8.1 Project Planning, Work Breakdown Structures & Critical Path Method (CPM) Scheduling
Nevada General Contractor Exam
Track your progress as you read
Finished sections get a check mark.
1 Chapter 1: Nevada State Contractors Board & Licensing Law
1.1 Nevada Contractor Exams: CMS and Class B Trade Exam Format, Outline & References 1.2 NSCB Regulatory Framework, NRS 624 Scope & Contractor Definitions 1.3 License Classifications (A, B, C, AB) & Qualifying Party Requirements 1.4 License Maintenance, Biennial Renewal, Inactive Status & Business Changes
2 Chapter 2: Financial Limits, Bonding & Residential Recovery Fund
2.1 Monetary License Limits, Financial Statements & Limit Increases 2.2 Contractor Surety Bonds (NRS 624.270) & Cash Deposit Rules 2.3 Residential Recovery Fund (NRS 624.400–624.560): Eligibility, Assessments & Payouts
3 Chapter 3: Unlawful Conduct, Citations & Disciplinary Procedures
3.1 Unlawful Advertising, Unlicensed Contracting Penalties & Criminal Sanctions 3.2 Administrative Citations, Fines, Disciplinary Hearings & License Revocation
4 Chapter 4: Construction Contracts & Nevada Residential Disclosures
4.1 Essential Contract Elements, Agreement Types & Standard Construction Clauses 4.2 Nevada Residential Contract Requirements & Disclosures (NRS 624.520, 624.600 & 624.970) 4.3 Subcontractor Agreements, Flow-Down Provisions & Independent Contractor Status
5 Chapter 5: Change Orders, Prompt Payment & Dispute Resolution
5.1 Change Orders, Written Authorization Rules & Constructive Changes 5.2 Nevada Prompt Payment Law (NRS 624.606–624.630), Pay-If-Paid & Retention 5.3 Nevada Construction Defect Law (NRS Chapter 40) & Dispute Resolution
6 Chapter 6: Nevada Mechanics' Lien Law
6.1 Statutory Lien Rights, Property Subject to Lien & Excluded Work 6.2 Notice of Right to Lien (31-Day Coverage), Notice of Nonresponsibility & 15-Day Notice of Intent to Lien 6.3 Recording the Notice of Lien (90-Day Rule), Priority, Statutory Waivers & 6-Month Foreclosure Suits
7 Chapter 7: Estimating, Bidding Strategy & Public Works
7.1 Quantity Takeoff, Direct Costs, Material & Labor Estimating 7.2 Overhead Allocation, Profit Margins & Markup Calculations 7.3 Competitive Bidding Strategy, Public Works Bidding (NRS 338) & Bid Bonds
8 Chapter 8: Project Management, CPM Scheduling & Quality Control
8.1 Project Planning, Work Breakdown Structures & Critical Path Method (CPM) Scheduling 8.2 Jobsite Logistics, Submittals, Daily Logs & Progress Tracking 8.3 Quality Control, Building Inspections, Warranties & Project Closeout
9 Chapter 9: Nevada Safety, NVOSHA & Mandatory Safety Cards
9.1 Nevada OSHA (NVOSHA) Framework, Inspections, Citations & Recordkeeping 9.2 Nevada Mandatory 10-Hour & 30-Hour Construction Safety Cards (NRS 618.983) 9.3 Personal Protective Equipment, Hazard Communication & Environmental Health Hazards
10 Chapter 10: Construction Site Safety, Excavation & Nevada One Call
10.1 Fall Protection, Scaffolding & Ladder Safety (29 CFR 1926 Subparts L, M, X) 10.2 Excavation, Trenching, Soil Classification & Shoring (29 CFR 1926 Subpart P) 10.3 Nevada One Call / USA North 811 & Underground Utility Damage Prevention
11 Chapter 11: Risk Management, Insurance & Construction Bonds
11.1 Commercial General Liability (CGL) & Builder's Risk Insurance 11.2 Nevada Workers' Compensation (NRS 616A–616D Industrial Insurance) 11.3 Construction Surety Bonds: Bid, Performance, Payment & Maintenance Bonds
12 Chapter 12: Construction Accounting, Financial Analysis, Taxes & Labor Law
