Study guide
9.2 Nevada Mandatory 10-Hour & 30-Hour Construction Safety Cards (NRS 618.983)
Nevada General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Nevada State Contractors Board & Licensing Law
1.1 Nevada Contractor Exams: CMS and Class B Trade Exam Format, Outline & References 1.2 NSCB Regulatory Framework, NRS 624 Scope & Contractor Definitions 1.3 License Classifications (A, B, C, AB) & Qualifying Party Requirements 1.4 License Maintenance, Biennial Renewal, Inactive Status & Business Changes
2 Chapter 2: Financial Limits, Bonding & Residential Recovery Fund
2.1 Monetary License Limits, Financial Statements & Limit Increases 2.2 Contractor Surety Bonds (NRS 624.270) & Cash Deposit Rules 2.3 Residential Recovery Fund (NRS 624.400–624.560): Eligibility, Assessments & Payouts
3 Chapter 3: Unlawful Conduct, Citations & Disciplinary Procedures
3.1 Unlawful Advertising, Unlicensed Contracting Penalties & Criminal Sanctions 3.2 Administrative Citations, Fines, Disciplinary Hearings & License Revocation
4 Chapter 4: Construction Contracts & Nevada Residential Disclosures
4.1 Essential Contract Elements, Agreement Types & Standard Construction Clauses 4.2 Nevada Residential Contract Requirements & Disclosures (NRS 624.520, 624.600 & 624.970) 4.3 Subcontractor Agreements, Flow-Down Provisions & Independent Contractor Status
5 Chapter 5: Change Orders, Prompt Payment & Dispute Resolution
5.1 Change Orders, Written Authorization Rules & Constructive Changes 5.2 Nevada Prompt Payment Law (NRS 624.606–624.630), Pay-If-Paid & Retention 5.3 Nevada Construction Defect Law (NRS Chapter 40) & Dispute Resolution
6 Chapter 6: Nevada Mechanics' Lien Law
6.1 Statutory Lien Rights, Property Subject to Lien & Excluded Work 6.2 Notice of Right to Lien (31-Day Coverage), Notice of Nonresponsibility & 15-Day Notice of Intent to Lien 6.3 Recording the Notice of Lien (90-Day Rule), Priority, Statutory Waivers & 6-Month Foreclosure Suits
7 Chapter 7: Estimating, Bidding Strategy & Public Works
7.1 Quantity Takeoff, Direct Costs, Material & Labor Estimating 7.2 Overhead Allocation, Profit Margins & Markup Calculations 7.3 Competitive Bidding Strategy, Public Works Bidding (NRS 338) & Bid Bonds
8 Chapter 8: Project Management, CPM Scheduling & Quality Control
8.1 Project Planning, Work Breakdown Structures & Critical Path Method (CPM) Scheduling 8.2 Jobsite Logistics, Submittals, Daily Logs & Progress Tracking 8.3 Quality Control, Building Inspections, Warranties & Project Closeout
9 Chapter 9: Nevada Safety, NVOSHA & Mandatory Safety Cards
9.1 Nevada OSHA (NVOSHA) Framework, Inspections, Citations & Recordkeeping 9.2 Nevada Mandatory 10-Hour & 30-Hour Construction Safety Cards (NRS 618.983) 9.3 Personal Protective Equipment, Hazard Communication & Environmental Health Hazards
10 Chapter 10: Construction Site Safety, Excavation & Nevada One Call
10.1 Fall Protection, Scaffolding & Ladder Safety (29 CFR 1926 Subparts L, M, X) 10.2 Excavation, Trenching, Soil Classification & Shoring (29 CFR 1926 Subpart P) 10.3 Nevada One Call / USA North 811 & Underground Utility Damage Prevention
11 Chapter 11: Risk Management, Insurance & Construction Bonds
11.1 Commercial General Liability (CGL) & Builder's Risk Insurance 11.2 Nevada Workers' Compensation (NRS 616A–616D Industrial Insurance) 11.3 Construction Surety Bonds: Bid, Performance, Payment & Maintenance Bonds
12 Chapter 12: Construction Accounting, Financial Analysis, Taxes & Labor Law
12.1 Construction Accounting Methods: Cash, Accrual & Percentage of Completion 12.2 Financial Statements, Balance Sheet Ratios & Cash Flow Management 12.3 Federal & Nevada State Taxes: FICA, FUTA, MBT, Commerce Tax & Sales/Use Tax 12.4 Nevada & Federal Labor Laws: Minimum Wage, Overtime, Final Pay & Paid Leave
13 Chapter 13: Building Codes, Plan Reading & Sitework
