Study guide
1.3 License Classifications (A, B, C, AB) & Qualifying Party Requirements
Nevada General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Nevada State Contractors Board & Licensing Law
1.1 Nevada Contractor Exams: CMS and Class B Trade Exam Format, Outline & References 1.2 NSCB Regulatory Framework, NRS 624 Scope & Contractor Definitions 1.3 License Classifications (A, B, C, AB) & Qualifying Party Requirements 1.4 License Maintenance, Biennial Renewal, Inactive Status & Business Changes
2 Chapter 2: Financial Limits, Bonding & Residential Recovery Fund
2.1 Monetary License Limits, Financial Statements & Limit Increases 2.2 Contractor Surety Bonds (NRS 624.270) & Cash Deposit Rules 2.3 Residential Recovery Fund (NRS 624.400–624.560): Eligibility, Assessments & Payouts
3 Chapter 3: Unlawful Conduct, Citations & Disciplinary Procedures
3.1 Unlawful Advertising, Unlicensed Contracting Penalties & Criminal Sanctions 3.2 Administrative Citations, Fines, Disciplinary Hearings & License Revocation
4 Chapter 4: Construction Contracts & Nevada Residential Disclosures
4.1 Essential Contract Elements, Agreement Types & Standard Construction Clauses 4.2 Nevada Residential Contract Requirements & Disclosures (NRS 624.520, 624.600 & 624.970) 4.3 Subcontractor Agreements, Flow-Down Provisions & Independent Contractor Status
5 Chapter 5: Change Orders, Prompt Payment & Dispute Resolution
5.1 Change Orders, Written Authorization Rules & Constructive Changes 5.2 Nevada Prompt Payment Law (NRS 624.606–624.630), Pay-If-Paid & Retention 5.3 Nevada Construction Defect Law (NRS Chapter 40) & Dispute Resolution
6 Chapter 6: Nevada Mechanics' Lien Law
6.1 Statutory Lien Rights, Property Subject to Lien & Excluded Work 6.2 Notice of Right to Lien (31-Day Coverage), Notice of Nonresponsibility & 15-Day Notice of Intent to Lien 6.3 Recording the Notice of Lien (90-Day Rule), Priority, Statutory Waivers & 6-Month Foreclosure Suits
7 Chapter 7: Estimating, Bidding Strategy & Public Works
7.1 Quantity Takeoff, Direct Costs, Material & Labor Estimating 7.2 Overhead Allocation, Profit Margins & Markup Calculations 7.3 Competitive Bidding Strategy, Public Works Bidding (NRS 338) & Bid Bonds
8 Chapter 8: Project Management, CPM Scheduling & Quality Control
8.1 Project Planning, Work Breakdown Structures & Critical Path Method (CPM) Scheduling 8.2 Jobsite Logistics, Submittals, Daily Logs & Progress Tracking 8.3 Quality Control, Building Inspections, Warranties & Project Closeout
9 Chapter 9: Nevada Safety, NVOSHA & Mandatory Safety Cards
9.1 Nevada OSHA (NVOSHA) Framework, Inspections, Citations & Recordkeeping 9.2 Nevada Mandatory 10-Hour & 30-Hour Construction Safety Cards (NRS 618.983) 9.3 Personal Protective Equipment, Hazard Communication & Environmental Health Hazards
10 Chapter 10: Construction Site Safety, Excavation & Nevada One Call
10.1 Fall Protection, Scaffolding & Ladder Safety (29 CFR 1926 Subparts L, M, X) 10.2 Excavation, Trenching, Soil Classification & Shoring (29 CFR 1926 Subpart P) 10.3 Nevada One Call / USA North 811 & Underground Utility Damage Prevention
11 Chapter 11: Risk Management, Insurance & Construction Bonds
11.1 Commercial General Liability (CGL) & Builder's Risk Insurance 11.2 Nevada Workers' Compensation (NRS 616A–616D Industrial Insurance) 11.3 Construction Surety Bonds: Bid, Performance, Payment & Maintenance Bonds
12 Chapter 12: Construction Accounting, Financial Analysis, Taxes & Labor Law
12.1 Construction Accounting Methods: Cash, Accrual & Percentage of Completion 12.2 Financial Statements, Balance Sheet Ratios & Cash Flow Management 12.3 Federal & Nevada State Taxes: FICA, FUTA, MBT, Commerce Tax & Sales/Use Tax 12.4 Nevada & Federal Labor Laws: Minimum Wage, Overtime, Final Pay & Paid Leave
13 Chapter 13: Building Codes, Plan Reading & Sitework
13.1 Building Codes (IBC/IRC), Permits & Inspection Sequence 13.2 Architectural & Structural Plan Reading, Scale & Symbol Conventions 13.3 Sitework, Grading, Soil Mechanics & Foundation Layout
14 Chapter 14: Concrete, Masonry & Metals
14.1 Concrete Materials, Field Testing, Formwork & Reinforcing Steel 14.2 Concrete Placement, Finishing, Joints, Curing & Post-Tensioning 14.3 Masonry: CMU, Mortar, Grout, Veneer & Wall Bracing 14.4 Structural Steel, Bolting, Welding, Joists, Light-Gauge Framing & Subpart R
15 Chapter 15: Carpentry, Thermal & Moisture Protection, Openings & Finishes
15.1 Wood Framing & Carpentry: Lumber, Engineered Wood, Anchorage & Shear Walls 15.2 Thermal & Moisture Protection: WRBs, Stucco, Insulation, Vapor Control & Roofing 15.3 Doors, Windows & Hardware: Fire Doors, Accessibility, Glazing & Flashing 15.4 Drywall & Finishes: Gypsum Board, GA-214 Levels, Ceilings, Tile & Paint
1.3 License Classifications (A, B, C, AB) & Qualifying Party Requirements
Key Takeaways Explain This Topic AI
NAC Chapter 624 sets up Class A (General Engineering, NAC 624.140), Class B (General Building, NAC 624.160) with subclassifications B-1 through B-7, Class AB (NAC 624.180), and Class C specialties numbered C-1 to C-42.
