping 9.2 Nevada Mandatory 10-Hour & 30-Hour Construction Safety Cards (NRS 618.983) 9.3 Personal Protective Equipment, Hazard Communication & Environmental Health Hazards
10 Chapter 10: Construction Site Safety, Excavation & Nevada One Call
10.1 Fall Protection, Scaffolding & Ladder Safety (29 CFR 1926 Subparts L, M, X) 10.2 Excavation, Trenching, Soil Classification & Shoring (29 CFR 1926 Subpart P) 10.3 Nevada One Call / USA North 811 & Underground Utility Damage Prevention
11 Chapter 11: Risk Management, Insurance & Construction Bonds
11.1 Commercial General Liability (CGL) & Builder's Risk Insurance 11.2 Nevada Workers' Compensation (NRS 616A–616D Industrial Insurance) 11.3 Construction Surety Bonds: Bid, Performance, Payment & Maintenance Bonds
12 Chapter 12: Construction Accounting, Financial Analysis, Taxes & Labor Law
12.1 Construction Accounting Methods: Cash, Accrual & Percentage of Completion 12.2 Financial Statements, Balance Sheet Ratios & Cash Flow Management 12.3 Federal & Nevada State Taxes: FICA, FUTA, MBT, Commerce Tax & Sales/Use Tax 12.4 Nevada & Federal Labor Laws: Minimum Wage, Overtime, Final Pay & Paid Leave
13 Chapter 13: Building Codes, Plan Reading & Sitework
13.1 Building Codes (IBC/IRC), Permits & Inspection Sequence 13.2 Architectural & Structural Plan Reading, Scale & Symbol Conventions 13.3 Sitework, Grading, Soil Mechanics & Foundation Layout
14 Chapter 14: Concrete, Masonry & Metals
14.1 Concrete Materials, Field Testing, Formwork & Reinforcing Steel 14.2 Concrete Placement, Finishing, Joints, Curing & Post-Tensioning 14.3 Masonry: CMU, Mortar, Grout, Veneer & Wall Bracing 14.4 Structural Steel, Bolting, Welding, Joists, Light-Gauge Framing & Subpart R
15 Chapter 15: Carpentry, Thermal & Moisture Protection, Openings & Finishes
15.1 Wood Framing & Carpentry: Lumber, Engineered Wood, Anchorage & Shear Walls 15.2 Thermal & Moisture Protection: WRBs, Stucco, Insulation, Vapor Control & Roofing 15.3 Doors, Windows & Hardware: Fire Doors, Accessibility, Glazing & Flashing 15.4 Drywall & Finishes: Gypsum Board, GA-214 Levels, Ceilings, Tile & Paint
5.2 Nevada Prompt Payment Law (NRS 624.606–624.630), Pay-If-Paid & Retention
Key Takeaways Explain This Topic AI
Under NRS 624.609, an owner must pay the prime contractor by the date set in a written payment schedule, or within 21 days after a payment request if there is no schedule or the agreement is oral.
Under NRS 624.624, a higher-tiered contractor must pay a lower-tier subcontractor by the scheduled date or within 10 days after it is paid for that work, whichever is earlier.
Retention on private Nevada projects may not exceed 5 percent of each payment (NRS 624.609 and 624.624), and late amounts accrue interest at the contract rate or prime plus 4 percent, whichever is higher (NRS 624.630).
An unpaid contractor or subcontractor may stop work after 10 days' written notice, then terminate on at least 15 days' further notice if still unpaid (NRS 624.610 and 624.626).
Even under a pay-if-paid clause, a lower-tier subcontractor may stop work if not paid within 45 days after the 25th day of the month in which it submitted its request (NRS 624.626(1)(b)).
Last updated: September 2026
Purpose and Scope of Nevada's Prompt Payment Law
Cash flow keeps a project moving. Nevada's prompt payment law, NRS 624.606 to 624.630 , sets payment deadlines, limits retention and withholding, requires written notices, gives unpaid parties stop-work and termination rights, and charges interest on late money.
Scope Limits: The owner-to-prime sections ( NRS 624.609 to 624.622 ) do not apply to (1) an agreement between a prime contractor and a natural person who owns a single-family residence for qualified services, or (2) a public work contract with a public body (NRS 624.622(4)). Public works follow NRS 338.515 to 338.565 instead.
- Owner to Prime Contractor (NRS 624.609)
- When Payment Is Due
Written Schedule: Pay on or before the date set in the schedule for payments in the written agreement.
No Schedule, or Oral Agreement: Pay within 21 days after the prime contractor submits a request for payment .
What the Owner May Withhold
If it gives proper notice, the owner may withhold:
Retention authorized by the agreement, not exceeding 5% of the payment.
The value of work not yet performed or materials not furnished, unless the agreement allows payment for them.
Costs to correct noncompliant work , to the extent they exceed 50% of the retention withheld.
Amounts the owner paid, or must pay, under an official notice from a state agency or employee benefit trust fund for which it is liable for the contractor's or subcontractors' obligations.
Payment until the prime contractor furnishes lien releases under NRS 108.2457.