13.1 Building Codes (IBC/IRC), Permits & Inspection Sequence 13.2 Architectural & Structural Plan Reading, Scale & Symbol Conventions 13.3 Sitework, Grading, Soil Mechanics & Foundation Layout
14 Chapter 14: Concrete, Masonry & Metals
14.1 Concrete Materials, Field Testing, Formwork & Reinforcing Steel 14.2 Concrete Placement, Finishing, Joints, Curing & Post-Tensioning 14.3 Masonry: CMU, Mortar, Grout, Veneer & Wall Bracing 14.4 Structural Steel, Bolting, Welding, Joists, Light-Gauge Framing & Subpart R
15 Chapter 15: Carpentry, Thermal & Moisture Protection, Openings & Finishes
15.1 Wood Framing & Carpentry: Lumber, Engineered Wood, Anchorage & Shear Walls 15.2 Thermal & Moisture Protection: WRBs, Stucco, Insulation, Vapor Control & Roofing 15.3 Doors, Windows & Hardware: Fire Doors, Accessibility, Glazing & Flashing 15.4 Drywall & Finishes: Gypsum Board, GA-214 Levels, Ceilings, Tile & Paint
9.2 Nevada Mandatory 10-Hour & 30-Hour Construction Safety Cards (NRS 618.983)
Key Takeaways Explain This Topic AI
Under NRS 618.983, a construction worker who is not a supervisor must obtain an OSHA-10 completion card within 15 days after being hired.
Under NRS 618.983, a supervisory employee must obtain an OSHA-30 completion card within 15 days after being hired.
NRS 618.950 to 618.990 set no expiration date for construction completion cards; the 5-year expiration and renewal rules apply to the entertainment-industry and convention-services card laws instead.
Under NRS 618.987, an employer must suspend or terminate a construction worker or supervisor who does not present a current, valid completion card within 15 days after hire.
NRS 618.990 fines an employer that fails to suspend or terminate up to $500 for a first violation and $1,000 for a second, then treats a third violation as willful; violations found in one day count as one.
Last updated: September 2026
Background: Nevada's Construction Safety Card Law
In 2009 , after a series of worker deaths on large Las Vegas Strip projects, the Legislature passed the law now codified at NRS 618.950 to 618.990 ("Mandatory OSHA-10 and OSHA-30 Training for Construction Industry"). It made OSHA outreach training mandatory for workers and supervisors on Nevada construction sites.
Exam Focus: Know the numbers: 15 days after hire, OSHA-10 for workers, OSHA-30 for supervisors, the employer's suspend-or-terminate duty, and the $500 / $1,000 / willful fine schedule.
- Who Is Covered
- Construction Worker (NRS 618.957)
A construction worker is a person who actually performs physical work at a construction site that results in the construction, alteration or destruction involved in the project, including painting and decorating , or who supervises such work. A construction site is any location where construction work is being started or is in progress (NRS 618.953).
Excluded: Work done for the upkeep of an existing property that has a certificate of occupancy , to keep it in its original condition or operational soundness, including repairing components or replacing them with the same or similar components.
Typical covered trades include carpenters, framers, drywall installers and tapers, electricians, plumbers and pipefitters, masons and concrete finishers, ironworkers and welders, equipment operators, painters, and laborers, apprentices and helpers.
Supervisory Employee (NRS 618.967)
A supervisory employee has authority, in the employer's interest, to hire, transfer, suspend, lay off, recall, promote, discharge, assign, reward or discipline other employees, or responsibility to direct them, adjust their grievances, or effectively recommend those actions. The authority must require independent judgment , not routine or clerical action, and must occupy a significant portion of the workday . Foremen and superintendents who direct crews typically qualify.