12.1 Construction Accounting Methods: Cash, Accrual & Percentage of Completion 12.2 Financial Statements, Balance Sheet Ratios & Cash Flow Management 12.3 Federal & Nevada State Taxes: FICA, FUTA, MBT, Commerce Tax & Sales/Use Tax 12.4 Nevada & Federal Labor Laws: Minimum Wage, Overtime, Final Pay & Paid Leave
13 Chapter 13: Building Codes, Plan Reading & Sitework
13.1 Building Codes (IBC/IRC), Permits & Inspection Sequence 13.2 Architectural & Structural Plan Reading, Scale & Symbol Conventions 13.3 Sitework, Grading, Soil Mechanics & Foundation Layout
14 Chapter 14: Concrete, Masonry & Metals
14.1 Concrete Materials, Field Testing, Formwork & Reinforcing Steel 14.2 Concrete Placement, Finishing, Joints, Curing & Post-Tensioning 14.3 Masonry: CMU, Mortar, Grout, Veneer & Wall Bracing 14.4 Structural Steel, Bolting, Welding, Joists, Light-Gauge Framing & Subpart R
15 Chapter 15: Carpentry, Thermal & Moisture Protection, Openings & Finishes
15.1 Wood Framing & Carpentry: Lumber, Engineered Wood, Anchorage & Shear Walls 15.2 Thermal & Moisture Protection: WRBs, Stucco, Insulation, Vapor Control & Roofing 15.3 Doors, Windows & Hardware: Fire Doors, Accessibility, Glazing & Flashing 15.4 Drywall & Finishes: Gypsum Board, GA-214 Levels, Ceilings, Tile & Paint
8.1 Project Planning, Work Breakdown Structures & Critical Path Method (CPM) Scheduling
Key Takeaways Explain This Topic AI
The Work Breakdown Structure (WBS) decomposes the total project scope down to distinct, deliverable-oriented work packages, adhering strictly to the 100% Rule where no scope is omitted or duplicated.
While bar charts (Gantt charts) provide clear visual schedules for executive presentations, only logic network schedules mathematically calculate dependencies, early/late dates, float, and the critical path.
Total Float ( T F = L S − E S = L F − E F TF = LS - ES = LF - EF TF = L S − ES = L F − EF ) measures scheduling flexibility without delaying overall project completion, whereas Free Float ( F F = min ( E S successors ) − E F FF = \min(ES_{\text{successors}}) - EF FF = min ( E S successors ) − EF ) measures flexibility without delaying any immediate successor.
The Critical Path consists of the continuous sequence of activities with zero (or negative) total float; any delay to a critical path activity directly delays the project completion date.
Schedule crashing compresses project duration by adding resources to critical path activities with the lowest cost slope ( ( Crash Cost − Normal Cost ) / ( Normal Time − Crash Time ) (\text{Crash Cost} - \text{Normal Cost}) / (\text{Normal Time} - \text{Crash Time}) ( Crash Cost − Normal Cost ) / ( Normal Time − Crash Time ) ), while fast-tracking performs sequential activities concurrently at higher risk of rework.
Last updated: September 2026
Project Planning Hierarchy and Strategic Scheduling
Effective construction project management begins long before ground is broken. In the commercial and residential construction sectors, project planning is the systematic process of defining scope, determining resource requirements, allocating trade responsibilities, and establishing temporal constraints. A disciplined planning framework prevents cost overruns, trade stacking, jurisdictional disputes, and project delays.
Project scheduling translates planning into an actionable, time-phased execution model. Within professional contracting operations, scheduling functions at four distinct hierarchical levels:
Executive Milestone Schedule (Level 1): High-level summary schedule prepared for owners, developers, lenders, and corporate executives. Highlights major project milestones such as site possession, groundbreaking, foundation completion, structural topping-out, building dry-in, substantial completion, and final occupancy.