The Written Notice of Withholding (NRS 624.609(3))
To withhold anything beyond retention, the owner must give written notice on or before the date the payment is due . The notice must:
Identify the amount withheld;
Give a reasonably detailed explanation of the reason, citing the specific contract provision and documents, and the building code, law or regulation not met; and
Be signed by an authorized agent of the owner.
The prime contractor may dispute the withholding in writing in good faith, or correct the condition and give written notice of the correction. After a notice of correction, the owner must pay the withheld amount by the next payment date or object in writing.
Final Payment (NRS 624.620)
Money remaining unpaid is payable within 30 days after the owner occupies or uses the work, or after the work becomes available for its intended use . The contractor must have given a written notice of availability or a certificate of occupancy. Partial occupancy requires payment in proportion to the value of the part occupied. After a notice of correction, the owner must pay or object within 10 days .
Stopping Work and Terminating (NRS 624.610)
A prime contractor may stop work after giving the owner at least 10 days' written notice if the owner:
- Fails to pay as NRS 624.609 requires;
- Fails to give a proper written notice of withholding;
- Withholds an amount the contractor disputes in good faith and for reasonable cause; or
Fails, within 30 days after a written change-order request , to issue the change order or explain in writing why it is unreasonable or what more is needed.
After stopping work:
The contractor may terminate by written notice given after stopping work and at least 15 days before termination . If paid before that date, it must resume work.
If the owner ignored a change-order request, the price and time increase by the amounts requested , and the owner pays with the next payment.
If the owner's own act or neglect stops work for 15 days or more , the contractor may terminate on 10 days' written notice if the owner does not let work resume.
On a proper termination, the contractor recovers the cost of all work, overhead, the balance of profit it would have earned, interest , and collection costs.
Higher-Tiered Contractor to Lower-Tiered Subcontractor (NRS 624.624)
Agreement Type Payment Due (whichever is earlier )
Written, with a payment schedule The scheduled date, or within 10 days after the higher-tiered contractor receives payment for that work
Written without a schedule, or oral Within 30 days after the subcontractor's payment request, or within 10 days after the higher-tiered contractor receives payment for that work
Retention: Not more than 5% of the payment.
Other Withholding: The same categories as the owner (unperformed work, corrections over 50% of retention, agency or trust-fund notices, lien releases), with a written notice on or before the due date. A copy goes to all reputed higher-tiered contractors and the owner .
Stop Work (NRS 624.626): A lower-tiered subcontractor may stop work on 10 days' written notice for nonpayment, an improper or disputed withholding, or an unanswered change-order request after 30 days . It may then terminate on 15 days' notice .
The Pay-If-Paid Backstop
NRS 624.626(1)(b) lets a lower-tiered subcontractor stop work if the higher-tiered contractor fails to pay within 45 days after the 25th day of the month in which the subcontractor submitted its payment request . This applies even if the higher-tiered contractor has not been paid and the agreement says it pays only if or when it is paid . Any clause that waives or limits these rights is void (NRS 624.628(3)).
Interest, Notices and Information Requests
Interest (NRS 624.630): Money due accrues interest from the due date at the higher of the contract rate or the prime rate at the largest bank in Nevada plus 4% . The prime rate is set on the January 1 or July 1 before the agreement was made.
No Waivers: Clauses that waive or limit these rights, relieve the owner or higher-tier contractor of its duties, or waive claims for unforeseeable delay or disruption are void (NRS 624.622(2), 624.628(3)).
Delivering Notices: Notices must be delivered personally (with a notarized proof of delivery), by fax plus regular mail , by certified mail , or as the agreement provides.
Payment Information: Within 5 days after a written request from a lower-tiered subcontractor, the owner or higher-tiered contractor must disclose the date and amount of a specified payment and any amount withheld and why. A prime contractor must also send its lower-tier subcontractors copies of its stop-work notices and notice of payments received (NRS 624.622(1), 624.628).
Retention on Public Works (NRS 338.515 – 338.555)
Rule Public Body to Contractor Contractor to Subcontractor
Progress Payments Within 30 days after receiving the progress bill (NRS 338.515(1)) Within 10 days after the contractor is paid (NRS 338.550)
Retention Before 50% Complete 5% withheld Not more than 5% (NRS 338.555(1))
After 50% Complete If progress is satisfactory, may stop withholding and release retention; if it keeps withholding, generally 2.5% maximum after first releasing half of the retention Same pattern under NRS 338.555(2)
Occupancy or Notice of Completion Remaining balance and retention within 30 days (NRS 338.520) Passed down within 10 days
Pay-When-Paid vs. Pay-If-Paid
Pay-When-Paid: A timing clause, for example payment within 10 days after the contractor is paid. Nevada's statute already requires payment within 10 days after the higher-tier contractor is paid, if that is earlier than the scheduled date.
Pay-If-Paid: Makes owner payment a condition precedent . Nevada's 45-day backstop lets the subcontractor stop work regardless, and NRS 624.628(3) voids clauses that waive these rights. Mechanic's lien rights also cannot be waived in advance except through the statutory release forms in NRS 108.2457 .
Exam Tip: Know the numbers: 21 days (owner, no schedule), 10 days (pass-through), 30 days (sub with no schedule; change-order response; final payment after occupancy), 45 days after the 25th (pay-if-paid backstop), 5% retention, 10-day stop-work notice, 15-day termination notice, and prime + 4% interest.