6.3 Recording the Notice of Lien (90-Day Rule), Priority, Statutory Waivers & 6-Month Foreclosure Suits
Nevada General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Nevada State Contractors Board & Licensing Law
1.1 Nevada Contractor Exams: CMS and Class B Trade Exam Format, Outline & References 1.2 NSCB Regulatory Framework, NRS 624 Scope & Contractor Definitions 1.3 License Classifications (A, B, C, AB) & Qualifying Party Requirements 1.4 License Maintenance, Biennial Renewal, Inactive Status & Business Changes
2 Chapter 2: Financial Limits, Bonding & Residential Recovery Fund
2.1 Monetary License Limits, Financial Statements & Limit Increases 2.2 Contractor Surety Bonds (NRS 624.270) & Cash Deposit Rules 2.3 Residential Recovery Fund (NRS 624.400–624.560): Eligibility, Assessments & Payouts
3 Chapter 3: Unlawful Conduct, Citations & Disciplinary Procedures
3.1 Unlawful Advertising, Unlicensed Contracting Penalties & Criminal Sanctions 3.2 Administrative Citations, Fines, Disciplinary Hearings & License Revocation
4 Chapter 4: Construction Contracts & Nevada Residential Disclosures
4.1 Essential Contract Elements, Agreement Types & Standard Construction Clauses 4.2 Nevada Residential Contract Requirements & Disclosures (NRS 624.520, 624.600 & 624.970) 4.3 Subcontractor Agreements, Flow-Down Provisions & Independent Contractor Status
5 Chapter 5: Change Orders, Prompt Payment & Dispute Resolution
5.1 Change Orders, Written Authorization Rules & Constructive Changes 5.2 Nevada Prompt Payment Law (NRS 624.606–624.630), Pay-If-Paid & Retention 5.3 Nevada Construction Defect Law (NRS Chapter 40) & Dispute Resolution
6 Chapter 6: Nevada Mechanics' Lien Law
6.1 Statutory Lien Rights, Property Subject to Lien & Excluded Work 6.2 Notice of Right to Lien (31-Day Coverage), Notice of Nonresponsibility & 15-Day Notice of Intent to Lien 6.3 Recording the Notice of Lien (90-Day Rule), Priority, Statutory Waivers & 6-Month Foreclosure Suits
7 Chapter 7: Estimating, Bidding Strategy & Public Works
7.1 Quantity Takeoff, Direct Costs, Material & Labor Estimating 7.2 Overhead Allocation, Profit Margins & Markup Calculations 7.3 Competitive Bidding Strategy, Public Works Bidding (NRS 338) & Bid Bonds
8 Chapter 8: Project Management, CPM Scheduling & Quality Control
8.1 Project Planning, Work Breakdown Structures & Critical Path Method (CPM) Scheduling 8.2 Jobsite Logistics, Submittals, Daily Logs & Progress Tracking 8.3 Quality Control, Building Inspections, Warranties & Project Closeout
9 Chapter 9: Nevada Safety, NVOSHA & Mandatory Safety Cards
9.1 Nevada OSHA (NVOSHA) Framework, Inspections, Citations & Recordkeeping 9.2 Nevada Mandatory 10-Hour & 30-Hour Construction Safety Cards (NRS 618.983) 9.3 Personal Protective Equipment, Hazard Communication & Environmental Health Hazards
10 Chapter 10: Construction Site Safety, Excavation & Nevada One Call
10.1 Fall Protection, Scaffolding & Ladder Safety (29 CFR 1926 Subparts L, M, X) 10.2 Excavation, Trenching, Soil Classification & Shoring (29 CFR 1926 Subpart P) 10.3 Nevada One Call / USA North 811 & Underground Utility Damage Prevention
11 Chapter 11: Risk Management, Insurance & Construction Bonds
11.1 Commercial General Liability (CGL) & Builder's Risk Insurance 11.2 Nevada Workers' Compensation (NRS 616A–616D Industrial Insurance) 11.3 Construction Surety Bonds: Bid, Performance, Payment & Maintenance Bonds
12 Chapter 12: Construction Accounting, Financial Analysis, Taxes & Labor Law