Under NRS 624.215(3), a Class B contractor builds structures requiring more than two unrelated trades and may not perform plumbing, electrical, refrigeration and air-conditioning, or fire protection work without the specialty license.
NRS 624.260(6) requires the qualifying individual to have at least 4 years of experience as a journeyman, foreman, supervising employee or contractor in the classification within the 15 years before applying; accredited training can replace up to 3 years.
Under NRS 624.260(3), the qualifying individual must be a bona fide member or employee who makes technical and administrative decisions, directs employees, and devotes himself or herself solely to the licensee's business.
Under NRS 624.285, the licensee must notify the Board within 10 days after its qualified individual leaves; the license stays in force for no more than 30 days, and late notice means automatic suspension.
Last updated: September 2026
Nevada Contractor License Classifications (NAC 624.140 - 624.574)
In Nevada, contractor licenses are classified according to the technical nature and scope of construction operations. The Nevada Administrative Code establishes four principal license branches:
- Class A: General Engineering Contracting
- Class B: General Building Contracting
- Class C: Specialty Contracting (classifications numbered C-1 through C-42; not every number is in use)
- Class AB: Dual General Engineering and General Building Contracting
Exam Warning: Under NRS 624.3015 , acting in the capacity of a contractor beyond the scope of your assigned license classification or subclassification constitutes grounds for immediate disciplinary action, administrative citations, and license suspension.
Class A: General Engineering Contractor (NAC 624.140)
A Class A General Engineering license covers a contractor whose principal business is fixed works requiring specialized engineering knowledge and skill. NAC 624.140 adopts the scope in NRS 624.215(2) , and NAC 624.150 lists the A subclassifications. The scope includes:
- Irrigation, drainage, water power, water supply, and flood control projects
- Harbors, docks, canals, inland waterways, and river control
- Highways, streets, roads, bridges, viaducts, tunnels, and overpasses
- Sewers, sewage disposal plants, and storm water systems
- Railroads, light rail systems, and airports
- Refineries, chemical plants, and heavy industrial foundation facilities
- Power generation plants, transmission lines, and substations
- Excavating, grading, trenching, paving, and earthmoving associated with civil infrastructure
- Class B: General Building Contractor & Subclassifications (NAC 624.160 and 624.170)
Under NRS 624.215(3) , a Class B General Building contractor's principal business is constructing or remodeling buildings or structures for the support, shelter and enclosure of persons, animals, chattels or movable property. The scope has three built-in limits:
More Than Two Unrelated Trades: The construction must require the use of more than two unrelated building trades or crafts , and the Class B contractor must be the prime contractor where building construction or remodeling is the primary purpose.
Specialty Work Only as Prime: Unless it holds the specialty license, a general building contractor may perform specialty contracting only when it is the prime contractor on the project.
Four Restricted Specialties: A general building contractor shall not perform plumbing, electrical, refrigeration and air-conditioning, or fire protection work without a license for that specialty; that work goes to properly licensed specialty contractors.
Class B Subclassifications (NAC 624.170)
The unlimited Class B license carries no height limit. NAC 624.170 also defines seven subclassifications:
B-1 (Premanufactured Housing): Fitting, assembling, placing and installing premanufactured units and modular parts for residential buildings no more than three stories above ground.
B-2 (Residential and Small Commercial): Construction and remodeling of houses and other structures that do not extend more than three stories above the ground and one story below the ground .
B-3 (Speculative Building): Construction, on property the contractor owns, of structures for sale or speculation.