Master Production Schedule (Level 2): Integrated baseline schedule incorporating all prime contract scopes, major procurement timelines, submittal approval cycles, and key jurisdictional inspection gates.
Look-Ahead Schedule (Level 3): Rolling operational schedule (typically spanning 3 to 6 weeks ) managed by project managers and superintendents. Used in weekly subcontractor coordination meetings to manage trade handoffs, verify material deliveries, and resolve site access conflicts.
Short-Interval Production Schedule / Daily Work Plan (Level 4): 1- to 2-week daily task schedule managed by trade foremen and superintendents, assigning specific craft crews, equipment, and tasks to defined physical work areas.
Work Breakdown Structure (WBS) Decomposition
A Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish project objectives and create the required deliverables. It organizes and defines the total scope of the project, dividing broad project deliverables into progressively smaller, more manageable components. Level 1: Total Project Scope (e.g., Commercial Medical Office Building)
- │
- ├── Level 2: Subproject / Phase (e.g., Substructure & Core)
- │ │
- │ ├── Level 3: Work Package (e.g., Cast-in-Place Concrete Foundation)
- │ │ │
- │ │ └── Level 4: Activities / Tasks (e.g., Excavate Footings, Place Rebar, Pour Concrete)
- The 100% Rule
The fundamental governing principle of WBS design is the 100% Rule . The WBS must encompass 100% of the work defined by the project scope and capture all deliverables—internal, external, and interim. The rule applies across all levels of the hierarchy:
The sum of the work at the "child" level must equal 100% of the work represented by the "parent" level.
The WBS must not include any work that falls outside the actual contract scope (0% scope creep).
Elements must be mutually exclusive; no scope overlap or duplication can exist between sibling packages.
Defining the Work Package
A Work Package represents the lowest level of the WBS before decomposing into detailed scheduling activities. A properly formulated work package possesses specific operational attributes:
Deliverable-Oriented: Results in a measurable, verifiable physical product or milestone.
Single Accountability: Assigned to a single designated subcontractor, superintendent, or trade foreman.
Resource and Cost Identifiable: Directly measurable in terms of labor hours, material costs, equipment usage, and subcontracts.
Manageable Duration: Typically spans an 80-hour threshold or one to two weeks of field execution, preventing unmonitored scope drift.
The WBS Dictionary
Accompanying the WBS hierarchy is the WBS Dictionary , a formal document that provides detailed narrative descriptions of each component. It defines the technical boundaries, milestones, deliverable specifications, required materials, quality control standards, and contract references for every work package, ensuring that subcontractors and estimators possess identical interpretations of package scope.
Bar Charts (Gantt Charts) vs. Logic Network Schedules
Contractors utilize two primary visual mediums for scheduling construction work: Gantt bar charts and logic network diagrams. Understanding their operational distinctions and analytical limitations is essential for licensing examinations.
Scheduling Feature Bar Chart (Gantt Chart) Logic Network Schedule (CPM)
Visual Clarity Excellent; highly intuitive for owners, lenders, and craft labor Complex; requires training to interpret node logic and float networks
Dependency Logic Minimal or hidden; bar movements do not automatically update dependent tasks Explicit; mathematically links predecessor and successor relationships
Critical Path Identification Cannot reliably determine the critical path Mathematically calculates the critical path via forward/backward passes
Float Calculation Cannot calculate Total Float or Free Float Computes exact Total Float and Free Float for every activity
Delay Analysis Inadequate for forensic delay claims or time impact analysis Industry standard for evaluating delay claims, compensability, and time extensions
Updating Dynamic Manual adjustment of bars; fails to show cascading effects Dynamic recalculation; changing one duration updates all successor dates
While a Gantt chart is effective for executive presentations and field notice boards, it is dangerous as a sole control tool on complex projects because it fails to reveal how an isolated delay in one activity affects downstream milestones.
Critical Path Method (CPM) Fundamentals: AON vs. AOA
The Critical Path Method (CPM) is a deterministic mathematical modeling technique developed in the late 1950s by the DuPont Corporation and Remington Rand. Unlike probabilistic methods such as Program Evaluation and Review Technique (PERT)—which uses three duration estimates (optimistic, most likely, pessimistic)—CPM relies on single, deterministic duration estimates derived from empirical labor production rates and quantity takeoffs.