12.1 Construction Accounting Methods: Cash, Accrual & Percentage of Completion 12.2 Financial Statements, Balance Sheet Ratios & Cash Flow Management 12.3 Federal & Nevada State Taxes: FICA, FUTA, MBT, Commerce Tax & Sales/Use Tax 12.4 Nevada & Federal Labor Laws: Minimum Wage, Overtime, Final Pay & Paid Leave
13 Chapter 13: Building Codes, Plan Reading & Sitework
13.1 Building Codes (IBC/IRC), Permits & Inspection Sequence 13.2 Architectural & Structural Plan Reading, Scale & Symbol Conventions 13.3 Sitework, Grading, Soil Mechanics & Foundation Layout
14 Chapter 14: Concrete, Masonry & Metals
14.1 Concrete Materials, Field Testing, Formwork & Reinforcing Steel 14.2 Concrete Placement, Finishing, Joints, Curing & Post-Tensioning 14.3 Masonry: CMU, Mortar, Grout, Veneer & Wall Bracing 14.4 Structural Steel, Bolting, Welding, Joists, Light-Gauge Framing & Subpart R
15 Chapter 15: Carpentry, Thermal & Moisture Protection, Openings & Finishes
15.1 Wood Framing & Carpentry: Lumber, Engineered Wood, Anchorage & Shear Walls 15.2 Thermal & Moisture Protection: WRBs, Stucco, Insulation, Vapor Control & Roofing 15.3 Doors, Windows & Hardware: Fire Doors, Accessibility, Glazing & Flashing 15.4 Drywall & Finishes: Gypsum Board, GA-214 Levels, Ceilings, Tile & Paint
6.3 Recording the Notice of Lien (90-Day Rule), Priority, Statutory Waivers & 6-Month Foreclosure Suits
Key Takeaways Explain This Topic AI
Under NRS 108.226(1), a notice of lien must be recorded within 90 days after the latest of completion of the work of improvement or the claimant's last delivery or work, or within 40 days after a valid, properly served notice of completion is recorded.
A notice of lien must be verified by oath and served on the owner within 30 days after recording (NRS 108.226(3), 108.227); a knowingly false statement in a lien is a gross misdemeanor with a $5,000 to $10,000 fine.
Under NRS 108.225, liens are preferred to any mortgage or encumbrance that attached after construction visibly commenced, regardless of when the lien is recorded; NRS 108.236 ranks labor first, then suppliers and equipment lessors.
NRS 108.2457 voids contract terms that waive lien rights; a waiver is enforceable only on the statutory conditional or unconditional progress and final release forms, and only to the extent payment was received.
A recorded lien may be released by a surety bond of 1.5 times the lienable amount (NRS 108.2415), and a lien expires unless a foreclosure action is commenced within 6 months after recording (NRS 108.233).
Last updated: September 2026
Perfecting the Lien: Recording Deadlines (NRS 108.226 and 108.228)
To perfect a lien, the claimant records a notice of lien with the county recorder of the county where the property is located, using the statutory form.
The 90-Day Rule (NRS 108.226(1)(a))
Record within 90 days after the latest of:
- Completion of the work of improvement (the whole project);
- The last delivery of material or furnishing of equipment by the claimant; or
The last performance of work by the claimant.
On residential projects, serving the 15-day notice of intent to lien extends this deadline by 15 days (NRS 108.226(6)).
The 40-Day Rule After a Notice of Completion (NRS 108.228)
Recording the Notice: After the work of improvement is complete, the owner may record a notice of completion . It states the date of completion, the owner's name, address and nature of title, a property description and the prime contractor's name, and it is verified .
