Study guide
4.2 Nevada Residential Contract Requirements & Disclosures (NRS 624.520, 624.600 & 624.970)
Nevada General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Nevada State Contractors Board & Licensing Law
1.1 Nevada Contractor Exams: CMS and Class B Trade Exam Format, Outline & References 1.2 NSCB Regulatory Framework, NRS 624 Scope & Contractor Definitions 1.3 License Classifications (A, B, C, AB) & Qualifying Party Requirements 1.4 License Maintenance, Biennial Renewal, Inactive Status & Business Changes
2 Chapter 2: Financial Limits, Bonding & Residential Recovery Fund
2.1 Monetary License Limits, Financial Statements & Limit Increases 2.2 Contractor Surety Bonds (NRS 624.270) & Cash Deposit Rules 2.3 Residential Recovery Fund (NRS 624.400–624.560): Eligibility, Assessments & Payouts
3 Chapter 3: Unlawful Conduct, Citations & Disciplinary Procedures
3.1 Unlawful Advertising, Unlicensed Contracting Penalties & Criminal Sanctions 3.2 Administrative Citations, Fines, Disciplinary Hearings & License Revocation
4 Chapter 4: Construction Contracts & Nevada Residential Disclosures
4.1 Essential Contract Elements, Agreement Types & Standard Construction Clauses 4.2 Nevada Residential Contract Requirements & Disclosures (NRS 624.520, 624.600 & 624.970) 4.3 Subcontractor Agreements, Flow-Down Provisions & Independent Contractor Status
5 Chapter 5: Change Orders, Prompt Payment & Dispute Resolution
5.1 Change Orders, Written Authorization Rules & Constructive Changes 5.2 Nevada Prompt Payment Law (NRS 624.606–624.630), Pay-If-Paid & Retention 5.3 Nevada Construction Defect Law (NRS Chapter 40) & Dispute Resolution
6 Chapter 6: Nevada Mechanics' Lien Law
6.1 Statutory Lien Rights, Property Subject to Lien & Excluded Work 6.2 Notice of Right to Lien (31-Day Coverage), Notice of Nonresponsibility & 15-Day Notice of Intent to Lien 6.3 Recording the Notice of Lien (90-Day Rule), Priority, Statutory Waivers & 6-Month Foreclosure Suits
7 Chapter 7: Estimating, Bidding Strategy & Public Works
7.1 Quantity Takeoff, Direct Costs, Material & Labor Estimating 7.2 Overhead Allocation, Profit Margins & Markup Calculations 7.3 Competitive Bidding Strategy, Public Works Bidding (NRS 338) & Bid Bonds
8 Chapter 8: Project Management, CPM Scheduling & Quality Control
8.1 Project Planning, Work Breakdown Structures & Critical Path Method (CPM) Scheduling 8.2 Jobsite Logistics, Submittals, Daily Logs & Progress Tracking 8.3 Quality Control, Building Inspections, Warranties & Project Closeout
9 Chapter 9: Nevada Safety, NVOSHA & Mandatory Safety Cards
9.1 Nevada OSHA (NVOSHA) Framework, Inspections, Citations & Recordkeeping 9.2 Nevada Mandatory 10-Hour & 30-Hour Construction Safety Cards (NRS 618.983) 9.3 Personal Protective Equipment, Hazard Communication & Environmental Health Hazards
10 Chapter 10: Construction Site Safety, Excavation & Nevada One Call
10.1 Fall Protection, Scaffolding & Ladder Safety (29 CFR 1926 Subparts L, M, X) 10.2 Excavation, Trenching, Soil Classification & Shoring (29 CFR 1926 Subpart P) 10.3 Nevada One Call / USA North 811 & Underground Utility Damage Prevention
11 Chapter 11: Risk Management, Insurance & Construction Bonds
11.1 Commercial General Liability (CGL) & Builder's Risk Insurance 11.2 Nevada Workers' Compensation (NRS 616A–616D Industrial Insurance) 11.3 Construction Surety Bonds: Bid, Performance, Payment & Maintenance Bonds
12 Chapter 12: Construction Accounting, Financial Analysis, Taxes & Labor Law
12.1 Construction Accounting Methods: Cash, Accrual & Percentage of Completion 12.2 Financial Statements, Balance Sheet Ratios & Cash Flow Management 12.3 Federal & Nevada State Taxes: FICA, FUTA, MBT, Commerce Tax & Sales/Use Tax 12.4 Nevada & Federal Labor Laws: Minimum Wage, Overtime, Final Pay & Paid Leave
13 Chapter 13: Building Codes, Plan Reading & Sitework