Network Conventions: AON vs. AOA
Historically, CPM schedules were constructed using two distinct graphic conventions:
Activity-on-Arrow (AOA / Arrow Diagramming Method - ADM): Arrows represent activities requiring time and resources, while circular nodes represent milestone events (start or completion points). AOA networks cannot easily accommodate complex lead/lag logic and frequently require "dummy activities" (dashed arrows with zero duration and zero cost) simply to maintain logical integrity and unique node identification.
Activity-on-Node (AON / Precedence Diagramming Method - PDM): Rectangular nodes represent activities, while lines or arrows represent logical relationships (dependencies). AON has completely superseded AOA in modern construction project management software (such as Primavera P6 and Microsoft Project) due to its superior flexibility and ability to handle advanced dependency relationships.
Standard AON Node Anatomy
CPM practice problems commonly use this Activity-on-Node box layout: ┌───────────────────┬────────────────────┬───────────────────┐
- │ Early Start (ES) │ Duration (D) │ Early Finish (EF) │
- ├───────────────────┴────────────────────┴───────────────────┤
- │ Activity ID & Description │
- ├───────────────────┬────────────────────┬───────────────────┤
- │ Late Start (LS) │ Total Float (TF) │ Late Finish (LF) │
- └───────────────────┴────────────────────┴───────────────────┘
Early Start (ES): The earliest possible calendar point in time an activity can commence, based on network logic and completion of all predecessors.
Duration (D): The estimated working time required to complete the activity using planned labor and equipment resources.
Early Finish (EF): The earliest possible calendar point in time an activity can finish.
Late Start (LS): The latest possible calendar point an activity can begin without delaying the overall contracted project completion date.
Late Finish (LF): The latest possible calendar point an activity can finish without delaying the overall contracted project completion date.
Total Float (TF): The amount of time an activity can be delayed without delaying the project completion date.
Forward Pass and Backward Pass Calculations
Determining activity early dates, late dates, float values, and the critical path requires two sequential mathematical passes through the network: the Forward Pass and the Backward Pass . [START] ──► Forward Pass (Calculates ES and EF; drives left-to-right)
- │
- ▼
- Determines Minimum Project Duration
- │
- [FINISH] ◄── Backward Pass (Calculates LF and LS; drives right-to-left)
- The Forward Pass: Determining Early Dates
The forward pass proceeds chronologically from the initial project milestone to the final activity. Using the standard end-of-day convention (where Day 0 represents the start of work):
Initial Activity: For the starting activity, E S = 0 ES = 0 ES = 0 .
Early Finish Formula: For any activity: E F = E S + Duration EF = ES + \text{Duration} EF = ES + Duration
Convergence (Merge Points): When an activity has multiple immediate predecessors, its Early Start is governed by the maximum Early Finish of those predecessors: E S = max ( E F predecessors ) ES = \max(EF_{\text{predecessors}}) ES = max ( E F predecessors ) Rule: A successor cannot begin until all of its required predecessors have finished.
The Backward Pass: Determining Late Dates
The backward pass proceeds in reverse chronological order from the final project activity back to the starting milestone:
Project Finish Activity: For the final activity, the Late Finish is set equal to its Early Finish (or the mandatory contract completion date): L F project = E F project LF_{\text{project}} = EF_{\text{project}} L F project = E F project
Late Start Formula: For any activity: L S = L F − Duration LS = LF - \text{Duration} L S = L F − Duration
Divergence (Burst Points): When an activity has multiple immediate successors, its Late Finish is governed by the minimum Late Start of those successors: L F = min ( L S successors ) LF = \min(LS_{\text{successors}}) L F = min ( L S successors ) Rule: An activity must finish in time to accommodate the most urgent successor's late start.
Float Analysis: Total Float vs. Free Float
Float (or slack) quantifies scheduling flexibility. In construction management, float is a critical asset that governs risk allocation, delay dispute negotiations, and resource leveling.