Mailing Copies: Within 10 days after recording , the owner must mail a copy by certified mail to each prime contractor and to each potential claimant who gave a notice of right to lien or asked for a copy.
Effect: If properly recorded and served , the lien deadline becomes 40 days after the notice of completion is recorded (NRS 108.226(1)(b)).
Failure to Serve: If the owner does not deliver a copy as required, the notice of completion is ineffective as to that prime contractor or claimant, and the 90-day rule applies to it. Deadline to record a notice of lien
- No notice of completion ............ 90 days after the latest of project completion
- or the claimant's last work or delivery
- Valid, served notice of completion . 40 days after the notice of completion is recorded
- Residential + 15-day notice ........ either deadline extended by 15 days
Exam Focus: First ask whether a notice of completion was recorded and mailed within 10 days to this claimant. If not, use the 90-day rule.
- Contents, Verification and Service
- Contents (NRS 108.226(2) and (5))
The notice of lien must state:
The lienable amount after deducting all just credits and offsets . The statutory form lists the original contract amount, additional or changed work, and payments received.
The name of the owner , if known.
The name of the person who employed the claimant or to whom it furnished materials or equipment.
A brief statement of the terms of payment .
A description of the property sufficient to identify it, with the assessor's parcel number.
Verification
The notice must be verified by the oath of the lien claimant or another person, sworn before a notary. It need not be acknowledged to be recorded. Knowingly making a false statement in or relating to a notice of lien is a gross misdemeanor with a fine of $5,000 to $10,000 (NRS 108.226(4)). It is also a ground for discipline (NRS 624.3016(3)).
Service (NRS 108.227)
On the Owner: Within 30 days after recording , serve a copy by personal delivery to the owner or its registered agent, or by certified mail, return receipt requested . If no address can be found, post a copy on the property, deliver one to a resident, and mail copies to the addresses of record.
Multiple Owners: Serving one owner preserves the lien even if another was missed.
On the Prime Contractor: Each subcontractor must also deliver a copy of each notice of lien to the prime contractor . Failing to do so is a ground for discipline.
- Priority (NRS 108.225) and Ranking (NRS 108.236)
- Priority Over Other Encumbrances
Mechanics' liens are preferred to :
Any lien, mortgage or other encumbrance that attached after the commencement of construction ; and
Any lien, mortgage or encumbrance unrecorded at commencement of which the claimant had no notice .
Every mortgage or encumbrance imposed after construction commenced is subordinate to the mechanics' liens, regardless of when the notices of lien are recorded .
Commencement of construction is the date when work performed, or materials or equipment furnished, is visible from a reasonable inspection of the site (NRS 108.22112). Jan 15 Excavation visibly begins (commencement of construction)
- Feb 1 Lender records a $5,000,000 deed of trust
- Jun 1 Electrical subcontractor starts work
- Nov 1 Electrical subcontractor records a $40,000 lien
Result: the deed of trust attached AFTER commencement, so the
electrical lien is preferred to it (NRS 108.225).
This is why construction lenders inspect sites and obtain title endorsements to confirm no visible work has begun before they record.
Ranking Among Lien Claimants (NRS 108.236)
When several liens are foreclosed together, the court ranks claimants, and sale proceeds are paid in this order:
- All labor , whether ordered by the owner, the prime contractor or a subcontractor;
- Material suppliers and lessors of equipment ;
- Other claimants who worked under contract with the prime contractor or a subcontractor; and
All other lien claimants .
Waivers and Releases (NRS 108.2453 and 108.2457)
No Advance Waivers: Any contract term that attempts to waive or impair the lien rights of a contractor, subcontractor or supplier is void (NRS 108.2457(1)). NRS 108.2453 also voids terms that limit lien rights, require another state's law, require out-of-state dispute resolution, or waive claims for unreasonable delay or disruption.
Only on Statutory Forms: A waiver is enforceable only if the claimant signs one of the statutory forms and, for a conditional waiver, actually receives the payment . Any oral or written statement purporting to waive lien rights is unenforceable except through a statutory form and only to the extent of payment received .