Exemption
The construction card law does not apply to the Nevada Department of Transportation or its employees performing their duties (NRS 618.970).
The Card Requirements (NRS 618.983)
Who Course Deadline
Construction worker (not a supervisor) OSHA-10 : a 10-hour course in construction safety and health hazard recognition and prevention developed by federal OSHA (NRS 618.960) Completion card not later than 15 days after hire
Supervisory employee OSHA-30 : the 30-hour construction course Completion card not later than 15 days after hire
The course must be one the Division of Industrial Relations has approved (NRS 618.977). New hire on a Nevada construction site
- |
- +-- Supervisory employee? --> No --> OSHA-10 card within 15 days after hire
- | --> Yes --> OSHA-30 card within 15 days after hire
- |
- +-- Card not presented by day 15 --> employer must suspend or terminate (NRS 618.987)
- Course Content
The OSHA-10 construction course covers hazard recognition, with emphasis on the Focus Four : falls, struck-by, caught-in or -between, and electrocution. It also covers PPE and health hazards. The OSHA-30 course adds deeper coverage for supervisors, including safety program management, excavations, concrete and masonry, steel erection, cranes and rigging, and confined spaces.
Do Construction Cards Expire?
No expiration is set in the construction card statutes. NRS 618.983 requires workers and supervisors to obtain the card within 15 days after hire, and NRS 618.987 requires them to present a "current and valid" card. Neither the construction sections nor their definitions set an expiration period.
The 5-year expiration with renewal by a new course or continuing education (5 hours for OSHA-10, 15 hours for OSHA-30) appears in other Nevada card laws: the entertainment industry (NRS 618.9911) and convention services (NRS 618.9929). Do not carry those rules over to construction.
Trainers and the State Registry
Who May Teach: Only a trainer may provide OSHA-10 or OSHA-30 courses. For construction, that means a person authorized by federal OSHA, including someone who completed OSHA 500 , the trainer course for the construction industry (NRS 618.980).
Trainer Duties: Each trainer must register with the Division , display the trainer card where courses are taught, and report to the Division the name of each person who completes a course.
Public Registry: The Division keeps an online registry of trainers and of people who completed the courses, so anyone can verify a worker's completion (NRS 618.977). The registry's cost may not be charged to the workers.
Employer Duties (NRS 618.987)
Workers: If a construction worker who is not a supervisor fails to present a current and valid OSHA-10 card within 15 days after being hired , the employer shall suspend or terminate the worker.
Supervisors: If a supervisory employee fails to present a current and valid OSHA-30 card within 15 days after being hired , the employer shall suspend or terminate that person.
Best Practice: Check each card against photo ID, keep copies in the jobsite file, and track hire dates so no one works past day 15 without a card. On multi-employer sites, general contractors commonly require subcontractors to certify compliance.
Penalties (NRS 618.990)
If the Division finds that an employer failed to suspend or terminate an employee as NRS 618.987 requires:
- Violation Penalty
- First Administrative fine of not more than $500 , in place of any other penalty under Chapter 618
- Second Administrative fine of not more than $1,000 , in place of any other penalty
- Third and each later The penalty for a willful violation under NRS 618.635 (up to the federal willful maximum)
One Day, One Violation: Any number of violations discovered in a single day count as one violation.
Due Process: Before a fine is imposed, the Division must follow the citation procedures in Chapter 618, including notice and the chance to contest under NRS 618.475.
Licensing Consequences
Willful disregard of Nevada's safety laws is also a ground for NSCB discipline under NRS 624.3011(1)(b)(2) , so repeated safety-card violations can affect the contractor's license as well.
Exam Scenario: A carpenter is hired on May 10, 2026, for a Henderson commercial project. If the carpenter has no OSHA-10 card on file, the carpenter must obtain one within 15 days after hire. If no current, valid card has been presented by then, the employer must suspend or terminate the carpenter. An employer that fails to do so faces up to $500 for a first violation.