B-4 (Service Stations): Construction of structures and installation of equipment used to service vehicles.
B-5 (Prefabricated Steel Structures): Construction with prefabricated steel of structures for the support, shelter or enclosure of persons, animals or chattels.
B-6 (Commercial Remodeling): Remodeling and improvement of interior spaces , including in structures over three stories. A B-6 licensee may not perform, manage or supervise work on any structural member, mechanical system, fire protection system or other life safety system .
B-7 (Residential Remodeling): Remodeling an existing, detached single-family residence, or a single-family unit in a structure no more than three stories above and one below ground. A B-7 licensee may not increase the existing enclosed space .
Class C: Specialty Contracting Classifications (NAC 624.190 - 624.574)
Class C classifications are numbered C-1 through C-42 , although several numbers are no longer used. A specialty contractor's principal business uses specialized building trades or crafts (NRS 624.215(4)). Under NRS 624.220(4)(a) , it may take a contract involving other crafts only when that other work is incidental and supplemental to its licensed craft. It cannot bid prime contracts for multiple unrelated trades outside its craft.
Key Class C classifications frequently tested on the Nevada examination include:
C-1 (Plumbing and Heating Contracting): Subclasses include C-1a (Boilers), C-1b (Fire Sprinklers), C-1c (Insulation of Pipes and Ducts), C-1d (Plumbing, which includes medical gas piping), and C-1e (Sheet Metal).
C-2 (Electrical Contracting): Subclasses include C-2a (Electrical Wiring), C-2c (Fire Detection), C-2d (Low Voltage), and C-2g (Photovoltaics/Solar).
C-3 (Carpentry, Maintenance, and Minor Repairs): Covers framing, rough carpentry, finish carpentry, and general repairs.
C-4 (Painting and Decorating): Painting, wallcovering, taping and finishing, sandblasting, drywall, sheet metal studs, and acoustical tile.
C-5 (Concrete Contracting): Forms, placing reinforcement and embedded items, placing and finishing concrete, sealants, and sawing, cutting and coring concrete and asphalt paving.
C-10 (Landscape Contracting): Covers exterior planting, irrigation systems, sod, and decorative rockwork.
C-14 (Steel Reinforcing and Erection): Includes C-14a (reinforcing steel and post-tensioning), C-14b (structural steel), C-14e (doors and windows), and C-14g (prefabricated steel structures).
C-21 (Refrigeration and Air Conditioning): Covers residential and commercial HVAC and cooling systems.
Class AB: Dual Engineering and General Building
A Class AB license (NAC 624.180) covers both general building and general engineering. NRS 624.215(1) treats the two branches as mutually exclusive , so a firm that wants both scopes needs the combined classification. NAC 624.180 limits Class AB to applicants who show enough experience and financial responsibility to support an unlimited license in both the A and B classifications.
Classification Statutory Code Primary Scope Critical Self-Performance Limits
Class A NAC 624.140 / NRS 624.215(2) Fixed engineering works, utilities, highways, bridges, earthwork When acting as prime, may hire no more than one general building contractor per project
Class B NAC 624.160 / NRS 624.215(3) Buildings and structures for shelter or enclosure Must involve more than two unrelated trades; no plumbing, electrical, refrigeration/AC or fire protection without the specialty license
Class C NAC 624.190–624.574 Specialty trades numbered C-1 through C-42 Other crafts only when incidental and supplemental to the licensed craft
Class AB NAC 624.180 Combined Class A and Class B scope Requires experience and finances for an unlimited license in both branches
Qualifying Party (QP) Requirements (NRS 624.260)
Every applicant for a Nevada contractor license must qualify through a natural person, often called the Qualifying Party (QP) or qualified individual . The QP proves the experience and knowledge required by NRS 624.260, passes the required examinations, and supervises construction for the licensee. The license belongs to the business, not to the QP.
Eligibility to Act as a Qualifying Party
Depending on the legal structure of the contracting business, the Qualifying Party must be:
Sole Proprietorship: The individual owner or a bona fide employee.
Partnership: One of the general partners or a bona fide employee.
Corporation: A qualified corporate officer or a bona fide employee.
Limited Liability Company (LLC): A manager, managing member, or a bona fide employee.
Verifiable Experience Requirements
Under NRS 624.260(6)–(8) and the Board's application requirements, the Qualifying Party must demonstrate:
Four (4) Years of Experience: At least four (4) full years of experience in the specific classification applied for.
Fifteen-Year Window: The four years must fall within the 15 years immediately preceding the application. The window does not apply to someone who previously qualified for a license in the same classification (NRS 624.260(7)).
Qualifying Levels of Experience: Experience must be as a journeyman, foreman, supervising employee, or contractor . A journeyman is fully qualified to work in the classification without supervision or has completed an approved apprenticeship (NRS 624.260(8)).