1. Total Float (TF)
Total Float is the total amount of time an activity can be delayed from its early start date without delaying the contracted project completion date (or violating a mandatory completion milestone).
Total Float ( T F ) = L S − E S = L F − E F \text{Total Float} (TF) = LS - ES = LF - EF Total Float ( TF ) = L S − ES = L F − EF
Zero Float ( T F = 0 TF = 0 TF = 0 ): The activity is critical. Any delay will immediately delay project completion.
Positive Float ( T F > 0 TF > 0 TF > 0 ): The activity has flexibility; it can absorb delays up to the float value without delaying completion.
Negative Float ( T F < 0 TF < 0 TF < 0 ): Occurs when an external contractual deadline or imposed milestone is earlier than the calculated early finish date. Indicates the project is currently trending behind schedule.
2. Free Float (FF)
Free Float is the amount of time an activity can be delayed without delaying the Early Start of any immediate successor activity.
Free Float ( F F ) = min ( E S successors ) − E F \text{Free Float} (FF) = \min(ES_{\text{successors}}) - EF Free Float ( FF ) = min ( E S successors ) − EF
Free Float is "owned" exclusively by the activity; consuming free float has zero impact on downstream activities.
Total Float is shared along an entire network path. Consuming total float on an early activity reduces the available float for all subsequent activities on that chain.
Mathematically, Free Float can never exceed Total Float: F F ≤ T F FF \le TF FF ≤ TF .
3. Interfering Float
Interfering Float is the difference between Total Float and Free Float:
Interfering Float = T F − F F \text{Interfering Float} = TF - FF Interfering Float = TF − FF
It represents the portion of total float that, if consumed by delaying the activity, will delay the early start of downstream successors without delaying the overall project completion date.
Identifying the Critical Path
The Critical Path is defined by three interrelated rules:
It is the longest continuous sequence of activities from project start to project finish.
It represents the shortest possible time required to complete the total project.
It consists of activities that possess zero Total Float ( T F = 0 TF = 0 TF = 0 ) (or the minimum float in a network with negative float).
Exam Key: A project network may have more than one critical path operating in parallel. When multiple critical paths exist, project management risk increases significantly because a delay on either path delays the overall project.
Activity Dependency Logic and Lead/Lag Durations
In modern Precedence Diagramming Method (PDM) scheduling, dependencies between activities are modeled using four primary relationship types: 1. Finish-to-Start (FS): [ Activity A ] ──────────► [ Activity B ]
(Most common)
- 2. Start-to-Start (SS): [ Activity A ]
- │ (SS + Lag)
- ▼
- [ Activity B ]
- 3. Finish-to-Finish (FF): [ Activity A ]
- │ (FF + Lag)
- ▼
- [ Activity B ]
- 4. Start-to-Finish (SF): [ Activity A ] ──(SF)──► [ Activity B ] (Rare)
- 1. Finish-to-Start (FS)
The standard, most common relationship in construction (>90% of all network ties). Activity B cannot commence until Activity A has completely finished.
Example: Activity A: "Erect Structural Steel" → \rightarrow → (FS) → \rightarrow → Activity B: "Install Metal Roof Decking".
2. Start-to-Start (SS)
Activity B cannot start until Activity A has started. Commonly used to model phased or staggered operations where successive trades work concurrently.
Example: Activity A: "Trench Utility Line" → \rightarrow → (SS with 2-day Lag) → \rightarrow → Activity B: "Lay Pipe in Trench". Pipe laying can commence two days after trenching begins.
3. Finish-to-Finish (FF)
Activity B cannot finish until Activity A has finished. Frequently used when two concurrent tasks must conclude simultaneously or in close sequence.
Example: Activity A: "Rough Electrical Installation" → \rightarrow → (FF with 1-day Lag) → \rightarrow → Activity B: "In-Wall Inspection". The inspection cannot conclude until the rough wiring is 100% finished.