13.1 Building Codes (IBC/IRC), Permits & Inspection Sequence 13.2 Architectural & Structural Plan Reading, Scale & Symbol Conventions 13.3 Sitework, Grading, Soil Mechanics & Foundation Layout
14 Chapter 14: Concrete, Masonry & Metals
14.1 Concrete Materials, Field Testing, Formwork & Reinforcing Steel 14.2 Concrete Placement, Finishing, Joints, Curing & Post-Tensioning 14.3 Masonry: CMU, Mortar, Grout, Veneer & Wall Bracing 14.4 Structural Steel, Bolting, Welding, Joists, Light-Gauge Framing & Subpart R
15 Chapter 15: Carpentry, Thermal & Moisture Protection, Openings & Finishes
15.1 Wood Framing & Carpentry: Lumber, Engineered Wood, Anchorage & Shear Walls 15.2 Thermal & Moisture Protection: WRBs, Stucco, Insulation, Vapor Control & Roofing 15.3 Doors, Windows & Hardware: Fire Doors, Accessibility, Glazing & Flashing 15.4 Drywall & Finishes: Gypsum Board, GA-214 Levels, Ceilings, Tile & Paint
4.2 Nevada Residential Contract Requirements & Disclosures (NRS 624.520, 624.600 & 624.970)
Key Takeaways Explain This Topic AI
NRS 624.600 requires a general building contractor to give the owner of a single-family residence the names and license numbers of its subcontractors and of suppliers furnishing $500 or more, a lien notice, and Board informational forms.
NRS 624.520 requires every residential contractor to include the Residential Construction Recovery Fund statement in each contract for qualified services.
Under NRS 624.970, residential improvement contracts must state the contractor's license number and monetary limit, the price, the completion date and a payment schedule, and must limit any deposit to the lesser of $1,000 or 10 percent.
Nevada residential pool and spa contracts over $1,000 must follow NRS 624.940 and NAC 624.6958; a contract that omits the Board's mandatory elements is void and unenforceable against the owner.
Last updated: September 2026
Why Residential Contracts Are Regulated
Owners of single-family homes are treated as consumers who need protection. Nevada therefore prescribes what a residential contractor must tell the owner and what the contract must say . Missing a required notice is a ground for discipline (NRS 624.3016(4)–(6)), and some defects make a contract voidable or void.
Disclosures by a General Building Contractor (NRS 624.600)
A general building contractor must provide in writing to the owner of a single-family residence with whom it contracts:
Subcontractors and Suppliers: The name, license number, business address and telephone number of all subcontractors it has contracted with on the project, and of all persons who furnish material of the value of $500 or more for the project.
Lien Notice: A notice that those persons may record a notice of lien on the residence and its improvements under NRS 108.226.
Board Informational Forms: The Board's prescribed forms about contractors (NAC 624.6932) and about mechanics' and materialmen's liens (NAC 624.693).
What the Board's Forms Tell the Owner
Contractors form (NAC 624.6932): Contractors must be licensed. The Board investigates complaints, and the owner can check a license or file a complaint online or by phone. A contractor must show its license number on all advertising, vehicles, bids and contracts .
Lien form (NAC 624.693): Anyone who provides work, materials or equipment worth $500 or more may give a "Pre-Lien Notice" or "Notice of Right to Lien," which is not a lien . If unpaid, that person may record a Notice of Lien . Every paid contractor, subcontractor or supplier should give an Unconditional Waiver and Release . The owner should insist on unconditional releases upon final payment from every subcontractor and supplier, and should consider consulting a lawyer.
Since 2025, NRS 624.600 also applies to residential photovoltaic work on qualified multifamily affordable housing.