Form When Used Effect
Conditional Waiver and Release Upon Progress Payment When requesting a progress payment Effective only when the stated payment is received
Unconditional Waiver and Release Upon Progress Payment After the progress payment is received Releases rights for work through the stated date, except retention and listed exceptions
Conditional Waiver and Release Upon Final Payment When requesting final payment Effective only when final payment is received
Unconditional Waiver and Release Upon Final Payment After final payment is received Releases all lien rights for the job
The Board's homeowner lien form tells owners to insist on an unconditional waiver and release upon final payment from every subcontractor and supplier (NAC 624.693).
Release Bonds (NRS 108.2413 – 108.2425)
To Release One Recorded Lien: The principal and a surety record a bond of 1.5 times the lienable amount in the notice of lien (NRS 108.2415(1)).
To Release All Liens on a Project: A bond of 1.5 times the prime contract amount releases all prospective and existing lien rights for the work of improvement (NRS 108.2415(2)).
Effect: The lien is released from the property, and the claimant looks to the bond . The surety pays what a court finds was secured by the lien, plus amounts awarded under NRS 108.237, up to the bond's penal sum. Release Bond = 1.5 × Lienable Amount \text{Release Bond} = 1.5 \times \text{Lienable Amount} Release Bond = 1.5 × Lienable Amount
Frivolous or Excessive Liens (NRS 108.2275)
An owner or other party in interest may ask the district court to order the claimant to show cause why a lien should not be released as frivolous or reduced as excessive :
The motion needs a notarized affidavit and supporting documents.
The applicant serves the order within 3 days , and the hearing is held 15 to 30 days after the order.
If the claimant does not appear, the lien is released with prejudice and the claimant pays the applicant's costs and attorney's fees.
If the lien is found frivolous and without reasonable cause , it is released and the applicant recovers costs and fees. If it is excessive, it may be reduced, with fees. If the lien is upheld, the claimant recovers its costs and fees.
- Enforcing the Lien (NRS 108.233, 108.237)
- The 6-Month Deadline
A lien does not bind the property for more than 6 months after the notice of lien is recorded unless a foreclosure action is commenced in a proper court within that time (NRS 108.233(1)). After 6 months the notice of lien expires and gives no notice of anything.
Extension by Agreement
The lien claimant and a person in interest may extend the time by a written instrument , acknowledged and recorded within the 6-month period .
The extension binds only those who sign it.
It may not run more than 1 year after the notice of lien was recorded , and no second extension is allowed.
No extension may be given if it would delay the collection of other liens or encumbrances.
Fees, Costs and Interest (NRS 108.237)
Prevailing Claimant: The court shall award the lienable amount, the cost of preparing and recording the lien, the costs of the proceedings including reasonable attorney's fees , and interest .
Interest Rate: The contract rate, or if none, prime plus 4% , adjusted each January 1 and July 1.
Lien Not Upheld: If the lien claim fails, the court may award the owner fees and costs if the lien was pursued without a reasonable basis in law or fact .
Summary of Lien Deadlines
- Step Statute Deadline or Rule
- Notice of right to lien NRS 108.245 Any time; covers the 31 days before it is given and afterward
- Notice of nonresponsibility NRS 108.234 Recorded within 3 days after the owner learns of the work
15-day notice of intent (residential) NRS 108.226(6) Served at least 15 days before recording; extends deadline by 15 days
Record notice of lien NRS 108.226 90 days after the latest completion or last work, or 40 days after a valid, served notice of completion
- Serve notice of completion NRS 108.228 Owner mails copies within 10 days after recording
- Serve recorded lien NRS 108.227 On the owner within 30 days after recording
- Release bond NRS 108.2415 1.5 times the lienable amount
- Foreclose NRS 108.233 Within 6 months after recording; one extension, at most 1 year after recording