4. Start-to-Finish (SF)
Activity B cannot finish until Activity A has started. This is rare in physical construction and typically restricted to just-in-time material supply or security shift handovers.
Lags and Leads
Lag: A mandatory delay inserted between a predecessor and successor. A positive lag shifts the successor forward in time. For example, a FS + 7-day Lag between pouring concrete footings and structural steel erection represents mandatory concrete curing time.
Lead (Negative Lag): An acceleration where a successor begins before its predecessor is completely finished. For instance, FS - 2-day Lead allows the successor to start two days prior to predecessor completion.
Schedule Compression Methods: Crashing vs. Fast-Tracking
When a project falls behind schedule or the owner demands an accelerated completion date, project managers must compress the schedule. The two recognized compression techniques are Crashing and Fast-Tracking .
Compression Feature Crashing Fast-Tracking
Mechanism Adding direct resources (overtime, extra crews, larger equipment, expedited freight) to critical activities Reconfiguring sequential critical activities to run concurrently (in parallel)
Cost Impact Increases direct project costs significantly Minimal direct labor cost increase, but potential major rework costs
Risk Profile Low-to-moderate risk; execution sequence remains standard High risk; increases probability of trade conflicts, coordination errors, and rework
Application Rule Applied strictly to critical path activities with the lowest cost slope Applied to critical path activities that can logically overlap without structural conflict
Crashing Mechanics and the Cost Slope Formula
When crashing a schedule, you must only crash activities on the critical path . Crashing a non-critical activity incurs additional cost without shortening the overall project duration by a single day.
When multiple critical activities exist, the scheduler must select the activity that provides the maximum time reduction at the lowest financial expense. This is evaluated using the Cost Slope :
Cost Slope = Crash Cost − Normal Cost Normal Duration − Crash Duration = Δ Cost Δ Time \text{Cost Slope} = \frac{\text{Crash Cost} - \text{Normal Cost}}{\text{Normal Duration} - \text{Crash Duration}} = \frac{\Delta \text{Cost}}{\Delta \text{Time}} Cost Slope = Normal Duration − Crash Duration Crash Cost − Normal Cost = Δ Time Δ Cost
The Law of Diminishing Returns in Crashing
Project managers must be cautious of over-crashing . Adding excessive labor or working continuous 60-hour weeks leads to trade stacking (spatial congestion), increased safety incidents, fatigue, and diminishing marginal productivity, where adding 20% more labor may yield only a 5% increase in production output.
Worked Numerical CPM Example
Consider a commercial sitework and foundation scope consisting of seven sequential activities:
- Activity ID Description Duration (Days) Predecessors
- A Clear & Grub Site 4 None
- B Site Rough Grading 6 A
- C Excavate Building Footings 5 A
- D Install Underground Utilities 7 B
- E Construct Retaining Wall 3 B
- F Form & Place Rebar in Footings 6 C
- G Pour Concrete Footings & Slab 4 D, F
- Step 1: Forward Pass Calculations
Activity A: E S = 0 ES = 0 ES = 0 ; E F = 0 + 4 = 4 EF = 0 + 4 = 4 EF = 0 + 4 = 4 .
Activity B: Predecessor A ( E F = 4 EF = 4 EF = 4 ). E S = 4 ES = 4 ES = 4 ; E F = 4 + 6 = 10 EF = 4 + 6 = 10 EF = 4 + 6 = 10 .
Activity C: Predecessor A ( E F = 4 EF = 4 EF = 4 ). E S = 4 ES = 4 ES = 4 ; E F = 4 + 5 = 9 EF = 4 + 5 = 9 EF = 4 + 5 = 9 .
Activity D: Predecessor B ( E F = 10 EF = 10 EF = 10 ). E S = 10 ES = 10 ES = 10 ; E F = 10 + 7 = 17 EF = 10 + 7 = 17 EF = 10 + 7 = 17 .
Activity E: Predecessor B ( E F = 10 EF = 10 EF = 10 ). E S = 10 ES = 10 ES = 10 ; E F = 10 + 3 = 13 EF = 10 + 3 = 13 EF = 10 + 3 = 13 .