Education Credit: Training in a program at an accredited college or university, or an equivalent program accepted by the Board, may satisfy no more than 3 years of the requirement.
Verification Documentation: The Board accepts four Certification of Work Experience forms for each trade qualifier, a current master's certification from a government agency in a substantially similar discipline, or proof of transferable military experience. Each qualifier also submits a Resume of Experience .
Duties of the Qualifying Party: Direct Supervision & Control
Under NRS 624.260(3) , the Qualifying Party is not a symbolic figurehead. The QP must be a bona fide member or employee of the licensee and, while the licensee is actively contracting, must:
Make technical and administrative decisions for the contracting business
Hire, superintend, promote, transfer, lay off, discipline or discharge employees and direct them, personally or through others, or effectively recommend those actions
Devote himself or herself solely to the licensee's business and take no other employment that conflicts with those duties
NAC 624.640(4) adds that if a license was issued partly because of the employment of a particularly qualified person, the licensee must continue to employ such a person to keep the license.
The Prohibition of "Ghost" or "Rent-a-Qualifier" Practices
It is a severe violation of Nevada law for an individual to serve as a "ghost qualifier" —acting as the QP on a license application for compensation while exercising no day-to-day management or on-site supervision. When the Board discovers an absentee qualifier, it initiates disciplinary proceedings resulting in license revocation, civil fines, and permanent disqualification of the QP.
Qualifying Multiple Licenses (NRS 624.260(5))
A natural person may not qualify on behalf of another for more than one active license unless:
- The person owns at least 25% of each licensee for which he or she qualifies;
- One licensee owns at least 25% of the other licensee; or
One licensee is a corporation for public benefit as defined in NRS 82.021.
Disassociation of a Qualifying Party (NRS 624.285)
When the person who qualified by examination resigns, is terminated, or otherwise stops being connected with the licensee, the licensee's authority to contract is at risk. NRS 624.285 sets a strict timeline: [Qualified individual leaves]
- |
- +--> Within 10 days: licensee notifies the Board in writing
- | |
- | +--> No notice in 10 days: license AUTOMATICALLY SUSPENDED
- |
- +--> License stays in force for a period set by the Board, no more than 30 days
- |
- +--> Replace with a similarly qualified person approved by the Board
- +--> Board may extend the deadline for good cause
- +--> Not replaced in time: license MAY BE SUSPENDED OR REVOKED
10-Day Notice: The licensee must notify the Board in writing within 10 days after the association or employment ends.
Up to 30 Days in Force: If notice is given, the license remains in force for a reasonable time set by the Board, not exceeding 30 days after the separation.
Replacement and Extensions: The licensee must replace the person with another natural person who is similarly qualified and approved by the Board within that time, unless the Board extends it for good cause .
Consequences: Missing the 10-day notice causes automatic suspension , which is lifted when an approved replacement is in place. Failing to replace within the 30-day period means the license may be suspended or revoked . Contracting while suspended is unlicensed contracting.
Examination Structure and NASCLA / Reciprocity Waivers
To be licensed, the Qualifying Party must pass the Contractor Management Survey (CMS) , which is the business and law exam, and the trade examination for the classification. Section 1.1 covers both exam formats, the subject outlines, the open-book reference rules, and PSI logistics.
A candidate has three attempts at each exam, must wait two weeks after a failure, and must pass within 6 months after the application is filed. After a third failure the application is void, and a new application may be filed 30 days after the last exam (NAC 624.600(4)).
The NASCLA Commercial General Building Accredited Exam
Under NAC 624.600(2), the Board waives an examination accredited by the National Association of State Contractors Licensing Agencies (NASCLA) when it finds that exam substantially equivalent. The NSCB states that if you passed the NASCLA Commercial General Building Contractor Examination , Nevada waives the state-specific trade exam for a general building classification. The transcript is sent through NASCLA's National Examination Database.
Licensure by Endorsement
Nevada also waives the trade exam, the experience certification, or both, for applicants licensed in states it finds substantially equivalent. Its equivalency chart lists Alabama, Arizona, California, Connecticut, Florida, Hawaii, Louisiana, New Mexico, North Carolina, South Carolina, Tennessee and West Virginia, by classification. The applicant must:
Have held an active license in the endorsing state with the same qualified individual for the past four (4) years ;
Have no investigation for misconduct and no revocation, suspension or other discipline in any jurisdiction; and
Have no disciplinary proceeding pending.
If the endorsing state has no equivalent trade exam, the Nevada trade exam is still required.
CRITICAL EXAM RULE: NASCLA and endorsement waivers apply only to the trade examination and/or experience certification . The NSCB states that the qualified individual must still pass the Nevada Business and Law (CMS) examination .