Recovery Fund Notice (NRS 624.520)
Every residential contractor must notify the owner of its rights regarding the Recovery Fund. This includes a written statement in any agreement or contract for qualified services , substantially in the statutory form headed "RESIDENTIAL CONSTRUCTION RECOVERY FUND." The statement says that payment may be available if the owner is financially damaged by a project on the residence because of certain violations of Nevada law by a licensed contractor, and that the owner may contact the State Contractors Board.
Fines: Up to $250 for a first violation and $500 for each later violation, deposited in the Recovery Fund.
Discipline: Failing to give the notice is a ground for discipline (NRS 624.3016(4)).
Mandatory Contract Elements for Residential Improvements (NRS 624.970)
Since October 1, 2023 , every contract between a residential contractor and the owner-occupant of a single-family residence for work on a completed residence must contain, in writing (NRS 624.970(2)):
- Element Requirement
- (a) Contractor Name, address, license number and monetary limit
- (b) Owner and Property Owner's name and mailing address; property address or legal description
- (c)–(d) Dates Date of execution; estimated completion date
- (e)–(f) Scope and Price Description of the work; total price including taxes
(g) Deposit Any down payment or deposit, not to exceed $1,000 or 10% of the contract price, whichever is less . The cap does not apply if the contractor has a $100,000 consumer-protection bond on file or has been relieved of the bond requirement under NRS 624.270(5)
(h) Notices Statement that the owner received the NRS 624.520 and 624.600 notices and forms
(i) Change Orders Statement that scope or price changes must be agreed in writing as change orders; a change order is unenforceable unless it sets out all changes in scope and price and the owner accepts it
(j) Plans For new work : plan and scale drawing, specifications, materials, equipment and price. Repair-only contracts are exempt
(k) Payment Schedule Each progress payment in dollars and cents and the stage at which it is earned. Payments may never exceed 100% of the value of work performed , apart from the deposit, unless a payment and performance bond covers the job
The contract must also:
Let the owner initial provisions to show they were read.
Include, near the signatures, a notice that the owner may contact the Board for help understanding the contract, request a payment and performance bond , consult an attorney, and ask for a translated contract if it was explained in another language.
Be printed in at least 10-point bold type . At signing, the contractor gives the owner copies of everything signed and a signed receipt for any money paid.
Consequences: A contract missing an element other than the deposit term may be modified by the owner to comply, and a reasonable modification binds the contractor. A contract that violates the deposit term is voidable by the owner . Any clause waiving the owner's rights is void , and the contractor must obtain all permits. Pools, spas and residential photovoltaic systems have their own rules.
Residential Pools and Spas (NRS 624.920 – 624.965)
License: Only a properly licensed person may perform or offer pool or spa work, or consult on it, for a fee (NRS 624.920). The qualified employee or officer must directly supervise and control the work (NRS 624.930).
Mandatory Elements: A contract with the owner of a single-family residence that omits the Board's mandatory elements is void and unenforceable against the owner (NRS 624.940(1)). A contract over $1,000 must include items such as the parties, dates, description, total price, a deposit not exceeding $1,000 or 10%, whichever is less , a statement that the NRS 624.600 notices were given, a written change-order rule, and a scale drawing with specifications (NRS 624.940(2)).
Payment Schedule (NAC 624.6964): State each payment in dollars and cents tied to work performed. No stage may be scheduled to take more than 30 days without written agreement. Payments may not exceed 100% of the contracted amount for any stage, and each stage's payment is not due until that stage is complete. Final payment may be required after plastering and final inspection , unless contract equipment, decking or fencing is unfinished.
Performance Duties (NRS 624.935): After receiving the deposit, start work within 30 days after permits issue unless the owner agrees in writing to longer. Do not stop work for any 30-day period. After each satisfactory payment, give the owner a full and unconditional lien release for that portion before further payment, unless a payment and performance bond or joint control covers the job.
Penalties (NRS 624.965): Violations are grounds for discipline. A first criminal offense is a misdemeanor with a fine of up to $1,000 , and a second is a gross misdemeanor.
Exam Tip: The lesser of $1,000 or 10% deposit cap appears in both NRS 624.940 (pools and spas) and NRS 624.970 (residential improvements). On a $65,000 contract, 10% is $6,500, so the cap is $1,000 . On an $8,000 contract, 10% is $800, so the cap is $800 .