Activity F: Predecessor C ( E F = 9 EF = 9 EF = 9 ). E S = 9 ES = 9 ES = 9 ; E F = 9 + 6 = 15 EF = 9 + 6 = 15 EF = 9 + 6 = 15 .
Activity G: Predecessors D ( E F = 17 EF = 17 EF = 17 ) and F ( E F = 15 EF = 15 EF = 15 ). Convergence rule applies: E S = max ( 17 , 15 ) = 17 ES = \max(17, 15) = 17 ES = max ( 17 , 15 ) = 17 ; E F = 17 + 4 = 21 EF = 17 + 4 = 21 EF = 17 + 4 = 21 .
Total Project Duration = 21 Working Days.
Step 2: Backward Pass Calculations
Activity G: L F = 21 LF = 21 L F = 21 ; L S = 21 − 4 = 17 LS = 21 - 4 = 17 L S = 21 − 4 = 17 .
Activity E: Terminal activity (no successors). L F = 21 LF = 21 L F = 21 ; L S = 21 − 3 = 18 LS = 21 - 3 = 18 L S = 21 − 3 = 18 .
Activity D: Successor G ( L S = 17 LS = 17 L S = 17 ). L F = 17 LF = 17 L F = 17 ; L S = 17 − 7 = 10 LS = 17 - 7 = 10 L S = 17 − 7 = 10 .
Activity F: Successor G ( L S = 17 LS = 17 L S = 17 ). L F = 17 LF = 17 L F = 17 ; L S = 17 − 6 = 11 LS = 17 - 6 = 11 L S = 17 − 6 = 11 .
Activity B: Successors D ( L S = 10 LS = 10 L S = 10 ) and E ( L S = 18 LS = 18 L S = 18 ). Divergence rule applies: L F = min ( 10 , 18 ) = 10 LF = \min(10, 18) = 10 L F = min ( 10 , 18 ) = 10 ; L S = 10 − 6 = 4 LS = 10 - 6 = 4 L S = 10 − 6 = 4 .
Activity C: Successor F ( L S = 11 LS = 11 L S = 11 ). L F = 11 LF = 11 L F = 11 ; L S = 11 − 5 = 6 LS = 11 - 5 = 6 L S = 11 − 5 = 6 .
Activity A: Successors B ( L S = 4 LS = 4 L S = 4 ) and C ( L S = 6 LS = 6 L S = 6 ). Divergence rule applies: L F = min ( 4 , 6 ) = 4 LF = \min(4, 6) = 4 L F = min ( 4 , 6 ) = 4 ; L S = 4 − 4 = 0 LS = 4 - 4 = 0 L S = 4 − 4 = 0 .
Step 3: Float and Critical Path Determination
Activity Duration ES EF LS LF Total Float ( L S − E S LS - ES L S − ES ) Free Float ( min ( E S succ ) − E F \min(ES_{\text{succ}}) - EF min ( E S succ ) − EF ) Critical?
- A 4 0 4 0 4 0 min ( 4 , 4 ) − 4 = 0 \min(4, 4) - 4 = 0 min ( 4 , 4 ) − 4 = 0 YES
- B 6 4 10 4 10 0 min ( 10 , 10 ) − 10 = 0 \min(10, 10) - 10 = 0 min ( 10 , 10 ) − 10 = 0 YES
- C 5 4 9 6 11 2 9 − 9 = 0 9 - 9 = 0 9 − 9 = 0 NO
- D 7 10 17 10 17 0 17 − 17 = 0 17 - 17 = 0 17 − 17 = 0 YES
- E 3 10 13 18 21 8 21 − 13 = 8 21 - 13 = 8 21 − 13 = 8 NO
- F 6 9 15 11 17 2 17 − 15 = 2 17 - 15 = 2 17 − 15 = 2 NO
- G 4 17 21 17 21 0 21 − 21 = 0 21 - 21 = 0 21 − 21 = 0 YES
The Critical Path is: A → \rightarrow → B → \rightarrow → D → \rightarrow → G (Duration: 21 Days).